Fan Wen Daquan > Program essay

Groundbreaking ceremony plan


Part 1: The foundation ceremony planning plan

First, the event time: May 3, 20XX

2. Venue: Xiamen Garden

Third, the event organizer: Yanling County Investment Promotion Bureau

Fourth, the event organizer: Qiling County brothers wedding etiquette company

V. Theme, purpose and principles of the event:

Highlight the fruitful results of investment promotion and cooperation development;

To celebrate the festive and warm atmosphere of the foundation of Xiamen Garden;

Improve the social awareness of Xiamen Construction Company;

Demonstrate the strength of Xiamen Construction Company;

The whole activity principle requires that the content atmosphere, the atmosphere is warm, the scene is grand, the cost is frugal, inspiring, and the response is strong.

Sixth, the venue layout:

1. Place a inflatable arch at the entrance of the event venue. The giant banner of “Warmly congratulate the ground-breaking ceremony of the Xiamen Garden” was placed on it; two festive lantern columns were erected on both sides, echoing the arches.

2.8 Miss etiquettes stood on both sides of the gate to welcome the leaders and guests present. The band played cheerful music and singers sang songs to welcome leaders and guests.

3. The red carpet has been laid from the entrance of the gate to the main venue stage, and the foundation is placed on the front right side of the stage. At the ground-breaking site, the diameter of the square is laid. The foundation pit is placed in the middle. The foundation stone with a height of 1.6 meters, a width of 1.0 meters and a thickness of 0.26 meters is placed in the middle. The red cloth is covered with 10 color plaques.

4. The stage is equipped with professional audio equipment, two vertical microphones, and the special large inkjet background directly highlights the theme of the whole event. On the background, there are two dragons resting on the head together, and the two sides of the two sides draw the "two dragon play beads" pattern, showing the dragon's descendants, the dragons take off, the dragons are prosperous. The middle of the book "Foundation Ceremony for the Opening of Xiamen Garden in Suiling County". The background of the inkjet background is decorated with balloons. Place 8 flower baskets in front of the background and a set of cold fireworks in front of the stage.

5. Two carpets on the front of the stage, two sets of remote control fireworks, two sets of spray fireworks, and one salute car.

6. Sign in the table and decorate a pot of flowers for decoration. The professional etiquette lady is responsible for all the reception signings.

7, four inflatable balloons, placed on both sides of the stage

8, 150 bunts are arranged around the venue

Sixth, event ceremony planning

One week before the event:

1. Determine the location of the foundation stone in advance, order the cornerstone and engrave the text. Please order and implement the list of invitees, and arrange for someone to be responsible for the distribution. Purchase gifts and promotional materials and other related matters.

2. Set up a groundbreaking ceremony working group for all staff on the day of the ceremony, such as reception staff, gift distribution, security, coordination and coordination.

The day before the event:

1. The staff enters the venue and arranges the venue according to the set layout plan.

All staff members will be convened to start the event preparation coordination meeting, and the respective positions will be assigned on the day of the event. Specific things are implemented to people

2. Convene all staff members to start the event preparation coordination meeting and assign the respective positions on the day of the event. Specific things are implemented to individuals.

The day of the event:

At 7:00, all the venues were arranged, the installation and commissioning of the audio equipment was completed, and the host finally implemented and arranged the list and order of the leaders and guests. The relevant coordinators are ready for final preparation. The person in charge of the site inspected and supervised; the hostesses wore a boutonniere for the guests.

7:10 The band played a festive music that brought together people from all directions. All of these are pre-heating the atmosphere of the active scene in advance, and attracting popularity. The host of the celebration hosted the song singing, the content of the celebration was announced by the host in the middle of the concert, and the atmosphere of the celebration was rendered.

At 8:00, the host opened the ceremony, announced the ceremony, and read the leaders and guests and the congratulations unit one by one. Miss etiquette teamed up to bring the leaders and guests to the designated position on the podium.

