Summary of XX year engineering construction and engineering supervision work



At the beginning of this year, according to the unified deployment of the investment center, I was arranged to work in the construction of XX consulting company. In the past year, under the correct leadership of the center and the manager of the company XX, I carefully grasped the intention of the superior, actively and creatively carried out the work; Responsibilities for posts, hard work on the knowledge of agent construction, and better completed the engineering construction and project supervision tasks arranged by the superior leaders. I will summarize my work in the past year as follows:
Summary of ××××year project construction and engineering supervision work
At the beginning of this year, according to the unified deployment of the investment center, I was arranged to work in the construction of XX consulting company. In the past year, under the correct leadership of the center and the manager of the company XX, I carefully grasped the intention of the superior, actively and creatively carried out the work; Responsibilities for posts, hard work on the knowledge of agent construction, and better completed the engineering construction and project supervision tasks arranged by the superior leaders. I will summarize my work in the past year as follows:
First, the construction work:
××× Street Reconstruction Project
This year, the number of key projects of the municipal management committee started, and the workload of the engineering department of the management committee is relatively large. In order to better strengthen the management of various engineering projects, the Chief of the Engineering Committee of the Management Committee decided to Responsible for the renovation of the XX Street, focusing on the on-site construction management of the project and the coordination work of the participating units. The XX ___ Street reconstruction project was held on the XX XX Day and the mobilization meeting was held on March ××. .
During this period, I compiled and completed the project management plan for the renovation of the XX Street, and carefully familiarized with the design drawings of the XX Street reconstruction project. I was familiar with the quality, schedule, and investment requirements of the project; The power distribution room of the supervisory office accounted for the demolition of the construction site, the demolition of the wall of the second rubber plant and the cutting of the roadside trees; coordination within the work. Arrange the municipal company to clean up the construction site, build the construction of the building, and construct the propaganda work for the safety and civilized construction signage on the construction site; urge the telecom engineering construction team to enter the construction as soon as possible to ensure that the entire project is completed as scheduled.
×月××日 organized the first site meeting, which arranged the construction period of each pipeline project, and negotiated with the construction and design unit on the elevation of the position of each pipeline crossing the road, and decided on the crossing problem. According to the actual situation, the solution is on site. Sign the safety and civilized construction responsibility letter with each construction unit. Cooperate with the person in charge of telecommunications engineering to determine the measures to speed up the construction schedule, and create conditions for the municipal rainwater pipeline project to start ahead of schedule.
During the implementation of the XX Street project, I organized all the participating units to carry out the construction drawing review and the intermediate acceptance work of the project, and coordinate the concrete work such as the construction process lap joints of the participating units, in order to ensure the quality and quantity of the project as scheduled. Upon completion, I have done a lot of coordination work between internal and external related units. The specific work is as follows:
I. External coordination work:
1 Coordination of the demolition work of the temporary power supply station of the ××× company, the demolition of the wall of the second rubber plant, and the tree cutting work of the garden center, so that the construction unit can enter the site as scheduled, remove the obstacles and provide the construction unit with a working surface.
2 Coordinate the planting center and the second unit of the district education committee to close the south gate and change it to avoid the impact on the construction.
3 Coordinating the quality supervision station to report quality supervision procedures, and the traffic brigade to handle the procedures for breaking the road.
4 Cooperate with the construction unit to do a good job of the propaganda card pattern, slogan design and coordination with the urban management brigade.
5 Coordinate the stone paving plan of the parking lot on the north side of Yixin Home, sign the paving agreement and pay for the project payment.
II. Internal coordination: In order to ensure the reasonable construction process of each pipeline project, to avoid mutual interference or repeated construction of each process, a large amount of internal coordination work has been done for each participating unit:
1 Coordinating the construction sequence of pipeline installation units such as electric power, telecommunications, Gehua cable, gas, water supply, and heat, and urged all construction units to enter the construction site on time. 2 Coordinating power and telecommunications to build cables to work in the ground. Construction starts on schedule to create prerequisites.
