Fan Wen Daquan > Contract Model > Construction Engineering Contract Model

Construction and installation contracting contract (4)


Construction and installation project contracting project name:
Construction unit:
Construction unit:
Review unit:
Project Number:

IX _____ years _____ month _____ days

Construction and installation contract

Signing the contract parties:

Construction unit: ________________________________________________________, hereinafter referred to as Party A;

Construction unit: ________________________________________________________, hereinafter referred to as Party B.

In order to clarify the rights and obligations of both parties in the construction process, the two sides should create conditions for each other, do a good job of cooperation and cooperation, and complete the national basic construction tasks quickly and economically. After full consultation between the two parties, this contract is signed to comply with

Article 1: General

First, the project name: __________________________.

Second, the state's approved investment plan for the project, project project table, application for building permit, project task book, preliminary design, general budget and other file numbers.

Third, the project number: ______________________________.

Fourth, the project location: ____________________________.

V. Project scope: The total installation area of ​​all engineering buildings in this contract is ______________ square meters.

Sixth, the project cost, the construction cost of all construction drawings of this contract is RMB ____________ yuan.

Article 2: Project deadline

The entire project of this contract was completed from the _______ year ________ month _________ day to the ninth ______ year _____ month _______ completion.

In the process of organization and construction, in the event of the following circumstances, the construction period shall be extended, and both parties shall conduct consultations in a timely manner and determine the extension period in writing:

First, those who are forced to stop working because of natural disasters or manpower cannot resist;

Second, because Party A proposes to change the plan or change the construction drawing and cannot continue construction;

Third, because Party A cannot supply drawings, supplies, materials or materials supplied by them, and equipment that meets the specifications, they are forced to stop work or fail to construct smoothly.

Article 3: Construction preparation

First, Party A should complete the land acquisition and demolition before starting construction; apply for a building license; remove the existing pipelines, greening and other obstacles that affect the construction within the construction site; solve the construction land; solve the construction water source, power supply and transportation road connection To provide all engineering design drawings to Party B; organize the design and construction units to carry out the engineering design.

2. Party B shall organize relevant personnel to learn and familiarize with the drawings before starting construction, participate in designing the balance, compile the construction drawing budget, be responsible for compiling the construction organization design or construction plan, carry out on-site layout, construct temporary construction facilities, and arrange the overall construction schedule. , reserve materials, processing components, and prepare for all construction.

Article 4: Material supply

First, all the materials required for this contract are handled according to the following first supply method:

1. The special materials, the departmental pipe materials and the mechanical and electrical products of the unified department are all purchased and supplied by Party A to the designated place of Party B. All other materials are purchased and supplied by Party B;

2, Party B is responsible for the application, ordering, and adjustment of materials. The mechanical and electrical products of the special materials and the departmental management department shall be purchased and supplied by Party A to the designated place of Party B, and other materials shall be purchased and supplied by Party B;

3, the contractor does not cover the project, all materials are purchased and supplied by Party A to the site or designated processing location.

4,......

Second, the complete set of equipment and non-standard equipment, Party A is responsible for handling applications, ordering and processing, before the delivery of complete sets of equipment to Party B, Party A shall be responsible for commodity inspection. Party A may entrust conditional Party B to process non-standard equipment processed at the construction site.

3. If the materials required for the project cannot meet the requirements of the project due to the specifications or materials of the supply department, and must be replaced or processed by other specifications, the original design unit and the consent of both parties shall be obtained in advance, after the relevant procedures are completed. Execution, the amount difference, price difference and processing fee incurred due to substitution or processing shall be borne by one of the responsible suppliers.

4. Any materials that should be accompanied by a certificate of conformity must be verified when entering the construction site. If there is no certificate, it must be approved by the test. The test fee shall be borne by the responsible supplier.

5. The materials and equipment that Party A is responsible for, if it is not delivered on time or the quality of the specifications does not meet the requirements, it cannot be solved by the efforts of both parties. Therefore, Party B shall bear the losses caused by Party A.