1. The organizer leads to a welcome speech;

2, the developer leads the word

3. Leading words from relevant units

4, the county leader's speech;

5, the master of ceremonies read the name of the founding leader. The band played the welcome song

8:28 ask the leader to announce the official start of the groundbreaking ceremony. All stand up and take off the hat to play the national anthem

6. Please contact the county leaders and the developers' chairman for the dragon's finishing touch. After the finishing touch, put the remote control fireworks.

7. The relevant leaders led the ceremonial staff to the cornerstone. The fireworks were fired at the same time as the groundbreaking ceremony began. The staff set off firecrackers and salutes at designated locations.

Remarks: The above speech sequence is for reference.

The ceremony is over. All leaders and guests attending the ceremony can take a group photo together. Partial leaders and guests are allowed to accept interviews with reporters from the on-the-spot news unit to make post-propaganda work.

Seven, the cost estimate

1, Rainbow Gate: 200 yuan

2, lantern column: 100 yuan

3. Banner: 100 yuan

4, the stage: 500 yuan

5, balloon: 200 yuan

6, flower basket: 100 yuan

7, audio: 100 yuan

8, the band: 300 yuan

9, cold fireworks: 150 yuan

10, remote control fireworks: 2 groups of 400 yuan

11, spray fireworks: 2 groups of 500 yuan

12, Miss etiquette: 12 600 yuan

13, salute: 200 yuan

14, etiquette host: 200 yuan

15, guest boutonniere: 300 300 yuan

16, carpet: 200 yuan

17,150 bunt flags


Part 2: Ground-breaking ceremony plan

The groundbreaking ceremony usually refers to some important buildings, including buildings, venues, pavilions, pavilions, gardens, monuments, etc., held at the beginning of the construction of the celebration activities.

I. Preparations for the preparation of the celebration

In preparation for the foundation ceremony, preparations should be made in five aspects, including public opinion, invitations to guests, selection and arrangement of the site, reception services, and programming.

1. Do a good job in publicity. Including the relevant mass media, and conducting on-the-spot interviews during the groundbreaking ceremony to arouse the attention and support of the society.

2. Do a good job in inviting guests. In order to increase their visibility, important guests should be invited to participate in the groundbreaking ceremony. Including the leaders at the higher level, the person in charge of the competent department, the cooperation unit and the person in charge of the same industry.

3. Do a good job in the selection and arrangement of the site. The place where the groundbreaking ceremony is held shall generally be selected at the construction site where the construction of the building is started. The location of the foundation should be selected on the right side of the main entrance of the building as usual. The cornerstone for laying the foundation should be a piece of rectangular shape that is intact and beautiful in appearance.

Shaped stone. On the cornerstone, the text should usually be vertical. In the upper right section, the official name of the building should be engraved. The central part of the building should be engraved with two large characters, and the left part should be engraved with the full name of the founding unit and the year, month and day when the foundation laying ceremony is held. The fonts on the cornerstone are mostly

Body writing, and preferably gold or black on white. Below or on the side of the cornerstone, a closed iron box should be placed with the information about the building and the name of the founder. At the groundbreaking ceremony, it will be buried in the ground together with the founding stone by the founders, to commemorate.

In order to show grandeur and respect, guests can lay red carpets where the guests, especially VIPs, stand, and hang banners, slogans, balloons, ribbons, etc. around the venue. Audio equipment should be debugged beforehand to prevent errors during use.

4. Do a good job in reception services. A person in charge must be responsible for the reception work of the guests. When receiving VIPs, the person in charge of the unit must personally come forward. Have a parking lot and lounge ready. Souvenirs can be given when guests return. The choice of souvenirs should be noted: to highlight the functional role of the building; souvenirs must have a certain commemorative significance; must have the characteristics of this unit.

