Unit project completion acceptance plan


Part 1: Unit project completion acceptance plan

I. Preparation for completion acceptance:

1. Finish the finishing project

The characteristics of the finishing project are sporadic, scattered, and small amount of engineering, but the distribution is wide. If not completed in time, it will directly affect the completion acceptance and commissioning and use of the project.

The project manager department should do a good job of finishing the project, find out the project at the end of the project in time, make a thorough check through the pre-check before completion, and compare the design drawings and the construction contract one by one to find out the key points of the missing project and the closing project. Work plans, interpenetrating construction; at the same time pay attention to the protection of finished products.

2. Preparation of completion acceptance data

The completion acceptance data and archives are an important basis for the completion and acceptance of the project. The project manager department should be fully accumulated and kept from the beginning of construction. When the completion of the inspection and acceptance, the functional departments should be catalogued and documented according to the relevant requirements of the government.

3. Pre-acceptance of completion acceptance

The pre-acceptance of the completion acceptance is to preliminarily identify the quality of the project, to avoid delays in the finishing of the project, and to ensure that the construction project is put into operation smoothly and the indispensable work is used. Through pre-acceptance, the remaining problems can be discovered in time and returned or reworked in advance.

Second, the basis for completion acceptance:

Completion acceptance basis mainly includes: construction drawings, construction contracts, drawing review records, design change orders, technical verification orders, current construction specifications and project quality, and completion acceptance data.

Third, the standard of completion acceptance:

The completion and acceptance of the project shall be completed in accordance with the construction drawings, construction contracts, drawings and audit records, design change orders, technical verification orders, current construction specifications and engineering quality acceptance specifications, that is, the indoor works are all completed, indoor and outdoor. The underground pipe network and the scattered water, open ditch, along the steps and the ramp are all finished, and the interior and exterior are finished; the site and structure are leveled within 2m, the obstacles are cleared, the road and the sewer are unblocked, and the water flow is bright, and the window is clear. Residential projects also require intercom systems, gas, etc. to be completed as much as possible.

Fourth, the completion acceptance program:

1. Project Manager Pre-Check

After the completion of the project, according to the project schedule, the project manager shall organize the relevant functional personnel of the project department to conduct the conditions and conditions for the completion of the project, and compare the requirements of the construction drawings, the construction contract and the current project quality acceptance specifications. Inspection and acceptance. It mainly includes whether the completed project meets the relevant regulations, whether the quality of the project complies with the current quality acceptance specifications, whether the completion data is complete, and whether the construction completion meets the construction drawings and usage requirements. For the defects of the appearance quality of the project, the empty surface of the decorative surface layer, the cracking, the mutual contamination between the finished products, the requirements for the use of functions, etc., the layer-by-layer, inter-stage, and carpet-by-floor inspections are carried out and an inspection record is formed. The inspection records are completed by the project quality inspectors. The project manager shall promptly organize the rectification of the defects or deficiencies detected, and complete the deadline.

After the project has been inspected and confirmed to complete the construction drawings and contractual provisions, and the completion acceptance criteria are met, the project department conducts a self-assessment of the unit project and fills in the “Completion Acceptance Notice” to report the company's chief engineer. See Appendix 2 for the completion acceptance notice form.

2. Company review

According to the application of the project department, the company's chief engineer organization engineering department and quality and security department carried out visual inspection of the completed project, and at the same time checked whether the completion acceptance data was complete and complete, and whether it met the relevant requirements of the government. For the defects or problems detected, the project manager is instructed to complete the rectification within a time limit. The company's functional departments provide guidance or assistance when necessary.

3. Completion report

When the self-evaluation result of the company's re-examination project department meets the requirements of the relevant national technical standards, the project department is responsible for filling out the unit project completion report. The completion report is signed by the company's legal representative and technical person in charge and stamped with the official seal, and submitted to the supervision unit. The quality level of the project is assessed. The project department will send the completion report signed by the supervising unit to the construction unit with the signature and seal signed by the chief engineer and legal representative of the supervising unit, and the application unit shall be completed and accepted.

4. Completion acceptance

Completion acceptance is organized by the construction unit. As the construction unit, it shall cooperate with the special inspection and organization organized by the construction unit; at the same time, participate in the acceptance group composed of the representatives of the survey, design, construction, supervision and other units and other relevant experts organized by the construction unit, complete the acceptance check of the project and report the project contract. Performance and implementation of laws, regulations and mandatory standards for engineering construction in all aspects of project construction.

Property transfer

First, the transfer of self-developed real estate

When the company's self-developed engineering project completes all the design drawings and contractual agreements, after the self-evaluation, accreditation, assessment, special acceptance, completion acceptance and various filing work, the company's chief engineer organization engineering department, quality and security department, project The department handed over the real estate company and the property management company at the same time, and filled in the real estate transfer order. The transfer order was signed by the real estate company and the property management company as the archival materials. The property delivery order is detailed in Schedule IV.