3 Participate in the unit project acceptance work organized by the supervision unit, contact the quality supervision station, invite relevant personnel to participate in the rainwater sewage project inspection, sewage pipe closed water test, road oil inspection and other work.
4 Coordinating the civilized construction and finished product protection work of all construction units. Because the construction site is located in the urban center, it is particularly important to cover the soil and cover the water and dust. Therefore, the XX municipal company is often urged to do the construction work on site.
5 Due to the coordination of the longitudinal and transverse pipeline positions of the pipeline construction units, there is no collision between the pipelines during construction and the excavation process to destroy the completed pipelines.
6 times to contact the municipal design office to change the construction drawings, participate in the development of pedestrian paving plans.
6 Coordinate the installation of street lamps and advertising light boxes, participate in determining the installation plane position, contact the trash can manufacturers, and arrange the installation on site.
In the implementation process of the XX Street reconstruction project, project quality, schedule, and investment management are particularly important. For this reason, I have done a lot of engineering management work:
Ø Quality control:
× In the process of quality control, follow the principle of adhering to the principle of quality first, adhering to the principle of human control, adhering to the principle of prevention, adhering to the principle of quality standards and the principles of science, justice and law-abiding, according to the relevant countries. And legal and regulatory documents related to quality management issued by relevant government departments, engineering contracting contracts, construction procedures,
The standards and methods of inspection and assessment related to the project and the design drawings, determine the quality control work program; adopt the quality control method combining pre-, in-, and post-control, quality control of the input material resources, quality control of the construction process, and The control of engineering product quality is focused on process quality control to ensure the quality of the sub-project and the quality of the unit project, thus ensuring the quality of the project.
Among them: ex ante control: require on-site supervision engineer to determine quality standards, establish quality supervision system, acceptance of construction site, review and approve the qualifications of each subcontractor, supervise the construction unit and improve the quality assurance system, check the quality of raw materials and semi-finished products used in the project, construction Mechanical quality control, review and approval of construction organization design, construction plan and start-up report of the construction unit, organization of drawing review and technical disclosure, review of construction unit management personnel, especially project managers, quality inspectors, construction workers and special types of workers Qualification to ensure the quality of the project input.
Control in the event: require the supervision engineer to pass the process control, process handover inspection, concealed engineering inspection and acceptance of the quality of the construction process; intermediate product quality control; sub-project quality assessment and acceptance; design change and technical negotiation; supervision order, payment Quality certification work to ensure the quality of the engineering conversion process.
After-the-fact control: Cooperate with the supervision engineer to ensure the quality of the project through the initial acceptance of the unit project, the quality assessment of the project, and the completion of the project.
× When conducting pre-existing control and in-process control, the quality of the input and output of the project is always ensured by controlling the five quality influencing factors of people, materials, machinery, methods and environment that affect quality.
Among them: the quality control of people, strict requirements for supervision engineers to check the employment certificates of various types of personnel and to prevent illegal operation; the quality control of materials is mainly for the material quality certificate through the written inspection of the incoming materials, the visual inspection of the incoming materials Physical and chemical testing of general test items for materials sampling and some other test items, and quality control of raw materials and semi-finished products; quality control of construction methods mainly cooperates with technical solutions, process flow and organizational measures adopted by supervision engineers for construction. The detection means and construction organization design are controlled, and the focus is on the approval of the construction organization design; the quality control of the construction machinery such as concrete mixer, mortar mixer and road roller is mainly for equipment selection.

Type, main performance parameters and operation requirements must be controlled to meet the needs of the project; quality control of environmental factors is mainly to control the engineering technology environment, engineering management environment and labor environment, the focus is on the quality assurance in the project management environment The system is controlled.