5 Do a good job in programming. The groundbreaking ceremony can be divided into four. The first one, the ceremony officially began, introducing the main guests. In the second item, the owner introduces the function and planning of the building. The third item, the guest made a speech. The fourth item was formally laid the foundation. At the time of laying the foundation, the drums and the firecrackers should be smashed. First, the founder would hold the new enamel with red silk as the cornerstone for the soil. Later, the owner and other guests will cultivate the soil in turn.

Second, the speech at the ceremony

The speech at the ceremony was very important. Through the introduction of the construction project by the host, the visibility of the project can be improved and the foundation for future construction can be laid. Leading cadres came to the scene to express their speeches, expressing great importance to the construction of the project and proposing hopes for the construction of the project.

The enthusiasm of the setters and the determination and confidence to overcome difficulties have all contributed.

All the speeches at the groundbreaking ceremony should be short and clear, but the following aspects are indispensable.

First, the speech of the founder. First of all, we should thank the leading comrades who came to the groundbreaking ceremony and the guests who gave great support to the construction of the project. Next, it will focus on the significance of this project construction, and introduce the background, preparation process, and construction objectives of the project construction. Finally, the specific steps, measures and practices for the construction of the project were put forward, indicating the determination and confidence to build the project.

Second, the speech of the superior leader. First of all, congratulations on the start of the project. Then focus on the significance and role of the project construction. Put forward the hopes and requirements for the organization and leadership of the project construction and the construction quality progress, and put forward the hopes and requirements for the relevant parties involved in the project construction. most

After that, he called on the majority of project builders to contribute to the work of the early days.


Part 3: Ground-breaking ceremony plan

First, the purpose of the activity

For the 180-acre large-scale real estate project such as “Pearl Garden”, the ground-breaking ceremony is an entry point for the project to be introduced to the market. The ground-breaking ceremony will be used to inform the property information. Therefore, this activity should be “prepared, coordinated, orderly, large-scale, and deeply rooted in people's hearts”. Through the cooperation of all parties, the following objectives can be achieved:

1. Let people from all walks of life have a preliminary understanding of "Yongcheng Mingzhu Garden"

2. Create the first river of Yongcheng real estate standard operation

3. By inviting the leaders of various government departments to participate, highlighting the policy advantages of real estate

4. Increase the market reputation of the project by awarding various awards

Second, the event time

Year, month, morning, morning

Third, the event location

"Pearl Garden" site site

Fourth, the activity content:

The foundation stone is the beginning of a real estate construction. It is also the beginning of a development process that has begun to receive attention. It is the need of market transparency requirements, and it is also the highlight of the pre-marketing of real estate. Through this foundation, the market transparency and market visibility and reputation will be maximized. There are several steps to achieve the above objectives:

1. Publicity covering the whole city. The pre-publicity propaganda that paved the entire Yongcheng made the building's incomparable momentum preemptive.

2. The strength of the invitation lineup. The mayor, the four major groups, the general manager of key enterprises, the political, business, and cultural circles gathered in the Yongcheng Pearl Garden.

3, the grand foundation of the scene. The audience reached more than a thousand people, and the whole city enjoyed the event.

4. Honored real estate. “The most trustworthy real estate in Yongcheng”, “The best garden landscape community in Yongcheng”, “Yongcheng Star Real Estate”, “Yongcheng Gold Medal Community” and “Yongcheng Real Estate Development Advanced Enterprise” make Yongcheng Mingzhu Garden a full honor when it is born.

5. Methodical organization and coordination. Straight-line real estate cooperates fully to ensure that the propaganda and organization work is in an orderly manner, and the first event of the Yongcheng Pearl Garden will be completed.

Fifth, the site layout

1. Level a square land at a designated location.

2. Set up a simple podium 3 days in advance. The area is about 30 square meters and the height is about 90 centimeters.

3. The rostrum uses the inkjet display board as the background wall.

4. Put the rainbow door in front of the rostrum, and hang the banner: the foundation stone laying ceremony of “Pearl Garden”.