Second, the handover of purchased real estate

In principle, the property purchased by the company should be accepted by the real estate company. Before receiving, the quality and safety department shall be inspected for inspection and acceptance. The inspection records shall be kept by the real estate company as archives; for the real estate that needs to be refurbished, the chief engineer of the company shall notify the engineering department and the installation department to carry out the decoration. After passing the inspection and acceptance of the quality and safety department, Received by a real estate company. The real estate company should do some after-sales treatment for the purchased purchased property and hand it over to the property management company in time.


Part 2: Unit Project Completion Acceptance Program

According to the "Interim Provisions on the Completion Acceptance of Building Construction Engineering and Municipal Infrastructure Construction Project" and the current relevant laws and regulations, our unit has formulated the "Project Completion Acceptance Plan". Please supervise the quality and safety supervision station of the construction project of Limin Economic and Technological Development Zone, check the acceptance process and the quality behavior of all parties.

I. Relevant information of this project:

1. The contents of the design file and the contractual agreement have been completed;

2. The units have been pre-accepted by construction, design, survey, construction, etc., and the existing problems have been rectified;

3. Changes involving design files have been signed by the design department, and major changes have been reviewed and approved by the reviewing agency;

4. The construction unit has inspected the quality of the project and confirmed that the quality of the project complies with the relevant laws, regulations and mandatory standards for engineering construction, and has submitted a project completion report;

5. The supervision unit has evaluated the project, has complete supervision materials, and has submitted a project quality assessment report;

6. The survey and design unit has inspected the design changes signed by the design unit during the survey, design file and construction process, and has submitted a quality inspection report;

7. The project quality control data is verified by the construction unit and meets the requirements;

8. The engineering safety and functional inspection data have been verified by the construction unit and meet the requirements;

9. The technical internals of the selected projects above the special project have completed the relevant special acceptance procedures as required and are filed in the archives.

10. The project name is: , Building A: Building B: The construction area is m2, and the actual completed area is m2. The excess area has been completed according to the requirements;

11. Have the following files:

Unit construction permit

, major design change supplementary review submissions

Approved file of the planning department

Approved file of the fire department

Approved file of the environmental protection department

Archives Acceptance Archives

Indoor environmental test report

, unit engineering quality warranty

, engineering contract payment is not arrears proof

, "Residential Quality Warranty" and "Residential Instruction Manual" for commercial housing

Second, the organization of completion acceptance:

The construction unit is responsible for organizing and implementing the completion and acceptance work of the unit project of the project, and is supervised by the Limin Construction Quality and Safety Supervision Station.

The completion acceptance time is determined as: 9:00 on the day of 20XX; the location is:

Third, the inspection personnel:

According to the regulations, our unit has set up a completion acceptance group. The members include: the person in charge of the construction unit, the person in charge of the construction, design, supervision and other units, as well as the technical and quality leaders of the relevant units. Among the members of the acceptance group are civil construction, plumbing electrical and other installations. Professional professionals. The leader of the acceptance team is served by XXX. The specific list is as follows.

Fourth, completion acceptance criteria:

Completion acceptance criteria are national engineering construction mandatory standards, current construction acceptance specifications and related standards, design files reviewed and approved, and relevant laws, regulations, rules and regulatory filings.

V. Completion acceptance program and content:

1. The team leader of the completion acceptance team presided over the completion acceptance;

2. The construction, construction, design, survey, supervision and other units report in writing the quality of the construction of the project, the performance of the contract and the implementation of national laws, regulations and mandatory standards for engineering construction;

3. The acceptance components are examined and accepted in three parts:

And check the quality of the engineering entity;

And inspect the completion data provided by the parties involved in the construction of the project;

The spot check and test of the use function of the construction project include water pressure, power supply, discharge main ball, insulation resistance, grounding resistance, leakage trip test, layer height and squareness.

4. Conduct a summary discussion on the completion acceptance of the project, form a comprehensive acceptance conclusion for the completion and acceptance of the unit project, fill out the “Completion Acceptance Record for the Unit Project”, and sign the personnel of the acceptance team and seal the unit;

5. When serious problems are found during the acceptance process and the completion acceptance criteria are not met, the acceptance team will instruct the responsible unit to immediately rectify and declare that the acceptance is invalid, and re-determine the completion and acceptance of the project.

6. When the quality problem that needs general rectification is found in the process of completion acceptance, the acceptance group may form a preliminary acceptance opinion and fill in the “Completion Acceptance Record of the Unit Project”. The personnel of the acceptance team shall sign separately, but each unit shall not be stamped with the official seal. The inspection and acceptance team instructs the relevant responsible units to rectify and entrust the project leader of the construction and supervision unit to organize a review. After the rectification is completed, the official seal of each unit shall be affixed;

7. When the parties to the completion acceptance group cannot form a consensus acceptance check, if the negotiation fails, they shall report to the construction administrative department or the quality supervision agency for negotiation and ruling.