×, the main method of quality control
Strict process quality control
The supervision engineer is required to set the quality control point according to the importance of the process, pre-control and key control of the quality. During the construction process, the supervision engineer carries out quality monitoring. The key points of the control include: layer bed backfilling and rolling, road bed soft foundation treatment , the compactness of the road bed and the base layer, the deflection of the asphalt pavement; the bearing capacity of the drainage trench foundation, the layering compaction and compactness of the trench backfill; the bearing capacity of the foundation pit foundation, the grounding resistance of the street lamp, etc., the site supervisors are next to the construction site Station control, at any time to supervise the unqualified procedures that may occur in the construction process of the construction unit, predict the factors that may affect the quality of the process during the construction process, and pre-control the quality of each process. At the same time, we will focus on controlling the activities of process activities and the effects of process activities, strictly in accordance with the procedures for inspection and inspection, and insist on the inspection of the quality of the process on the basis of the inspection of the construction unit. The process of passing the inspection and acceptance can be carried out in the next process. Rework processing is strictly required for non-conforming products to ensure the realization of engineering quality objectives.
According to the test results of the compaction test of the roadbed, it is determined that the crushing height is reserved for the excavation section, and the phenomenon of over-excavation backfilling is eliminated.
According to the characteristics of rainy season construction, it is proposed to adjust the ratio of fly ash and lime mixing in the two-ash base layer to ensure the quality of the base layer.
The parallel detection method is used to detect the compactness of the road bed and the base layer, the flexural strength of the concrete pavement is detected in parallel, and the elevation of the road bed and the base layer is detected in parallel.
The dredging section adopts the supervision of the side station, and the cleaning of the original soil requires the construction unit to stop the dredging work and avoid unnecessary waste.
Ø Progress control:
The contract period of the road engineering project of this project is ×× days, the project starts on the day of ××××year×month××, and the completion of the work on the day of ××××year×month××, the total construction period×× days, meets the requirements of the contract period. Due to many factors affecting the progress of the project, there are a number of factors affecting the impact of the construction-related units, the impact of design changes, the impact of construction conditions, the impact of the contractor's own management level and the impact of various risk factors. Therefore, the focus of the supervision of the supervision organization of the project is to inspect and evaluate the progress of the project and supervise the construction progress of the project with local construction conditions to eliminate the impact of the contractor's own management level. In the elimination of the impact of the management level of the contracting unit, technical measures and contractual measures are mainly adopted. By timely processing the technical problems encountered in the project, construction conditions are created for the construction unit as much as possible; and the construction unit is urged to increase the input of resources through the supervision instructions. Construction process to speed up construction progress.
The main tasks of coordination with the supervision unit for progress control are:
×, organize professional supervision engineers to review the construction progress plan submitted by the construction unit, so that the total progress plan and the total contract period have a certain surplus time, so that the construction time schedule of each sub-project is coordinated with each other and meets the construction period. The overall goal of the request.
×. Assisting the contractor in implementing the progress plan, checking the key control points of the construction progress plan at any time, and dynamically understanding the implementation of the progress plan.
×, check and review the monthly and weekly progress plans submitted by the construction unit, and strictly carry out progress check according to the weekly progress plan, and adjust the progress at any time.
×, according to the characteristics of the project, set the node to focus on control. In order to ensure the realization of the project's total construction period goal, the overall progress is divided into two stages. ×月××Day requires that the construction must complete the construction of the drainage project and the construction of the base layer under the road bed. This goal requires control of the progress.
×, organize a site progress meeting, site meeting. Timely meetings will be held on various issues affecting the progress of the site, timely analysis, notification of project construction progress, improvement measures, coordination of projects that the contractor cannot solve
×, assist the construction unit to improve and improve the management level of the schedule. Regularly and at any time, check and compare the progress of the progress, and at the same time exchange our opinions and opinions with the construction person in charge to solve the existing progress problems.
Ø Investment control:
×, the project project investment × × × million.