Article 5: Settlement of construction funds

First, the settlement method of the entire project cost of this contract shall be handled according to the following items:

1. Settle the construction plan budget plus the increase or decrease of the change budget;
2. According to the construction drawing budget plus the coefficient to determine the dry cost, the cost outside the scope of the package, and adjust the dry cost according to relevant regulations;
3. According to the standard construction drawing, the cost of the construction shall be unilaterally packaged, and the cost outside the scope of the package shall be adjusted according to the relevant regulations;
4. The contractor does not include the project, and settles according to the contracted labor quota or the labor fee.
5. ......

2. From the date of signing the contract, Party A shall, within ____________ days, allocate the amount of ____________ of the total construction cost to Party B for the preparation and construction fee. During the project, Party A shall review the monthly report of the completed workload provided by Party B, and allocate the progress payment to the project accordingly. Before the completion of the project, the final payment of ____________ of the total cost of the project can be reserved, and will be paid in full after the project is completed and accepted.

Article 6: Construction and design changes

First, Party B must adhere to the principle of “a hundred years of planning and quality first” in the organization of construction. It must organize construction according to the construction acceptance specifications and quality inspection standards issued by the state, as well as design requirements, and require all projects to meet the eligibility criteria.

Second, in the construction of the organization, it is necessary to adhere to the construction according to the drawings. No party may arbitrarily change the design. In the event of the following circumstances, Party B’s work, rework and backlog of materials and components, labor, mechanical transfer and other losses shall be Party burden:

1. If any design is found to be wrong or has serious unreasonable conditions during construction, Party B shall notify Party A in writing, and Party A shall agree with the original design unit to propose to modify or change the design file within seven days, and shall continue construction after Party A and Party B go through relevant procedures. ;


2. If the design exceeds the original design standard or scale after the design change, it must be approved by the original approval unit, and both parties can apply for the relevant procedures. No one may force construction until the design change has been approved;

3. In the case of construction, if it is suspended in the middle of construction, the construction will be completed, and both parties will customize the construction in progress to the safe part.

Third, in the construction due to Party B's own reasons for stoppages, rework, materials, component back-transport, mechanical secondary approach and other losses, are all borne by Party B.

Fourth, Party B must strictly implement the concealed project acceptance system. After the concealed project is completed, it must be checked and accepted to make the next process. The general concealed project shall be inspected and accepted by Party B and recorded well; the major or complex concealed works shall be notified by Party B in writing to Party A and the design unit for acceptance and acceptance of the concealed acceptance procedures. If Party A and the design unit do not participate at that time, Party B may check and accept it by itself, and shall make a record. Party A shall acknowledge it. If Party A submits the inspection later, if the inspection result does not meet the requirements, Party B shall be responsible for the inspection expenses; if it meets the requirements, Party A shall be responsible for the inspection expenses.

5. In the process of organizing the construction, in case of special circumstances, Party A shall adopt a special construction method for accelerating the completion of a single project in advance, so the additional construction costs shall be borne by Party A. Before the construction of the organization, both parties should complete the formalities for changing the construction method.

Article 7: Completion acceptance, settlement and warranty

1. Party B shall inform Party A of the acceptance date in writing on the date of completion of the individual project ________. If Party A fails to participate in the acceptance, it shall notify Party B in advance and agree with Party B on the acceptance date, but Party A Party B’s completion time must be acknowledged. Party A shall postpone the acceptance, and the management fees and losses incurred during the period shall be borne by Party A.

Second, the completion project has passed the inspection, and the transfer from Party A to Party A within ______________ days from the date of acceptance. If Party A fails to take over as scheduled, the loss incurred by the accepted project shall be borne by Party A.

3. If a single project in a project needs to be handed over to Party A separately for construction by another construction unit, Party A and Party B shall handle the intermediate acceptance procedures at the time of handover as the basis for the acceptance of the completed project.

4. In the completion of the completion of the project, if it is found that it is not qualified to rework or repair the repaired part, the two parties shall agree on the repair measures and time limit during the acceptance, and Party B shall complete the repair within the prescribed time limit, and then pass the experience after acceptance. Therefore, the expenses incurred by Party B shall be borne by Party B.

5. The project has been basically completed. If a certain material or equipment cannot be resolved, the project cannot be completed on schedule. With the consent of both parties, the project can be completed and reduced, and the completion and acceptance of the completed project will be completed. formalities.

