Biotechnology Department work summary and work plan
A brief review of work in 2019
First, the basic situation of the power grid
Basic condition of equipment
As of November 30, 2019, the company has 18 substations of 35kv and above, with a total capacity of 209.65mva, an increase of 21.07% over the same period of last year. The comprehensive automation commission rate is 38.9%. There are more than 17 oil circuit breakers for 35kv circuit breakers. The rate of conversion is 75.71%, 26 sets of 10kv less oil circuit breakers, the oil-free rate is 75.7%, the main transformer has a load regulation rate of 40.9%; the 35kv and above transmission lines are 28, 385km, an increase of 5%; the hydropower station , the total capacity of 2 × 1600kw;
Equipment failure and analysis
System operation status
The grid voltage changes with the seasons and time, especially in the dry season, the output of the power station decreases, the grid voltage is obviously low, and the voltage at the tail end is seriously low. The main reason is that the grid structure is unreasonable, and a transmission line covers the new 80. The rural network of only one is supported by only one 110kv substation, and the grid voltage is completely dominated by the output of the power station.
The grid current has experienced severe imbalances many times, which directly affects the power generation of the power station and the user's power consumption, and even causes a false signal of relay protection. The main reason: the design of high-energy plants and mines is unreasonable, the operation is not standardized, and the equipment maintenance is not in place, resulting in a serious imbalance of power consumption.
, the operation status of substation equipment
Main transformer and arc suppression coil failure 4 times; circuit breaker failure 15 times, of which 3 times of lightning damage, 7 times of mechanism failure, 5 times of oil failure of multi-oil circuit breaker; 11 sets of isolation switch fault; current 5 transformer failures; 6 faults in equipment clamps; 7 failures in protection and automation equipment; 3 failures in DC systems. The main reason: some equipment is seriously aging, the quality of new equipment is poor, lightning protection measures are poor, design and construction are not carried out according to requirements, countermeasures are not implemented enough, daily maintenance is not in place, and so on.
Line operation status
Line faults 31 times, its interruption line failure 7 times, porcelain bottle breakdown 18 times, cable reinforcement 5 times, pole base collapse 1 out; 110kv line trip 3 times, the main reason for trip is 110kv bus pt fast disconnection of substation The device tripped once, the device parameter setting caused 2 times; the 35kv trip 81 times tripped.
Second, the completion of each indicator
Maintenance management work
, maintenance planning and management to a new level
1 The “Measures for the Management of New Power Company Maintenance Plans” was issued, and the principles of maintenance planning were formulated, and the principle of “no plan to stop” was adhered to. The seriousness of the management of the maintenance plan was guaranteed, and the inspection rate dropped from 70.4% to 29.3%.
2 Strengthened maintenance quality management and effective control before operation. In line with the principle of “repairing must be repaired”, we will continue to improve the quality system, strictly overhaul the process, and strengthen process management and control. At the same time, we will increase acceptance management, improve the acceptance process, emphasize the inspection and control efforts, and strengthen the principle of “who is responsible for who is responsible”.
3 Pay attention to the construction site to ensure construction safety. "Personal safety" is one of our company's "two bottom lines" this year. In the past year, the Ministry of Biotechnology has attached great importance to the safety of the job site, strictly implemented various safety measures and operating procedures, and increased the intensity of on-site checks.
4 Strengthen emergency treatment, improve emergency response capability, and reduce power outage time. This year, the lightning is serious, some equipment is seriously aging, and the equipment is particularly damaged. The maintenance personnel are not affected by the day or the night, regardless of whether it is sunny or rainy. It still arrives at the scene of the accident at one time and quickly handles it, ensuring the stability of the power supply and improving the stability. The company's economic and social benefits, the total number of repairs throughout the year reached 103 times. Especially in the flood fighting and rescue, they have rescued 15 times. On June 8th, there were 5 rescue sites, heavy rain and inconvenient traffic. They took a few kilometers on the tools and materials. It was dark and did not give up. Until the power supply was normal, but it was late at night, but there was no complaint.
2, grasp the implementation, the maintenance task was successfully completed
Overhaul the technical improvement. In 2019, the Ministry of Biotechnology was responsible for 18 technical transformation and overhaul projects, with a total investment of 2.082 million yuan. After efforts, so far, 15 major overhaul technical transformation projects have been basically completed; 3 projects have not been completed, mainly due to the late start, plus the addition of highways and high-speed rail construction and electricity projects, the materials are not in place.
Completion of anti-accident measures
In the 135kv system capacitor current rectification, a new arc suppression coil was added in the furnace change. One direct grounding of all 35kv busbar pt and 10kv busbar pt in the system was changed to 30 grounding via harmonic elimination device.
2 The gap of the 110kv neutral point of the furnace change 1# and 2# main transformer was replaced.
3 Replace the 43 sets of current transformers for protection; at the same time, put some of the recloseable switching devices into operation.