×, the actual cost of the project:
About 10 million yuan for roads, pedestrian paving, drainage works, heat, gas, water supply, telecommunications, cable TV, electric power, street lighting, greening, transportation, etc.
The excess is caused by engineering design changes. For example, the original pedestrian pavement design is an ordinary cement brick, which is now changed to ×cm thick granite planing stone.
×, the main method of investment control:
Strict design change: For engineering changes, design revisions, etc., first conduct technical and economic rationality pre-analysis, and if necessary, the construction, design, and supervision of the three parties agree and submit to the owner for approval before implementation, when found and original investment control When there are major differences in the plan, report it to the owner in time and negotiate with the owner and designer.
Visa with strict cost control: All visas with economic expenses are carefully reviewed and required to be accompanied by the original basis, and will be valid only after being signed by the owner.
Do a good job in engineering measurement:
1 Engineering measurement according to the engineering measurement program.
2 Require supervisors to be familiar with the contents of each construction contract, master the principles and conditions of engineering measurement, and avoid cross-repetition measurement of engineering quantities.
3 Carefully review and review all kinds of measurement raw materials and documents, and require the supervision engineer to work with the contractor to conduct on-site measurement and measurement to ensure the accuracy of measurement.
4 Do a good job of monthly work to complete the project volume review.
5 Strictly control the principle that the project that has not passed the process acceptance is not measured, and the amount of engineering and technical treatment measures caused by the construction unit itself will not be measured.
Ø Safety and civilized construction:
The project management department of the project resolutely implements the safety production of “safety first, prevention first”
The policy is to strengthen the management of on-site safety and civilized construction, and supervise all parties involved in the construction of this project to conscientiously implement the national safety management regulations for construction projects and project legal persons to safety applications.
Relevant regulations of the work, take effective measures to prevent major personal injury and death accidents, major equipment safety accidents, create a safe and civilized construction environment, and achieve the goal of creating a safe and civilized construction site.
×, safety work focus:
1 Establish and improve the safety production system, combine the characteristics of the production site, carry out various inspections; urge the construction unit to increase investment in the safe and civilized construction of the production site, make the safety protection railings meet the safety requirements, the safety signs are conspicuous, and various materials and materials are stacked. Orderly, clearly marked, the surface of the civilized construction site is completely new, and the civilized construction is orderly;
2 Give full play to the role of the Convention on Construction Site Safety. Hosted a site safety production meeting. At the meeting, the construction units carefully reviewed the safety work of the unit, summed up the experience, and found out the shortcomings. Everyone was free to talk, learn from each other, exchange, learn, communicate, coordinate, reach consensus, unify opinions, and work safely in the future. The plan will focus on the key points and make overall plans. Do it with layout, inspection, and summary.
×, carry out safety production and civilized construction safety inspection. Since the commencement of the project, the project supervision department has actively carried out the construction site safety inspection activities, and carried out major inspections on the safety production and civilized construction of each unit. The construction unit has organized construction electricity, excavation machinery, special work certificates, and Heavy safety equipment, fire-fighting facilities, personnel code of conduct, hollow cover and frontier protection, team safety activities and other safety special inspections × × times, found and corrected many hidden dangers. Due to persistence

The pre-existing control eliminated the accident in the bud, effectively ensuring the long-term safe and civilized construction since the commencement of the project;
×. Strictly review the safety construction measures for major projects, important processes, hazardous operations and special operations. Strictly review the construction organization design of the construction unit and the safe and civilized construction, hazard sources and environmental protection measures involved in major technologies and on-site general layout. Participate in the review of major projects, important projects, dangerous projects, special operations, and propose safety management revision opinions or suggestions to make the construction plan more reasonable, more scientific, and easier to operate. A total review of construction plans and safety measures × copies;
×, strengthen the safety and civilized construction inspection, require the construction site to be fixed and managed, must be implemented
The safety passage of the work is unblocked, the materials are placed neatly, the safe operation rules of small tools and equipment, the material labeling plate are conspicuous and clear, the front edge protection, the hole cover plate is complete, the color is clear, and the production site basically reaches the “clear site of the finished work”;
×, supervise and inspect the construction safety and civilized construction situation of the construction unit, and promptly supervise the whole problem
change. Always adhere to safety supervision for on-site service, supervise and help the construction unit safety facilities in place, standardize the behavior of construction personnel, safety first, do a good job of safe and civilized construction, safety and construction progress go hand in hand to achieve safe production. In security management, focus on the use of helmets.