Sixth, the acceptance of the completion project is based on the construction acceptance specifications issued by the state, the quality inspection standards and the construction drawings. In the case of completion acceptance, Party B shall provide Party A with the following conditions:

1. Increase or decrease the relevant procedures and other negotiation records of engineering changes;
2. Concealed project acceptance record and intermediate delivery acceptance record;
3. If the project is not changed, the construction unit should indicate it on the original construction drawing and submit it to Party A for archiving. If the project changes greatly, Party A shall draw or commission the design unit to draw the as-built drawings.

7. Party B shall, within ____________ days of completion and acceptance of the individual project, send the completed project settlement piece to Party A for verification. After receiving the completion settlement, Party A shall complete the verification within ______________ days, if it is not validated due After the completion or no objection, it is deemed that the settlement is agreed, and the construction bank will allocate funds accordingly.

8. After the project is completed and accepted, Party B shall be responsible for the warranty of the construction civil engineering quality for one year, and the heating project shall guarantee the first heating period. During the warranty period, it is true that due to construction responsibility, the roof leakage, pipe leakage, air leakage, blockage and other quality accidents shall be repaired by Party B and shall bear all repair costs.

Article 8: Awards, Punishment and Arbitration

First, Party B proposes to rationalize the design of the design on the premise of ensuring the quality of the project. Only Party A and the original design unit can agree to the construction. Therefore, the investment in the project is ______________ percent. __________ is the design unit.

Second, because Party B's liability is not completed according to the date specified in this contract, the completion date of completion acceptance shall be calculated. For each day overdue, Party B shall pay the __________ liquidated damages to Party A according to the budget of the project. If Party B takes measures to complete the work ahead of time, Party A will pay Party B a reward of ____________ for every one day in advance. The bonus is paid by Party A’s income or from Party A’s investment in the drug. If Party A does not have a source of funds, the bonus and penalty clauses may not be implemented. Party B shall proceed from the overall situation and shall not postpone the delivery of work.

Third, Party A and Party B shall not owe all kinds of payables for any reason. If they fail to pay within the time limit, they will be treated as loans. The delaying party shall increase the interest payable for unpaid expenses.

Fourth, the construction contract is supervised by the construction banks at all levels. Economic disputes during construction shall be resolved through consultation on the principle of seeking truth from facts. If the two parties cannot resolve the dispute, they may, at the request of one of the parties, submit the arbitration of the administrative department for industry and commerce with jurisdiction.

Article 9: Project leader and industrial accident

First, Party A sends _____________ comrades as the person in charge at the scene, and Party B sends _____________ comrades as the person in charge of on-site construction to jointly perform the provisions of this contract.

Second, Party B has the responsibility to educate workers to strictly implement the operating procedures, safe construction, fire prevention and theft. Party B shall be responsible for any casualties caused during construction and other losses caused by poor management of Party B. Party B shall not affect the progress of the project.

Article 10: Copies and Validity Period

First, this contract is a form of ________. The original two copies, one for each Party A and Party B; one copy of _________ copies, submitted to the competent authorities of Party A and Party B, the industrial and commercial administration and the Construction Bank for each record.


2. This contract shall become effective on the date of signing by both parties and shall be lapsed after the completion and acceptance of all the projects of this contract and the settlement of the final payment.

Article 11: Supplementary provisions

1. If there are any unfinished matters in this contract, the parties may, in accordance with the specific circumstances and the relevant provisions, agree to the terms of the by-laws as an auxiliary file of this contract, which shall have the same effect as this contract, but shall not be inconsistent with this contract.

2. The engineering agreement signed by both parties before the conclusion of this contract may be used as an auxiliary file of this contract after signing this contract. Where this contract is inconsistent, this contract shall prevail.

Article 12: Contract Attachment File

First, the project - watch

Second, all construction drawings

Third, the construction drawing budget table

Fourth, Party A is responsible for supplying materials and equipment.

Fifth, the state has approved the investment plan for the project, the project task book and other __________ files.

Article 13: Other terms

____________________________________________________________.

Construction unit:______________ __________________
Representative: _____________________________
address:___________________________
phone:________________________________
Contact: ____________________________
Bank account:_______________________
Construction unit:_________________________
Representative: ______________________
address:__________________________
phone:__________________________
Contact: ____________________________
Bank account:_________________________
IX _______ years __________ month _ day order

recommended article

popular articles