Expense application report
Application report on the cost of project management by the supervision company applying P3, etc.
Hunan Power Construction Corporation:
Zhuzhou, Fuyang, Liyujiang Thermal Power Project, Fengtan Hydropower Project is using P3 software for project management. Our company is responsible for the main development and management coordination of P3 in the above projects; at the same time, our company is in the provincial company, State Grid Corporation, In the power transmission and transformation projects of China Southern Power Grid Corporation, a large number of p3, project management tools such as Web-based project management platforms are used for management. According to the current situation, most of the projects have achieved good management benefits, especially in the plant. In the state power plant, Xiangyang Power Plant, and Liyujiang Power Plant, the application of P3 has become one of the most important supporting environments for infrastructure MIS. Among the Zhuzhou power plant projects, our company applied P3 to complete the preparation of the first-level network plan. P3 applies planning and coding design, and organizes contractors such as Huo'an to complete secondary network planning, some three-level network planning, and weekly tracking of secondary and partial tertiary networks. Now, the task of supervising the P3 server for tracking and counting has reached more than 4,000, which has effectively assisted the project management decision. The provincial company and the Zhuzhou Power Plant Project Department gave high praise. In the present and future In the process, we must vigorously promote P3 and other project management tools for modern project management to improve the project management level. Due to the large-scale application of P3 and other project management, it takes a lot of expenses, which is difficult for our company to bear. The construction company's application for the 2.378 million yuan fee details can be found in the attached file), please support it.
Hunan Electric Power Construction Supervision Consulting Co., Ltd. March 22, 2002
Attached files:
The supervision company applies project management tools such as p3 to carry out the project management application fee list name category application project cost description
P3 server
IBMPC server Zhuzhou Power Plant
100000
P3 server
IBMPC server Yuyang Power Plant
100000
P3 server
IBMPC server Fengtan Power Plant
100000
P3 server
IBMPC server 鲤鱼江电力
100000
P3 server
IBMPC Server Supervision Company Headquarters / Power Transmission Project
200000
P3 online version
8 users Liyujiang Power Plant
220000
P3 online version
8 users Fengtan Power Plant
220000
MSProject2002
Enterprise Edition Supervision Company Headquarters / Liyujiang Power Plant
20000
Snow P3/Project double code conversion software unlimited version all items
98000
Convert P3/Project single-code network map to double-coded time-scale network map
Exp7.5 online version
8 users of the national network / South Network project
250000
Staff training and development costs for all projects
150000
My engineering network web-based project management platform rental
10G space all projects
500000
For all project communication, communication, file sharing, version management, workflow approval, integration with P3, Project on the Internet, including video conferencing and on-site monitoring platform, on-site monitoring equipment including PTZ camera, video servo Zhuzhou Power Plant, Fuyang Power Plant, Fengtan Power Plant, Liyujiang Power Plant
320000
With PTZ camera, video server set of 80000, a total of four sets; remote control and unlimited monitoring on the provincial wide area network and the Internet; integrated with my engineering network Web-based project management platform
2378000
Hunan Power Construction Corporation:
Zhuzhou, Fuyang, Liyujiang Thermal Power Project, Fengtan Hydropower Project is using P3 software for project management. Our company is responsible for the main development and management coordination of P3 in the above projects; at the same time, our company is in the provincial company, State Grid Corporation, In the power transmission and transformation projects of China Southern Power Grid Corporation, a large number of p3, project management tools such as Web-based project management platforms are used for management. According to the current situation, most of the projects have achieved good management benefits, especially in the plant. In the state power plant, Xiangyang Power Plant, and Liyujiang Power Plant, the application of P3 has become one of the most important supporting environments for infrastructure MIS. Among the Zhuzhou power plant projects, our company applied P3 to complete the preparation of the first-level network plan. P3 applies planning and coding design, and organizes contractors such as Huo'an to complete secondary network planning, some three-level network planning, and weekly tracking of secondary and partial tertiary networks. Now, the task of supervising the P3 server for tracking and counting has reached more than 4,000, which has effectively assisted the project management decision. The provincial company and the Zhuzhou Power Plant Project Department gave high praise. In the present and future In the process, we must vigorously promote P3 and other project management tools for modern project management to improve the project management level. Due to the large-scale application of P3 and other project management, it takes a lot of expenses, which is difficult for our company to bear. The construction company's application for the 2.378 million yuan fee details can be found in the attached file), please support it.
Hunan Electric Power Construction Supervision Consulting Co., Ltd. March 22, 2002
Attached files:
The supervision company applies project management tools such as p3 to carry out the project management application fee list name category application project cost description
P3 server
IBMPC server Zhuzhou Power Plant
100000
P3 server
IBMPC server Yuyang Power Plant
100000
P3 server
IBMPC server Fengtan Power Plant
100000
P3 server
IBMPC server 鲤鱼江电力
100000
P3 server
IBMPC Server Supervision Company Headquarters / Power Transmission Project
200000
P3 online version
8 users Liyujiang Power Plant
220000
P3 online version
8 users Fengtan Power Plant
220000
MSProject2002
Enterprise Edition Supervision Company Headquarters / Liyujiang Power Plant
20000
Snow P3/Project double code conversion software unlimited version all items
98000
Convert P3/Project single-code network map to double-coded time-scale network map
Exp7.5 online version
8 users of the national network / South Network project
250000
Staff training and development costs for all projects
150000
My engineering network web-based project management platform rental
10G space all projects
500000
For all project communication, communication, file sharing, version management, workflow approval, integration with P3, Project on the Internet, including video conferencing and on-site monitoring platform, on-site monitoring equipment including PTZ camera, video servo Zhuzhou Power Plant, Fuyang Power Plant, Fengtan Power Plant, Liyujiang Power Plant
320000
With PTZ camera, video server set of 80000, a total of four sets; remote control and unlimited monitoring on the provincial wide area network and the Internet; integrated with my engineering network Web-based project management platform
2378000
recommended article
- Enterprises create civilized units to apply for reports
- Power application report
- New employee rectification application report
- Application report
- Car application report
- Unpaid leave application report
- Grant application report
- Item purchase application report
- Promotion application report
- General taxpayer application report
- Travel application report
- Activity funding application report
popular articles
- Apply for air conditioning report
- Classical life motto
- Sad love sentence 2019
- Funding application report
- Thanks to the friend's words 2019
- Bing Xin’s famous words
- Civil servant application
- Deaf people jingle 2019
- 2014 is very touching words
- The latest high school inspirational maxim
- English famous words
- Transfer application report
- Du Yuexi's famous sayings
- Injured sentence
- Tao Xingzhi's famous sayings
- Replace the new computer application report
- Strong words
- Describe the fast time sentence 2019
- a good saying that loves labor
- College entrance examination inspirational quotes
- Korean swear words
- Report on the application for transfer
- Property tax reduction application report
- Teacher's famous saying
- Qq space mood phrase
- Application report
- Activity funding application report
- I want to say something to the teacher.
- Application report
- Taizai’s famous sayings