×, strengthen on-site inspections, find illegal operations, timely stop, find safety hazards in a timely manner, require supervisors to issue supervision engineer notices or work contact sheets for rectification within a time limit. For serious violations of the rules and serious threats to personal safety, the "Notice of Penalty Construction Violation" is issued for punishment.
×, strengthen on-site civilized construction management, urge the construction unit to do the construction site to cover the soil cover and sprinkle water and dust reduction work, basically do not cover the soil exposed on the construction site, no dust situation occurs; the site dregs can be transported in time, the construction site The materials are piled up neatly, the roads are clean and the construction site is in order.
The completion of project acceptance and transfer of the use of the unit is the last level to assess the performance of the agency construction work. Therefore, the completion of the project completion and acceptance work is the key to the construction work. In order to do this work, I have done a lot of preparatory work:
×, arrange the completion acceptance date, notify all relevant inspection units, clarify the acceptance criteria, review the construction technical data of the construction unit, and compile the completed drawings;
×, preparation of the summary report of the completion of the West Street project.
××× garbage transfer station, garbage room and waste recycling room project
In order to meet the Olympic Games and improve the living environment of the rural people in the ××× district, the People’s Government of ××× District decided to build a garbage room ××× rest in the ××× villages in the ××× district, and the garbage transfer Station × × seat, the project investment × × × × million yuan. The project began to be planned on ×××, and the site selection of the garbage transfer stations in each town began on ××××. The relevant construction units started construction, and the construction period was initially set at the end of the year.
In order to do a good job in the construction of this project, I carefully studied the construction drawings and was familiar with the project. Since the project is built in various towns and towns, it is necessary to coordinate the relevant personnel of the township governments, construction units, supervision companies and owners, etc. Therefore, the coordination work is huge.
Under the circumstances of doing a lot of coordination work, I compiled the “Management Measures for Construction of Garbage Transfer Station and Garbage House Project”, and reported it to the Municipal Management Committee and XX Consulting Company for approval and implementation.
During the project construction management work, I have done a lot of related work, especially the garbage transfer station project. Because there are no detailed construction drawings and general drawings, the specific projects such as the on-site fence, pavement, external network and guard room are me. The construction project manager confirmed on site and received unanimous approval from the owners, laying a good foundation for signing the contract for construction. Actively inspect and inspect the progress and quality of the construction of garbage houses in each village, and report the project status to the Municipal Management Committee of the Municipal Management Committee on the basis of the project briefing on a weekly basis to assist the supervision company in doing the engineering quantity measurement work. The towns in the construction of the house have been completed and accepted. At present, the acceptance of the garbage house project in X towns has been completed. It is expected that the acceptance of the garbage houses in the remaining ×× towns will be completed in mid-March.
Second, supervision work:
Due to the shortage of professional staff in the supervision company, the head office was responsible for optimizing the allocation of resources, and assigned me to work as the director of the project supervision project department of the ××× district landfill.
The Shunyi District landfill project was built in the ××× town of ××× District, covering an area of ​​××ha, and the daily garbage disposal was ××× tons, the service life was ××year, and the investment was RMB 100 million.
