Construction engineering labor contract


Contractor:

Contractor:

In accordance with the "Contract Law of the People's Republic of China", "Law of the People's Republic of China", "Labor Law of the People's Republic of China" and other relevant laws The principles of administrative regulations shall be negotiated by the contracting parties. The following terms are formulated:

One. Project Overview:

1. Project Name: 5#53#54#55#56# project of Southwest Information Industry Park.

2. Project address:

3. Building area: 16662.80 square meters

4. Structure type: frame

5. Project cost:

two. Contracting:

The contractor shall provide general contracting for labor service labor costs for the 5#53#54#55#56# project of Southwest Information Industry Park.

three. Contracting scope:

1. The scope of contracting for this project is the labor service of the three major projects of the steelwork above the beam surface in the construction drawing issued by Party A, the formworker and the mason.

four. Contracting period:

1. Start-up time: 2007 month

2. Completion time: 2007 month

Fives. Standard costs:

1. Labor service fee is based on the actual construction area + 0.000 or more / 122 yuan per square meter

2. Party A entrusts Party B to complete the work outside the scope of contracting and negotiate with the on-site market price.

3. If a design change occurs during the construction of the project, the overall labor service is less than 2,000 yuan, and Party A does not make up another portion. The amount of change is more than 2,000 yuan. Party A will increase the labor service fee for change.

six. Engineering Quality

Under the arrangement of Party A engineering and technical personnel, the quality of the project must meet the eligibility criteria.

Seven. Fulfillment of margin and labor labor costs and payments:

1. Party B shall pay Party A a labor performance bond of RMB 10,000 yuan within one week.

2. Party A shall return Party B's performance bond to RMB 10,000 yuan within five days after the main body of the project is capped.

3. The main frame structure of the project will be completed on the fifth floor. Party A shall pay Party B's labor service fee at 85% of the total price, and settle the project volume on the 25th of each month, and pay 85% of the labor wage within the next five days.

4. The site has an average of 50 yuan per day in addition to the contract, and the technician is 70 yuan per day.

5. Party A shall enter Party B's labor wages into Party B's account, and Party B shall provide Party A with a labor fee receipt.

6. All labor service payments will be paid within one month after the completion of the project.

Eight. A. Party B's responsibilities:

1. Party B shall only provide one of the welding machines and the required “strands and nails for the construction of the project”, and the rest shall be the responsibility of Party A.

2. Party A shall provide the office and accommodation room of Party B personnel, the equipment and pots of the cafeteria.

3. Party B shall provide Party A's on-site management personnel for work and dining free of charge.

nine. Due to the reasons of Party A, the site was shut down, and Party A was expected to subsidize RMB 50 per person per day according to the on-site personnel.

ten. Site safety:

1. On the spot, according to the requirements of Party A, Party B personnel shall abide by the rules and regulations on site and achieve safe production and civilized construction.

2. Party B shall be responsible for the safety accidents occurred by Party B personnel in violation of the operating procedures.

person A person B:

Person in charge: Responsible person:

Phone: Phone:

Year, month, day, month, day

Note: This Agreement is in quadruplicate, and both parties shall hold two copies. This Agreement has legal effect.