5. The red carpet is placed on the chairman's desk, and flowers are planted in front of the stage.

6. The groundbreaking ceremony area is set up in front of the rostrum and fenced.

7. Invite 8 etiquette ladies to stand on both sides of the podium.

8. Place 6 liters of air ball and hang the banner under the balloon. The content of the banner is:

* The foundation of the Pearl Garden was started.

* Millennium Emperor

* Leading a new era to create a new life

* Green life, leading the trend of living.

* Pearl Garden Choose a resort lifestyle.

* Digital life, life achievement dream

The site layout is shown in the figure.

Preparations

In order to ensure the orderly development of the foundation laying ceremony, preparations must be completed before the foundation laying ceremony, and various factors should be considered in order to achieve the best results.

1. Engineering work

The site is leveled and construction waste should be cleaned up in time.

Complete the wall beautification work before January 18.

Construction equipment and building materials are stationed at the site, and they must be placed neatly.

2. Propaganda work

In the first month of the year, hundreds of banners were prepared and hoisted on the streets to convey the information on the start-up;

The content is as follows:

On the 18th of January, you will gather in the Pearl Garden to experience modern living style.

Seeing the construction of Yongcheng Pearl Garden, witnessing the arrival of a living era

On the 18th of January, the Pearl Garden was laid and laid the foundation.

On the 18th of January, the Pearl Garden was laid and laid the foundation.

The start-up message was broadcast on the local TV station two days in advance.

Prepare a bicycle team of 50-100 people three days in advance, unify the clothing, issue a single film, and do pre-publicity.

On the day of the event, a direct train was opened in the traffic lane of the old city, and people were taken to the scene.

The tabloids, monolithic and other promotional materials are in the order.

On January 18th, on-site flags, carpets, sounds and other equipment were in place.

3. Main work on the day of the foundation laying ceremony:

Do a good job in the reception work of the leaders.

The reception work of the reporters.

Strictly check and implement on-site business management.

Maintain order at the scene.

4, office work

Invite leaders to participate

* Mayor

* City Construction Bureau Leader

* Planning Bureau Leader

* Housing Authority leadership

* Land Bureau Leader

* Public Security Bureau Leader

* Cultural Bureau Leadership

* Head of construction company

* Supervisor company supervisor

Invite a property representative

Invite news unit reporter

* "TV" journalist

* Plane journalist

5. Other preparatory work.

* Do a good job in the activities before the start of construction, to achieve the purpose of the city.

* The company's leadership speech is ready and confirmed two days in advance. If the speeches of the leaders of the Construction Committee and the Housing Authority need to be prepared, they should be prepared and confirmed in advance.

* Medal production. “The most trustworthy real estate in the city” “Best garden landscape community in the city”, “City star real estate”, “City gold community”, “Advanced enterprise in real estate development”

* Prepare the shovel used in the groundbreaking ceremony.

* Prepare the stone monument used in the groundbreaking ceremony.

* The items used for ribbon cutting are listed by the etiquette company, and the company staff is ready to be in place five days in advance.

* On the day of the start of the work, the guests are prepared for lunch, rest and reception work.

* Tools for taking pictures on the day of the foundation stone laying ceremony

* Prepare salutes and firecrackers for the day of the foundation stone laying ceremony

* Invite TV host to host the groundbreaking ceremony

* Inviting the police to maintain order on the foundation of the foundation

* Reserved parking spaces on the event site

* Division of responsibility for work with etiquette companies

* Pay attention to the weather conditions on the day of the groundbreaking ceremony.

* Other related items needed for the preparation ceremony

Sixth, the activity process

Waist drum team, military band performance activities 8:30 - 10:00

Invited guests in place 10:00

Moderator's speech 10:00 - 10:05

Mayor's speech 10:05-10:10

Chairman of the Construction Committee speech 10:10-10:15

Housing Authority Leadership Speech 10:15 - 10:20

Company General Speech 10:20-10:25

The head of the construction company speaks 10:25 - 10:30

Supervisor company responsible person speaks 10:30 - 10:35

Owner's representative speech 10:35 - 10:40

Award ceremony 10:40 - 11:00

Ground-breaking ribbon-cutting ceremony 11:00 - 11:30

Shovel enters the field 11:30

The moderator announced the end of the groundbreaking ceremony 11:50

Seven, details of the event:

Popularity: In addition to doing propaganda work in the early stage of the opening ceremony, in consultation with large enterprises or institutions, they are required to send staff to participate in the groundbreaking ceremony. Determine the initial number of people above 500.