In the course of being the director of this project, I learned more about the project situation, arranged the supervision engineer to prepare the supervision rules, organized the internal work meeting of the supervision project department, checked the supervision work of the professional supervision engineer, and timely discovered and solved some practical problems in the supervision work; Weekly presided over the establishment of regular meeting sites, coordinated the relationship between the owners and the construction parties, and created favorable conditions for the smooth implementation of the project construction; carefully inspect the internal materials of the supervision, strive to synchronize the engineering materials with the construction, and prepare for the smooth handover of the project completion. Carefully review the construction organization design of the construction unit, promptly submit the unreasonable and non-conforming construction specifications, and instruct the construction unit to review and submit the inspection; actively carry out inspections on the construction site to ensure that the construction is inspected on the construction site every week×day. It is easy to understand the progress and quality of the project, and lays a good foundation for the coordination of three controls and two managements.
During the work of the director, he can better complete the tasks of this position, fulfill the duties of the post, and make the owners satisfied.
Third, other work
While striving to complete the tasks assigned by the company, I actively participated in the income-generating activities for the company, and completed the design work of the steel structure of the XX×X×Zuo marker, which generated more than 10,000 yuan for the company.
Participate in the continuing education activities organized by the company's office, strive to improve the professional quality, and save energy for better construction work in the future.
Fourth, lessons learned
As a new type of management mode, it is implemented in the country in the year of ××××. First of all, it reflects the separation of the functions of “investment, construction, management and use”, which can effectively avoid unauthorized expansion of construction scale and improve construction standards. , to increase the construction content and other behaviors, as well as the "three estimates of super-estimation, budget over budget, settlement over budget" to achieve the purpose of improving investment efficiency and management.
Secondly, the agent construction unit is highly professional and has high work efficiency. Due to the professional construction of the project, the agent has a professional team. They are familiar with the business, familiar with the market, and have a strong sense of cost savings. This kind of internal management is not only improving work efficiency but also saving costs. It makes the project supervision more "special". .
Again, it makes the division of power more "clear." After all, all the funds are allocated and managed by the financial department and the national treasury. The owner does not care about the money and construction. The agent can not see a penny. The project is not used by itself. It is truly tailored to prevent it. The bigger the project is, the more it overcomes the drawbacks of investment, construction, management, and use of “multiple integration”. The four powers are separated and mutually balanced, and the immunity to corruption naturally doubles.
From the above several perspectives, the construction management of the "agent construction system" is still relatively viable. Practice has proved that the implementation of the "agent construction system", the appropriate centralized and unified management of government investment projects is conducive to improving the professional level of government investment project management, and can play a positive role in controlling investment and improving investment efficiency. To this end, the "Decision of the State Council on Investment System Reform" proposes to accelerate the implementation of the "agent construction system" for non-operating government investment projects.
××× Engineering Management Co., Ltd. is engaged in the construction of such a large environment, which is enough to see the wiseness of the decision makers. However, due to the initial involvement of the company in the construction of the agency, there are still many experience in the construction of the construction, in the process of project management and internal and external coordination, etc.

High, the division of labor is not fine and so on. Therefore, there have been some mistakes in the construction work of this year. For example, in the construction work of the renovation project of the XX Street, there are many unrealistic situations in the construction schedule, the order of entry and the schedule of the pipelines. Phenomenon, especially power engineering, is self-designed and self-constructed. It has strong independence. During the coordination, we neglected the box change and the position of the shutter. The result was rework due to the box change and the unreasonable position of the switch. Redoing causes unnecessary waste.
In order to do a good job in the construction of government investment projects, we must be rigorous in our work. We should fully understand the requirements of the scope, duration, quality and other aspects of the project, and carefully analyze the relationship between the projects. Reasonably arrange the construction sequence, pay attention to the coordination work of the construction units, and make the project smoothly implemented under the condition of quality and quantity, and completed according to the project schedule. At the same time, we should also study the knowledge of engineering project management, improve the business level, and use the knowledge and information of science and technology, economic management, engineering management and other aspects to do the project construction work.