time flies. Looking back at the work of this year, it was tense and dull, but in this tense and dull day, I stepped forward step by step and walked steadily. I actively and conscientiously do my job, complete the tasks assigned by the company, and be responsible for the mechanical repair work of the branch. Below I will make a brief report summary of the work of this year: I led the mechanics to do the following

First, increase staff training, improve staff quality and business skills. The current mechanics section of the Burning Plant is a strong team. A mechanical training meeting was held on the 2nd of each month to summarize the achievements and mistakes of the previous month, learn from experience and lessons, and arrange the work plan for the month to lay the foundation for the safety and accidents in 2019. It also ensures the completion of the production task in 2019.

Second, the operating rate of rotary kiln is 86.44%.

Third, energy saving:

1. Repair 2 sets of vertical grinding scraper plates in the whole year, a set of 60,000 yuan, totaling 120,000 yuan, repairing 2 sets of materials costs 30,000, can save the company 90,000 yuan.

2. Repair 12 arc valves, one 4800 yuan, 57600 yuan, repair 12 materials cost 6000 yuan, can save 51,000.

3 yuan monthly maintenance contact with the external association to change the vertical roller skin clamp block to 60,000 yuan, replacement time 3 days. The internal staff of our organization used the full stop to replace the warehouse. Saved the company maintenance costs.

4, repair a high temperature gate valve, the purchase of a high temperature gate valve needs 60,000 yuan, repair a material cost of 5,000 yuan, can save 55,000 yuan.

6. On April 23, the cement grinding accessories hoist chain and sprocket were replaced. The external quotation was 30,000 yuan for 48 hours. The company's leaders reduced the time, and the replacement was completed by our firing machine. It took 24 hours to complete. The above items can save 316,000 yuan.

Fourth, technical changes:

1. According to the experience of the company's leaders, the renovation of the cooling fan of the grate cooler effectively increased the power generation. In 2019, the clinker power generation was 30.1, the 2019 tm clinker power generation was 35.47, and the tonne clinker was increased by 5.37 degrees. At the same time, the clinker temperature is also lowered, and the quality is stabilized to improve the equipment life cycle.

2, coal mill 7306 screw conveyor faults frequently, high repair costs, motor power 22KW. Switch to 7.5KW of zipper motor, save 10 degrees of electricity per hour, can save coal mill 2019, boot time of 5891.19 hours *10 degrees can save 58991 degrees of electricity, but also reduce repair costs.

The above items are the results of my hard work with the mechanics. I was rated as a model worker, and my heart is under greater pressure. I will use this as an opportunity to accomplish the tasks of 2019.

Advanced personal work summary

With the goal and confidence, I am honored to be a member of the unit in July 2011. I am very proud to offer my own meager strength to the company. After a year and a half of practical study, I have integrated into the dynamic group of rapid development of the unit, and day after day absorbed new knowledge and new ideas that could not be found in the school. Looking back now, I have benefited a lot.

In June 2012, the unit was transferred from the unit to the Haitong Industrial Park Ping An High-speed Rail Project Department. It was comforted in terms of living habits and working conditions. Thank you for your understanding and care.

I came to Haitong Industrial Park Ping An High-speed Rail Project Department and found a job and work enthusiasm that is more similar to my own wishes. I would like to thank you again for the development opportunities and development platform that leaders have given me. In Haidong Industrial Park, I am mainly responsible for the safety production management of the A-2 community. I just got here and I was familiar with all the drawings of the 11th floor commercial and residential building of the A-2 community under the leadership of I--. I have a relatively familiar understanding of the drawings. A week later, I was transferred to the A-2 community construction site to carry out on-site safety production management. Here, under the leadership of many leaders and many careful guidance, I stepped onto the construction site safety step by step. The production management track has its own unique insights and methods of doing things right in front of many on-site facts. Here, the earthwork, basic engineering, and main works of each building were successively carried out until the eleventh floor of the nine buildings in the whole district on November 20th. Although in the process of early greed, no day and night work, but always

Passionate, never felt tired.

In terms of on-site production management: We will remember---- said: "Wrist management, human management, system management", this management method is mutually infiltrated and applied. Although my management experience is still insufficient, in the management process, diligence and inferences will always bring great gains. Eat a long, wise, and grow up unconsciously. During the construction process, we successively overcome many difficulties such as design technology change rework, difficult construction technology, complicated external communication, inconvenient concrete supply, difficulty in safety management of high-altitude operation, influence of rain and snow frost in the early and late stages, and finally achieved the annual goal. I am very pleased.