6. Commitment:

The project shall be submitted to the filing department for completion acceptance inspection within 15 days from the date of acceptance of the project, otherwise, all economic liabilities and legal consequences arising therefrom shall be assumed.


Part 3: Unit Project Completion Acceptance Program

First, the acceptance premise:

The various sub-divisions and sub-divisions of the project have been accepted and accepted.

If there are still branch projects that do not meet the acceptance criteria, this part of the project is not directly related to the function of the building main body. For example, outdoor greening and ventilation may be treated as “defects” after approval by the construction administrative department. After the acceptance of the unit project, a single acceptance will be carried out.

Second, the specific work of the acceptance premise is as follows:

1. The self-inspection certificate provided by the construction unit is complete and meets the requirements;

2. Relevant files that have been accepted and signed by the project supervision unit;

3, with the "construction engineering quality uniform acceptance criteria" GB50300 specified in the four unified tables and their recoverable files;

(1) Summary of division and sub-division project acceptance records

(2) Concealed project acceptance record summary table

(3) Use function and safety inspection inspection record summary table

(4) Summary table of sampling test test records on the construction site

(5) Summary of inspection and approval records for raw materials, equipment, components and purchased finished materials

(6) Other relevant archives

4. The construction unit writes a report on the construction process and submits comments to the supervision unit and the construction unit. The content should include the evaluation of quality management and safety management.

5. The supervision unit made the “Quality Evaluation Opinion Report”.

6. When the supervision unit and the construction unit confirm that the project has the acceptance conditions, the construction unit is instructed to issue the intermediate acceptance report of the division project to the supervision unit, construction unit, and quality supervision station. All units shall send qualified personnel to participate in the inspection and acceptance, and all participating units such as design and survey shall be notified by the construction unit.

7. The supervision unit fills in the acceptance conclusion in the four sheets, and the responsible person of the relevant unit signs and confirms and stamps the seal corresponding to the contract seal, and the acceptance program ends.

8. The completion of the unit project and the delivery of the city archives shall be completed by the construction unit.

Second, the acceptance criteria

1. Inspection batch qualified quality standard

(1) The quality of the main control project must be qualified after sampling inspection;

(2) The quality of general items shall be qualified after sampling inspection. Allowing items with certain deviations may have individual deviations. A maximum of 20% of inspection points may exceed the allowable deviation, but it may not exceed 150% of the allowable value;

(3) Have a complete construction operation basis and quality inspection record.

2. Substandard project quality standards

(1) The inspection batch included in the sub-project shall meet the standards of qualified quality;

(2) The quality acceptance record of the inspection lot included in the sub-project shall be complete;

(3) The parts and sections of the inspection lot shall cover the scope of the sub-project, and the parts that are not missing;

(4) The contents of the inspection batch acceptance record and the signatory shall be correct and complete.

3. Standards for the qualification of branch projects

(1) The quality of the sub-projects included in the sub-project shall be accepted and accepted;

(2) Quality control information should be complete;

(3) The inspection and sampling test results of safety functions in the sub-project shall comply with relevant regulations;

(4) Appearance quality acceptance should meet the requirements, mainly from the elevation, axis position, section deviation, surface defects and the presence or absence of water seepage.

(5) Requirements for data acceptance: It is necessary to have a complete list and sort the data into a book according to the list; the sub-item and inspection batch acceptance records are complete, other technical review materials are signed, the data is accurate, and there are no missing items; The number of test standards required, the signatory is qualified personnel who meet the requirements of the acceptance criteria, and the seal is consistent with the contract.

Third, the acceptance organization

1. In the contract stage or the parties involved in the construction, the supervisory unit organizes the relevant units to conduct on-site inspection and confirmation in the previous stage of the project image. In the process of inspection and confirmation, the list does not meet or does not meet the acceptance. The specific content of the conditions, and form a meeting minutes, the content of the inspection must determine the responsible unit or responsible person. Determine the pre-acceptance time.

2. Pre-acceptance is presided over by the supervision unit. The acceptance meeting must determine two contents, one is the content that needs to be rectified, and the other is the time for completion acceptance;

3. The completion acceptance of the unit project shall be presided over by the construction unit. Participants in this meeting must match the “responsible person” identified in each contract. The conclusion of this full conference should be “pass” or “not pass”. Passing means that the project has reached the eligibility criteria; if it does not pass, it means that the acceptance meeting of the same scale must be repeated again.

4. Comprehensive acceptance. This means that the building fully meets the requirements of both design and planning, and can complete the functions of planning and design and ensure safe use. The main projects include fire protection, lightning protection, greening, lighting, power supply, water supply, telecommunications, cable TV, sewage and municipal road interfaces.

5. Supervision and acceptance unit: Local construction project quality supervision station.