***, male, 39 years old, member of the Communist Party of China, ** Provincial People's Canal Second Management Office ** Power Station Deputy Station Manager. In July 198, he graduated from the Ministry of Water Resources and Electric Power School in the same year. In the same year, he was assigned to work in our department. In 199* years*, he obtained a bachelor's degree in electrical system and automation from Wuhan University of Water Resources and Electric Power. In 199* years*, he was appointed as a power professional. Engineer; in 2003, he obtained the professional certificate of foreign language exam*, and obtained the certificate of Class A for the computer test in 200* years; the results of the 200* to 200* annual assessment are all competent. In 200* years, it was awarded the title of “Employees with outstanding contributions” by our office.
2. Political Thoughts The comrades supported the party's line, principles, and policies, earnestly studied Deng Xiaoping Theory, worked hard to implement the important thinking of the "three represents," and constantly improved their political and ideological qualities. In the work, you can lead by example and perform your job duties without any compromise; have a rigorous, meticulous and realistic work style, master the professional theoretical knowledge and technology in a long-term practical work, and be flexible in your work. Applying, with rich practical experience and ability to solve complex technical problems, has made outstanding contributions to the production management of our power station.
Third, engaged in professional and technical work and achievements Since the comrade took part in the work, he has been engaged in power plant production technology and management. In addition to doing a good job in the daily production technology management of the power station, he also led the completion of many overhaul and technical transformation work of the power station, and It also often helps the fraternal units and external units to solve technical problems, and has achieved outstanding results, and has been unanimously affirmed both internally and externally. Its main work performance is:
1. Participated in the overhaul of the butterfly valve of No. 1 machine of Galaxy Power Station.
2. Participated in the replacement of the thrust tile of the 1250KW unit of the Galaxy Power Station.
3. Presided over the transformation of the water guiding mechanism of the 1250KW unit of Yinhe Power Station.
4. Presided over the transformation of the main valve operating mechanism of the 1250KW unit of Yinhe Power Station.
5. Participated in the technical transformation of the oil cooler on the 3200kw unit of Yinhe Power Station.
6. Participated in the technical transformation of the 1250KW turbine runner of Yinhe Power Station and presided over the replacement of the new runner bottom.
7. Presided over the technical transformation of the 3200KW generator excitation system of Yinhe Power Station.
8. Participated in the installation of two 3600KW hydroelectric generating units of Xinghuo Power Station.
9. Participated in the replacement of the main valve of the Xinghuo Power Station.
10. Participated in the work of the first water machine of the Xinghuo Power Station.
11. Participated in the design of the electrical part of the paper trough power station and presided over the installation and commissioning of the generator set.
12. Completed the design work of the electromechanical part of Chengbei Power Station independently, and presided over the installation and commissioning of electromechanical equipment.