In life: leaders and colleagues often gather together, we speak freely, can do everything, talk about their own feelings after work, their own future development, trivial things in their own lives. It is often because of our unintentional conversation that we get better benefits, more care, and more development opportunities than others. Those leaders and colleagues who silently care about their subordinates and take care of their colleagues have made me feel a collective warmth.

Only this working time, absorbed a lot of theoretical and practical work experience, made up a lot of deficiencies, felt a collective warmth, and realized the true meaning of care and help. However, there are still many bad habits that I have not been able to correct, lack of theoretical knowledge, lack of practical experience, and my own quality needs to be improved.

In the future, in terms of project production management: I must also strengthen construction technology theory learning, engineering economic theory learning, project management theory and practical learning, change many bad habits, improve one's own quality, maximize the ability to work, and create the best benefits for the company. .

In the future, in terms of life: aiming at thrift and seeking a way for development. Finally, I would like to express my sincere gratitude to all the leaders for their guidance and careful guidance in the work, the learning space and work platform for me, and my colleagues for their guidance and support. In the future, I will work harder and live up to expectations.

Day and night change, time shuttle, progress with the company

Advanced personal work summary

After 2019 efforts, I adhered to the scientific development concept as a guide, constantly learning new knowledge, new technology and new business, and achieved some achievements in the work of the company's information technology center; in the company's leadership, all colleagues' support, cooperation and my own Efforts have been made to successfully complete the work objectives established by the Information Technology Center at the beginning of the year; and to support and cooperate with the leadership work, and conscientiously fulfill the duties and requirements of the full-time positions of the information technology center clerks, and earnestly perform their duties and work actively.

I will summarize my thoughts, work, and study in the following year: 1. Integrity and self-discipline:

Since I started my work, I have always strictly demanded myself as a member of the Communist Party. In particular, after taking up the post of a woman director, I insisted on leading by example in political studies, community work, and life style, and strictly implemented various rules and regulations of the company. In style, life style, work style, to be honest, self-disciplined, and take the lead. I am confident in my work and can always maintain a strong work enthusiasm. Second, earnestly perform good duties:

I usually serve as both a clerk of information technology center and a director of a woman. In the position of the clerk of the Information Technology Center, my main tasks are: completing the entry, printing and copying of various files and materials of the company; Reported mimeographed printing work; timely attendance at the end of the month, check and statistical work, report to the company's human resources department, and establish a sound attendance and use account; do a good job in the information center staff salary, bonus table, audit, timely delivery to the company's labor department Distribute wages and other management tasks; collect monthly plans for office, labor insurance supplies, and living materials for daily use, collect and register, and keep daily storage materials and supplies; and complete on time Other tasks assigned by the leadership and the superior authorities at any time.

In the position of director of women, the tasks of the superiors were successfully completed, all kinds of women's products were distributed, various activities were organized, the people were served, and women's security work was further improved. In the usual work, we can earnestly perform good job duties, obey the rules and discipline, have a strong sense of team, and consciously safeguard collective leadership, collective interests and collective honors, work civilized, polite, and no security incidents. Third, improve their own quality and strengthen the style of work:

I insist on strengthening learning as a key measure to improve my own quality. Ideologically demanding continuous progress, politically demanding advancing with the times, demanding pragmatism in the work, continuously improving my overall quality, and providing a powerful ideological weapon for carrying out various tasks. While strengthening theoretical study, he also used his spare time to self-study college correspondence courses, which laid a solid foundation for completing his job. In the past year, I have strictly met my own requirements. I have always regarded my patience as being flat, willing to pay, and obscurity as my own criteria. In the work, I will regulate all my words and deeds by system and discipline, strictly abide by the company's rules and regulations, respect leadership, and unite with comrades. Modest and prudent, take the initiative to accept opinions from all sides, and constantly improve the work; insist on doing things that are not conducive to the company's image, not to mention the company's image, and actively maintain the company's good image. Fourth, future work

In the past year, I have done some work and achieved some achievements, but the achievements I can only show the past and look forward to the future. I have to work harder to do my job well, carry forward my achievements, overcome the shortcomings, and work hard. Responsible spirit, down-to-earth, diligently do all the work, and live up to the expectations of leaders and comrades.