VIP reception program

The timing of the fireworks bloom:

The groundbreaking ceremony began, and the main leaders began cutting the ribbon

The timing of the local shooting guns:

The gun was the last link, and the gun was fired at the beginning of the groundbreaking ceremony.

The timing of the band performance:

Guest arrival

The host announced that the groundbreaking ceremony was officially started.

Award medal

Groundbreaking ceremony

Groundbreaking ceremony process:

Award ceremony process:

Gift preparation type:

Divided into four categories: the first category - special guest gifts

The second category - guest gifts

The third category - news reporter gifts

The fourth category - intentional customer gifts

Eight, organize work

A special activity service team was established, with XXX as the general commander, and four organizational departments were set up according to different work contents.

Project: Responsible for the preparation of the previous event venue, site erection, organization of construction equipment and other work.

Propaganda: Responsible for the pre-publicity activities, organization of popular sentiment, the preparation of intermediate activities, the middle photography work of the venue, and post-conference supervision and publicity.

Reception: Responsible for inviting relevant leaders to attend this meeting.

Scene control: Responsible for on-site security maintenance, scene control, and early contact with visitors.

The organization chart is as follows:

Event organizers and implementation forms:

stage

Work content

Executive

principal

Complete time

Propaganda

Salesperson training

Promotional banner content writing

Promotional banner production

Promotional banner suspension

Promotional materials production

Leadership speech writing

The host wrote a manuscript

Media release manuscript writing

Contact the TV station before the start of the TV station

Live photography

Reporter reception guide

Live banner production

Bicycle team clothing preparation

Bicycle team organization

engineering

Site erection

Foundation shovel preparation

Ground-breaking site

Construction equipment arrives in advance

Foundation stone preparation

On-site item purchase order

On-site item purchase

Host invitation

Reception

Prepare a list of invited guests

Invitation to prepare and distribute

Guest sign-in area arrangement

VIP reception and guidance

News reporter gift preparation

Purchase of guest gifts

Lunch arrangement

on site

Approval of the licensing unit in the early stage of medal production

Medal design and production

Watching the RV banner production

Watching the car accompanying

Watching the RV organization

Site layout command

Audio equipment

Flower pot

Fireworks cannon purchase

Fireworks

Firecracker

Foundation area fence preparation

Waist drum team contact, military band contact

Etiquette company contact

On-site air balloon contact

Live banner suspension

Color arch door contact

Field control

Carpet purchase


Part 4: Ground-breaking ceremony plan

First, the theme, purpose and principles of the event:

The theme of the event is to celebrate the groundbreaking ceremony of the office building of the Municipal Grain and Oil Reserve Center.

The purpose of the activity is:

1. Demonstrate the development direction of the enterprise and the positive development spirit through the foundation laying ceremony, enhance the vitality and enthusiasm of the enterprise, sublimate the enterprise spirit, and enhance the market combat effectiveness;

2. Strengthen communication and cooperation with government agencies to promote the further development of enterprises;

3. Improve the visibility of the company.

The principle of activity is: the content atmosphere, the atmosphere is warm, the scene is grand, the cost is frugal, inspiring, and the response is strong.

Second, the time, place and participants of the foundation

Time: June 16

Location: The site of the library site of Shenyang Grain and Oil Reserve Center.

Participants: company personnel, customers, ceremonial host, hostesses, etc.

