Summary of Jianghe River Management Work in 2019


Municipal Flood Control Office:
Under the guidance and support of the higher authorities, under the leadership of the county party committee and the county government, the special funds of the above-mentioned levels are mainly used to fully mobilize the enthusiasm of the people and give play to the two committees of the village. The people are working hard. Through the year of governance, in accordance with scientific planning, meticulous design, meticulous construction, strict quality control, the river management project was successfully completed this year, in order to ensure smooth flow of rivers next year, cross-strait traffic trunks, infrastructure, residents, farmland The flood control safety has laid the foundation and strong support for the healthy development of the economy. The current situation of river governance in XX is summarized as follows:
I. Basic Conditions of the Project This year, there are only three rivers and rivers management projects implemented in our county. One is the Zhenanhe River Management Project of the Gongdai Project, the Baofa Reform and Reform Area [XX] No. 565, and the Baocai Agricultural [XX] No. 149 Investment. Governance of 3.2 million yuan; Second, the central extra-large flood prevention subsidy of 1 million yuan, to protect the financial farmers [XX] No. 145, Long Cainong [XX] No. 3 text issued to my county; third is the township fundraising bridge.
II. Implementation of the project In order to implement the good governance of the river project, our county will carry out the exploration, scientific and rational planning and careful design of the implemented projects as early as possible, and select the qualified construction team through bidding, so that the organization will be carefully organized, carefully constructed, and strictly controlled. The quality is closed and the funds are closed. The funds are invested in special funds, and the fund personnel are “two safe”.
III. Completion The river management project of this year is 2.2 km from Zhen'an West Street Section, the Xiangbai River Flood Diversion Tunnel Project and the Xiangda Traffic Bridge Construction. details as follows:
Zhen'an River Management Project:
1. The investment of the work-for-work project was 3.2 million yuan. It was started on December 12, XX, and completed on May 29, XX. A total of 2,200 meters of river support was completed, and the earthwork of the excavation was 16,600 m3, the backfill was 1.66 m3, the m75 masonry was 14,700 m3, the concrete was 1.36 m3, the machined road was 2.8 km, the tooth wall was 26, and the work was completed for 11,500 working days. .
2 The special flood control project of the Xiangbai River flood diversion project is 1 million yuan. It is used together with other project funds. The total investment is 45 million yuan and the length of the cave is 1234 meters. The project started construction on April 10, XX, and was completed on July 31, XX. .
3 The reconstruction of the river across the river is 220,000 yuan, and the earthwork is 55m3, the stonework is 123.5m3, and the c20 concrete is 139m3. The project started on December 20, XX and was completed on April 10, XX.
Fourth, engineering benefits
After the implementation of the river management project in XX, the first is to indirectly protect the 320 National Highway of Zhen'an from 1.2 km. The second is to ensure that the rivers are flooded, convenient for people to ensure the safety of Xiangda Town, and third, to achieve better economic benefits and long-term benefits. Social benefits.
V. Problems and difficulties
1. Our county is a poverty-stricken mountainous county with many rivers. There are many rivers and rainfall. Every year, small and medium-sized rivers must have flood disasters, which damage important facilities and farmland on both sides of the strait, which seriously restricts the economic development of our county and needs to be cured.
2. Some river planning is not in place, and most of them are constantly increasing and cultivating on the basis of the original;
3. The county's finances are very difficult. There is no capital to carry out special treatment. Only the superiors support and organize the people to work and solve the problem, and there are many river sections that need to be managed. For example, the lower section of the Pingda River needs to be treated. The governance of Zhen'an River is only Ten percent, most of the river sections are still earth embankments and cannot meet flood control requirements;
4. The concept of the people's legal system is not strong. Many rivers still have dumping garbage, spoiling soil, illegal rivers and river-crossing buildings, which seriously hinders the smooth flow of traffic;
5. The water and soil conservation in the upper reaches of the river has a long way to go. With the demand for economic development and the frequent human activities in recent years, mining, quarrying and sand excavation have increased the burden of river flooding.
6. The river management plan for XX year According to the city arrangement, there are 4 river management projects in our county in XX, with a total investment of 21.52 million yuan.
1. The Pingda River tail and dam section treatment project is 5.06 million yuan, and the river channel length is 1.4km. The planned completion of the earthwork is 0.504 million m3, and the masonry side is 24,900 m3;
2, like the Dahe River governance project, the investment is 5.44 million yuan, mainly to complete the stone earthwork of 19,500 m3, and the stonework of the stonework is 26,000 m3;
3, Mangguan River section treatment 6km, investment 5.82 million yuan, completed excavation of earth and stone side 24,000 m3, supporting building 27,700 m3.
4. The Supa River is treated around the corridor, and the earthwork excavation is 0.96m3, the stonework is 2.48m3, and the investment is 5.2 million yuan.
In the face of a period of time in the future, the country will expand domestic demand and increase opportunities for investment in water conservancy. Our county will conscientiously grasp, scientifically plan the project reserve, carefully design, complete the construction task according to the quality and quantity, and use every penny to make it benefit the party, give full play to the river flood control and drainage efficiency, and strongly support the local place. Economic development and development.