4 Replaced the three sets of batteries of Baixi and Shenzhen.
5 Replaced the 110kv furnace observation microcomputer anti-misoperation device.
6 timely adjusted the main changes in the near-zone change of Pingxi, Jinfeng, Baixi, Zhenshang and Shuangjiangkou power stations, and at the same time transformed the near-zone change protection of Shuangjiangkou Hydropower Station to ensure normal power order. To ensure the safe and reliable operation of the equipment.
7 Completed and replaced all the “three cards” of 35kv and above transmission lines.
8 pairs of water lines 6 sets of routes, 118 sets of white lines for furnace travel, 48 sets of pull lines for furnace double water lines, 6 sets of pull lines for Yangji line and 3 sets of pull lines for cross antennas were replaced.
9 pairs of 110kv tour line towers were clearly connected, and the grounding lines of 70 35kv lines of overhead ground lines were reconstructed; 14 lines were installed in horizontal lines, Wenping lines, furnace double water lines, horizontal antennas and furnace lines. Set the line arrester, ground lead wire to conduct, re-install the grounding device.
10 outside Wenping Line 51# rod straight pole position resistance.
11 A 10kv line reactive power compensation device was installed in the Wentang Line and the Chetian Line, and the reactive power compensation device for the 10kv line of Pingxi was relocated.
12 Change the electro-hydraulic control of the 1# unit governor of Chenguang Power Station to plc control, which greatly improves the reliability of start-stop.
13 pairs of 110kv furnace observation, 35kv Hengyang change, Wentang change, Jiqing change and Yangxi change production area were replaced; at the same time, the duty room of all substations was cleaned.
14 Replace the insulation of 5 multi-circuit breakers such as Jiqing, Waterwheel, Baixi and Hengyang.
Routine maintenance and repair work
1 Completed the preventive maintenance work of two conventional substations in Hengyang and Baixi.
2 Completed 103 repair tasks, items, 35kv lines, 36 parts of the power-changing part 67, ensuring the healthy operation of the equipment, the emergency defect elimination rate reached 100%; 11 major defects, 9 elimination, the elimination rate reached 82 %.
3 The main network faces a serious test, replacing 3 porcelain bottles, 2 broken wire treatments, 2 wire drawing treatments, and 1 dismantling bar.
New construction project
1 The completion of the installation of Wentang changed two 10kv line intervals.
2 After the completion of Jinfeng, two 35kv line intervals and one 10kv line interval were installed.
3 Completed the installation of Jiqing to 10kv line interval.
4 The completion of Yangxi changed to a 35kv line interval and three 10kv line spacing installation.
5 completed the installation of 35kv Ronghua.
6 Completed the demolition of the 35kv expressway line 12 times.
7 Complete the 6.5km of the 35kv new line artichoke line and 5km of the 琅 antenna.
Seasonal work
1 Carry out the peak summer work in an all-round way, take effective measures to suppress the system voltage and the current imbalance, and ensure the safe and stable operation of the power grid.
2 Completely repair the antifreeze and ice melting of the furnace change, the Qiangtang change, the Baixi change and the Jiqing change, and the overhaul of the antifreeze and ice melting equipment to ensure the smooth progress of the winter.
Other jobs
1 The company's 2019 overhaul technical transformation project was compiled.
2 Increase system high-voltage line loss management and take effective measures to reduce line loss.
3 Increase power supply reliability management, take effective measures to reduce the number of line trips and improve the availability of equipment
Transmission line management
1. Strengthen the management of basic work: formulate a six-proof work plan for transmission lines, and establish a line six-proof account.
2, do a good job of daily line inspection maintenance management and good acceptance. Completed the acceptance of the highway and high-speed rail line demolition project, completed the acceptance of the 35kv new line, the Fengfan Line, the Yangshuo Line, and the Changping Line, Pingxiao Line and Bachang Line, and completed the 110kv tour line channel deforestation, 35kv water On the line, a 10-day greening obstacle was carried out.
4. Pay close attention to safe production, ensure that no personal injury or death occurred, and no downturn occurred.
5, in order to reduce the line trip and prevent the reversal of the pole as the goal, pay close attention to the implementation of the overhaul technical transformation project and quality acceptance.
Scheduling management work
1. Grid operation index
By November 30, 2019, our company had completed a total of 28232kwh of power supply, 100% pass rate of 110kv, 86.36% of 35kv bus voltage, and 95.45% of 10kv bus voltage.
2. Safety production management
Safety production management objectives have been set so that everyone can define their own safety responsibilities. Strictly implement safety procedures and resolutely put an end to the phenomenon of no ticketing. Before the operation of the switchover, the operation ticket was carefully filled out. By November 30, 2019, a total of 1758 dispatched operation tickets were dispatched, and the pass rate was 100%.