Invited guests: City Leader, Shenyang Municipal Finance Bureau, Shenyang Municipal Development and Reform Commission, Shenyang Agricultural Development, Shenyang Land Bureau, Shenyang Municipal Planning Bureau, Shenyang Grain Bureau, Shenyang Construction Bureau, Shenyang Research Institute of Science and Technology, National Grain Reserve Bureau, Construction unit representatives and the relevant department heads.

Celebration Host: Shenyang TV Station Host

Invited media: "Shenyang Daily", Shenyang TV Station, "Liaoshen Evening News".

Third, the main agenda

The main agenda has the following items

1. The guest signs in and receives the gift. The guest is guided by the hostesses.

2: Participants in the groundbreaking ceremony are in place, waiting for the groundbreaking ceremony to begin

3: The band played music, the host announced that the foundation ceremony ceremony began, introducing the leaders and guests present.

4: The leader leads the speech

5: Company leader's speech

6: Speech by the leaders of the Shenyang Municipal Government for the foundation stone laying ceremony of the Grain and Oil Reserve Center Library 7: The ribbon cutting ceremony begins

8: Miss etiquette guides guests into the groundbreaking site

9: The salute sounded, the band played music, and the foundation stone ceremony began.

10: Miss etiquette guides guests into the guest's departure

11: Hotel, celebration reception

activity ends

1. Construction representatives, company leaders and participants took a group photo.

2. All the leaders who participated in the foundation laying ceremony of the work came to the site to guide the work.

Third, matters needing attention and service contact

1. Guests, VIPs, etc. will first sign in at the reception after arriving at the venue.

2. The vehicles of the participants are parked at the designated site of the construction site, and the security is responsible for the supervision.

3. Leading guests are required to organize personnel to enter the venue by 9:30.

4. Participants must strictly abide by the discipline of the venue and obey the command. After the event is over, the person in charge of the on-site security shall be guided to walk to ensure the safety of the people.

5. Check-in: It is located at the entrance of the foundation. There is a signboard at the sign-in place, and a hostess with a shoulder strap is responsible for signing in.

6. Gift distribution area: sign-in place. The person responsible. The gift is tentatively designated as a consumer card.

Fourth, preliminary preparation work

1. The main venue layout and stage construction were completed the day before. And do all the preparations needed for the ceremony.

2. Get the weather information on the opening day to the Shenyang Meteorological Bureau 3 days in advance.

3. Implement command and responsible order work 6 days in advance, and implement the command and responsible order work within the scope of activities.

4. Determine the list of VIPs and guests 4 days in advance.

5. Do a good job in the gift work at the event site in advance, and apply for fire protection approval for the air ball in advance 3 days in advance and file with the Meteorological Bureau.

Fifth, the venue layout

Site site

1. One rainbow gate at the entrance of the construction site and the foundation site

2. Hanging banners on both sides of the railway bridge).

3. Set 6 golden air balloons on the sidewalk of the Nanxun Street construction site.

4. A number of colorful flags are inserted on both sides of the construction site to highlight the atmosphere.

6. The stage is placed on the west side of the construction site, facing the east. Potted flowers are placed under the stage, red carpet is laid on the stage, and the “Shiyan City Grain and Oil Reserve Center Library Opening Ceremony” is hanged behind the stage. The microphone and speaker set on the stage. .

7. The military band, the prestige and the drum team, standing at the Taipei side of the building's main entrance.

8. The cornerstone is placed in the center of the construction site.

9. The ribbon-cutting area is located at the chairman's desk. The specific design is as follows:

Chairman's Desk: Located at the entrance of the sales department, the left side is a special microphone for the VIPs, the right side is the host's vertical microphone, the table top is covered with red carpet, the red carpet is covered with golden cloth, and the front and left and right sides are Greenery and stainless steel etiquette columns.

Guest area: set on both sides of the ribbon-cutting area.

