Construction and installation contracting contract (5)
Construction and installation contract
Employer: _____
Contractor:_____
In accordance with the "Contract Law of the People's Republic of China", this contract was signed by both parties and was strictly implemented.
First project
1. project name:_____
2. construction place:_____
3. Project Number:_____
4. Project scope and content: All construction area _____ square meters.
5. Project cost: The total construction cost of the construction project is RMB ___ yuan, of which: labor cost ___ yuan ____
Second project deadline
1. Date of commencement of construction: According to the quota of the period of time promulgated by the state, the contract completion date is as follows:
All works started on _______ day, and completed on ________.
2. The preparatory work before the construction shall be completed by the two parties in accordance with the provisions of Article 3 of the Engineering Agreement.
3. During the construction process, the construction period can be extended in the following cases. The extension of the time limit shall be negotiated by both parties in a timely manner, and the agreement shall be signed and reported to the relevant department for the record.
Forced to stop working due to irresistible human resources;
If Party A changes the plan or changes the construction drawing, it cannot continue the construction;
Because Party A cannot supply drawings, supplies, equipment or materials and equipment as required, and is forced to stop working, it cannot be smoothly constructed.
Article 3 Material supply
1. The materials required for all projects are handled in the following manner.
Special materials, integration, departmental materials, and mechanical and electrical products of the department and department are all purchased by Party A and supplied to the designated place of Party B. Other materials are purchased and supplied by Party B.
For the matching and departmental materials, Party B shall be responsible for handling the application, ordering, transfer and use, special materials and integrated mechanical and electrical products. Party A shall be responsible for the procurement and supply to the designated place of Party B. All other materials shall be purchased and supplied by Party B.
The contractor does not include the project, and all materials and equipment are purchased and supplied by Party A to the site or designated processing location.
other methods:________
2. The type, specification, quantity and entry period of materials and equipment supplied by Party A.
3. For complete sets of equipment and non-standard equipment, Party A shall be responsible for handling the application, ordering and processing, and the introduction of the established equipment shall be inspected by Party A before delivery to Party B. Party A entrusts Party B to undertake equipment ordering and non-standard equipment processing, and an agreement shall be signed.
4. If the materials required for the project cannot meet the engineering requirements due to the specifications, varieties or materials of the supply department, and must be replaced or processed by other specifications and varieties, the original design unit and Party A shall obtain the prior consent and be signed by the three parties. . The amount difference, price difference and processing fee incurred due to substitution or processing shall be settled according to the current regulations.
5. Any material that should be accompanied by a certificate of conformity must be verified by the supplier when entering the site; if there is no certificate of conformity, it must be used after the supplier has passed the test, and the test cost shall be borne by the supplier. As the construction unit or design unit requires retesting the materials with the factory certificate of conformity, the test cost shall be borne by Party A.
6. If the materials and equipment provided by Party A are not supplied on time, or the specifications and quality do not meet the requirements, they will not be resolved by the efforts of both parties, thus causing Party B’s losses, which shall be borne by Party A.
Article 4 Settlement of construction funds
1. The settlement method of all construction costs shall be handled in accordance with the following provisions.
Settled by reviewing the construction plan budget plus the increase or decrease of the change budget.
According to the construction drawing budget plus the dry coefficient, the package cost is settled, the expenses outside the scope of the package are covered, and the payment is made according to the relevant regulations.
According to the standard construction drawing, the unilateral cost will be settled, and the expenses outside the scope of the contract will be paid according to the relevant regulations.
The contractor does not include the project, and the labor fee is set according to the budget quota.
The bidding project shall be settled according to the bid price.
2. The payment and settlement methods for project funds shall be handled in accordance with the current regulations.
Article 5 Construction and Design Changes
1. Party B shall organize the construction according to the construction acceptance specifications and quality inspection standards and equipment requirements issued by the State, and all shall be qualified.
2. It is necessary to adhere to the construction according to the drawings, and no party may change the design at will. In case of the following circumstances, the work of the other party, such as work, rework, backlog of materials and components, construction strength and institutional transfer, shall be borne by the responsible party.
If any design is found to be wrong or seriously unreasonable during construction, Party B shall notify Party A in writing, and Party A shall agree with the original design unit within seven days to propose to amend or change the design file, after the agreement is signed between Party A and Party B. Quasi-construction.
During construction, if the design change exceeds the original design standard or scale, it should be re-approved according to the approval procedure before construction. After reviewing the project budget by the review office, the bank will review the investment and the agreement will be signed by both parties. construction. Otherwise, no one may force the construction.
During the construction, if the construction is suspended or slowed down in the middle of the construction, both parties shall make a custom-made project to the safety site.