3. Grid economic operation
Strictly implement maintenance planning management. From July to December, 439 projects were planned and overhauled, 221 projects were overhauled, 141 were temporarily overhauled, 43 were overhauled, and 64 were overhauled. The implementation rate was 47.1%, and the temporary implementation rate was 34.8%. 432 maintenance tickets were completed, the completion rate was 92.1% on time, 37 tickets were postponed, and the maintenance ticket extension rate was 7.9%.
Operation management work
1. In accordance with the principle of “three no harms”, prevent the occurrence of misoperations, strictly implement the operation control system, and carry out standardization operations according to the on-site training requirements of the municipal bureau. Therefore, no misoperations have occurred throughout the year to ensure normal production.
2. In combination with the on-site training and skill appraisal test of the Municipal Bureau, four training courses were held for the operating personnel, and the field simulation operation was carried out in conjunction with the equipment of the Qiangtang transformer. The effect was very obvious.
3. Strictly grasp the management of the five anti-locking devices, comprehensively cleaned up and perfected the locking devices of the substations, and carried out the computer-based transformation of the 110kv furnace observation and locking device and the modification of the live locking device in the Chenguang power plant.
4. Use the operation management system to standardize the work of each substation. The site regulations for Changfeng, Qiangtang and Ronghuachang were revised and approved. At the same time, the environment of the duty room of each substation was cleaned up and standardized, and measures to prevent small animals and anti-condensation measures were strengthened.
5. Strictly implement the inspection and maintenance system to ensure the quality of maintenance and improve the operational rate of equipment.
Maintenance management
1. Relay protection operation
In 2019, the total relay protection of the power grid was 823 times, the correct action was 806 times, the correct action rate was 97.9%; the system re-closing was operated 103 times, the correct action was 103 times, and the correct action rate was 100%.
2. Work completion
Implemented the implementation plan for the “five-one-one-one-guarantee” work of the substation, and specially formulated the “Reformation Plan for the Relay Protection of Xinhua Electric Power Company in 2019” and the “Implementation Plan for the Implementation of the “Five Preventions and One Protection” of the Substation” "New Power Company Fixed Value Management System".
Complete the calculation and preparation of the new system impedance map.
Improve system valuation management:
1 Completed the calculation of 35kv Ronghua transformer production.
2 The 35kv line fixed value accounting work of the furnace observation substation was completed and re-adjusted. All line protection was changed from the original two-stage type to three-stage type protection.
3 Completion of the recalculation of the Yangxi main transformer and the 35kv line setting, improved the frequent tripping of the 35kv ocean manganese line and the jump of the Yangxi 10kv line to the main transformer. Complete the calculation of the replacement of the Jinfeng main transformer replacement.
4 The completion of the re-closing operation of the Qiangtang, Wentang and Furnace change lines was completed.
5 Completion of the calculation of the production and setting of the corresponding equipment of Changfeng Change.
6 Completed the calculation of the 10kv new interval of Tianmen Power Station, Jinfeng Jinshuang Power Station, Wentang Coal Mine i Line, ii Line and Qiantang Tangba Line. The calculation of the fixed value of the 35kv flat small line and the flat long line was completed.
7 Completed the adjustment calculation of the main transformers of Pingxi, Zhenshang, Baixi and Shuangjiangkou.
8 Completed the 10kv line fixed value calculation for all 35kv substations, and the correct operation rate of relay protection increased to 95%.
[1] [2] Next pagerecommended article
- City Audit Bureau Citizen Moral Construction Month Activity Summary
- Summary of year-end work of boiler operation team
- Summary of work on poverty alleviation
- Summary of village-level elections
- Sports team semester work summary
- Food and Beverage Restaurant and Kitchen Team Work Summary
- Hotel front office work summary
- Summary of the work of the teaching office
- Geological technician work summary
- Property Insurance Service Department Peaceful Creation Summary
- Preparatory party members summary throughout the year
- Summary of work of production companies in 2019 and 2019
popular articles
- Encouraging words 2019
- English joint test composition omnipotent sentence
- Summary of poverty alleviation work in 2019
- Summary of the work of national unity in towns and towns in 2019
- Deng Xiaoping's famous sayings
- Student Union Propaganda Department work summary
- Honesty and good words
- Grasp the opportunity
- Summary of news and publicity work in 2019
- Cherish the time of the famous sayings
- a famous saying of adversity
- Praying the mother's famous words
- Give the teacher 2019
- University Student Union Propaganda Department work summary
- Sentences describing mental activities
- English four-level composition omnipotent sentence
- Participle phrase
- Latest praise to the teacher
- Summary of the work of 2019 old cadres
- Summary of the work of the teaching and research section in 2019
- Modest and famous sayings
- a good saying that loves labor
- The most common words of Satay
- Summary of the 2019 Winter Conscription Work of the Armed Forces
- Lincoln's famous sayings
- Sentence of life
- a famous saying in the face of difficulties
- The most sad sentence 2019
- Financial Section 2019 Financial Work Summary
- Summary of the work of party style and clean government construction in 2019