Special Note:

Guest identification. After the guests arrived, the hostesses wore brooch for the guests according to their different identities. If the VIP wears the brooch made by the orchid, the starry sky and the bamboo, the guest wears the boutonniere made of roses, gypsophila and wenzhu. The VIP is accompanied by the hostesses or the company leader to accompany the VIP lounge. The guests are treated by etiquette. Miss leads to the sales hall.

Six, staffing

Chief commander: The general manager of the company is responsible. Serve as. Responsible for the sixth, the ceremony schedule

1: Ceremony and work arrangement

time

Location Qingfeng Nanxun Street site

Celebration agenda organizer organizes implementation instructions

5:30--7:30, the field is specially set up to stare at the field to prevent the wire from being short-circuited by people.

7:00--7:30 military band military band rehearsal

7:30--8:00 band ready to debug musical instruments, audio equipment

7:50-8:30 line, audio equipment layout staff always leave the scene

Site supervision:

8:00-8:20

Carpet laying and security maintenance carpet cleaning

7:50-8:10

At the sign-in desk, set up a sign-in person, two etiquettes; a table, a chair, a sign-in card, and a list of two invited people

8:10-9:50 visitors to the reception etiquette:

Reception security:

7:50-10:30

The construction team queued up the construction team to wear a helmet

9:00-11:00 media reporters, interviews

9:00-9:20 model show

9:20-9:40 military band, prestige and drums alternately played

9:20-9:40 Leaders and VIPs are admitted to the venue by the admission of VIPs, leading the admission, determining the position of the 9:40 celebration. The host announces the start of the celebration, introduces the leaders, VIPs, guests, and the person in charge of the sign-in office provides the list of the participants.

9:43—9:45 Chairman's speech

9:45-9:48 General Manager's speech

9:49-9:52 Government Leadership Speech

9:53—9:56 City government leaders announced the start of ribbon cutting

The list of 9:58--10:00 ribbon-cutting ceremony ribbon-cutting lists is determined:

Give a gift: fly a small balloon:

Playing military music: salute:

10:05 foundation laying ceremony

10:10 work guide

Arrange for dining at 11:00:

10:20 stage performance

10 ribbon cutting professional etiquette:

10 welcome ceremonies:

16 holds:

List of personnel selected:

Ceremony host:

Information Liaison:

VIP reception room reception:

Reporter:

Flying small balloons:

Give flowers:

Floor book, dm and small gift distribution:

Emergency handling of the problem of selling houses:

Head of stage performance:

The overall coordinator of the event:

Mobile staff:

Note: All staff members are basically ready to work at 8:30, and all preparations are stopped after 9:00.

VII. Cloth materials, personnel and budget Zhengzhou started the groundbreaking ceremony plan

materials

18 meters of 18-meter rainbow gate, 1 pair of dragon pillars, 2 pairs of palace lampposts, 2 walking cartoons, 14 lifted golden balloons, 2 salute cars, 1 airship, 34+80 banners, 8 meters red carpet, gold Cloth 8 meters, flowers 200 pots, 9 hand-held fireworks, 2 backgrounds, 200 small balloons, 1 set of speakers, 2 seat microphones, 2 wireless microphones, 2 beautiful flower arrangements, 1 stone foundation, bunting A number.

Staffing

Miss etiquette 8-12; 1 tuner; 33 military band; lion dance team, 12 people.

gift

1) Several Youngor shirts

2) Umbrella, notebook

lunch

Media campaign


Chapter 5: Ground-breaking ceremony plan

Part I Topic

First, the event name: XXXXX foundation laying ceremony

Second, the event time: xxxx year xx month xx day

Third, the event location: xx city xx development zone

Fourth, expected to participate in the celebration staff

1. xx city government leaders and relevant leaders of xx development zone

2. Relevant leaders of relevant committees, offices and bureaus

3, XXXX company leadership

4. News media reporter

5. Other relevant personnel, etc.

The second part of the ceremony site layout

In order to reflect the grand and enthusiastic completion of the XXXX project, the celebration company designed and laid out the groundbreaking ceremony and arranged the day's activities.

1. Set the main venue for the XXXX groundbreaking ceremony and set up a subjective ceremony.

2. The green plant decoration is arranged around the podium, and the sound system is arranged and installed.

3, background board inkjet theme, "XXXX groundbreaking ceremony."

4, the atmosphere around the scene layout, air model, bunting, air floating ball and so on.

5. Place a rainbow door at the entrance of the main venue, a red carpet on the passage, and a flower basket on both sides of the road.

6. Set up the foundation pit in front of the rostrum and place the cornerstone.

Part III Program Arrangement

07:00 Preparation before the meeting

08:00 Check before the meeting

08:30~09:00 Play music, create a warm atmosphere

09:00~09:18 Military band welcomes guests

09:18~10:30 Ceremony stage

The host announced the ceremony and introduced the guests.

The organizer leads the welcome speech and introduces the situation

VIP speech

Government leadership speech

Ground-breaking ceremony

The foundation stone ceremony was completed

10:30~11:20 Go to the hotel

11:30~13:00 Reception Luncheon

Part IV Program specific content

09:00 check-in stage

The guests arrived one after another. The staff and the hostesses were present at the welcome. The VIPs were guided by the hostesses to the VIP reception. Other guests were entertained at the ceremony venue, the military band,

The South Lion and the Drums alternately perform, adding to the warm atmosphere of the ceremony.

09:18 The ceremony begins

At the ceremony, the guests took the podium under the guidance of Miss etiquette. The military music and the lion drums rang and the guests were seated.

The host took the stage to announce the start of the groundbreaking ceremony and asked the general manager of the company to speak on the stage.

Message from the general manager of the company:

Dear leaders, distinguished guests, ladies and gentlemen, how are you!

Xxxx Development Zone xxxx Engineering Co., Ltd.......,XXXX

Today, a grand foundation stone laying ceremony was held here. On behalf of all the staff of the company, I would like to express my heartfelt gratitude and warm welcome to all of you who can participate in our ceremony during your busy schedule.

First of all, let me introduce the guests who came to our ceremony today:

Government leaders at all levels have: xxx xxx xxx xxx

The real estate industry guests are: xxx xxx xxx xxx and friends from all major media and guests from all walks of life xx,

Let us once again express our sincere gratitude and warm welcome to all the leaders and guests.

09:45 First of all, please give a welcome speech to Mr. xxx, General Manager of XXXX Group Co., Ltd.

09:53 Please ask the city leader Mr. XXX/Ms.

09:58 Please ask Mr. xxx Mr./Ms.

10:03 Please ask the investor VIP xxx Mr. / Ms.

10:08 First, please speak to Mr. xxx/Ms. President of XXXX Group Co., Ltd.

10:13 Let's talk to the xxx city government leader Mr. XXX/Ms.

10:18 The xxx group has received strong support and care from the government, the municipal government and other government departments from the establishment to the opening of the business. I would like to express my sincere gratitude! At the time of the establishment of the group, we also received a congratulatory letter from all parties. Let me read out: ........., let us express our heartfelt thanks here!

10:20 Next, the Southern Lions' eye-catching ceremony was held. Have the government leader Mr. xxx, the general manager of XXXX Group Co., Ltd. Mr. xxx, Mr. xxx, the finishing touch for the South Lion.

10:28 A ribbon-cutting ceremony is now held. We are pleased to invite the following guests to cut the ribbon for the establishment of XXXX Group Co., Ltd., and please introduce the hostess.

When the leaders cut the ribbon, they released balloons, fireworks and salutes.

10:33 Next, we will hold the groundbreaking ceremony for XX. Please have Mr. xxx, Mr. xxx and so on lay the foundation for the xxx project. After the leaders were in place, the moderator announced that the foundation was laid! Please lead the foundation for the project!

10:38 The foundation stone laying ceremony was completed. We had a luncheon at the xxx hotel. Please invite the leaders and guests to the hotel.

recommended article