During the construction, if Party A is found to be under-invested, the project progress payment cannot be paid on time, and the construction will be suspended or slowed down in the middle, and the losses caused to Party B shall be borne by Party A.
3. Party B shall strictly implement the concealed project acceptance system. After the concealed project is completed, it must be recorded and accepted before proceeding to the next process. Before the concealed project is concealed, Party B shall notify Party A to inspect. If Party A fails to check in time, Party B may check it by itself, fill in the hidden project inspection record, and send the record to Party A. After Party A checks the concealed project and meets the quality standards, the inspection fee shall be borne by Party A; if it does not meet the quality standards, the inspection fee shall be borne by Party B. Party B did not notify Party A to inspect and conceal the project by itself. The inspection fee shall be borne by Party B.
4. Both Party A and Party B shall encounter construction projects in the course of construction and shall report for approval according to the quota management method. The change budget attached to the change of the engineering agreement shall be sent to the bank in time for construction as the basis for settlement of the project.
Article 6 Completion Acceptance, Settlement and Warranty
1. Party B shall notify Party A of the acceptance date in writing on the date of completion of the individual project five days before the completion of the individual project. If Party A fails to participate in the acceptance on time, Party B shall notify Party B in advance to obtain the consent of Party B and set the acceptance date, but Party A shall acknowledge the date of completion. If you fail to participate in the acceptance on time, the management fees and losses incurred by the company shall be borne by Party A. And pay the overdue liquidated damages of Party B to one-tenth of the daily cost of the budget.
2. The completion of the completion of the project acceptance, within three days from the date of acceptance, Party B is handed over to Party A. If Party A cannot take over as scheduled, the loss of the project after acceptance shall be borne by Party A.
3. If the unit project in a project needs to be handed over to Party A separately, at the time of handover, both parties shall go through the intermediate acceptance procedures as the basis for the acceptance of the completion project of the unit.
4. In the completion of the completion of the project, if the quality of the project is found to be inconsistent with the regulations, Party B shall be responsible for the repair or rework without compensation, and shall be completed within the agreed measures and deadlines. After the experience is accepted, the transfer will be made. If the project is overdue, Party B shall reimburse Party A for overdue liquidated damages of one-tenth of a million per day of the budget.
5. The project has been basically completed. If a certain material or equipment cannot be resolved, the project cannot be completed on schedule. With the consent of both parties, the project can be completed and reduced, and the completion and acceptance of the completed project will be completed.
6. The acceptance of the completion project is based on the construction acceptance specifications, quality inspection standards and construction drawings issued by the state. In the case of completion acceptance, Party B shall provide Party A with the following files 10 days before the acceptance:
Increase or decrease the change file and other negotiation records;
Concealed project acceptance record and intermediate delivery acceptance record;
After the completion of the project, the as-built drawings shall be drawn. The construction unit shall make a description of the construction change on the original construction drawing and submit it to the construction unit for filing. If the project changes greatly, the construction unit may draw or commission the design unit or the construction unit to draw the as-built drawings.
7. After the completion and acceptance of the individual project, Party B shall belong to the industrial construction project within 15 days after the completion of the acceptance of the civil construction project. The completion settlement shall be sent to Party A for review within 30 days after the completion of the acceptance. Party A shall, after receiving the completion settlement, within 15 days of civil construction, the industrial construction shall be reviewed within 20 days. If no objection is filed at the expiration date, the appropriation bank shall approve the appropriation.
8. After the project is completed and accepted, Party B shall be responsible for the quality of the civil works for construction for one year. During the warranty period, Party B shall be responsible for the repair of quality accidents such as roof leakage, pipeline leakage, air leakage and blockage caused by the responsibility of the construction unit.
9. If the project is not experienced, Party A shall use it in advance or use it automatically, and Party A shall be responsible for the quality or other problems arising therefrom.
Article 7 Liability for breach of contract and arbitration
1. Since Party B’s liability is not completed according to the date stipulated in this contract, every one day overdue shall be repaid to Party A for overdue liquidated damages of one ten-thousandth of the budget. If it is not covered by the contractor, it shall be repaid to Party A for each day. Overdue liquidated damages of ___ of the budget labor cost of 10,000.
2. Party A and Party B shall not owe all kinds of payables for any reason, such as delaying payment, and paying the default payment of overdue payment according to the bank's short-term loan interest rate.
3. In the implementation of the rationalization proposal award and the advance completion award, both parties shall make an agreement in accordance with the relevant policies.
4. When a contractual dispute arises in the contracting of a construction and installation project, both parties shall consult in time. If the negotiation fails, either party may apply to the urban and rural construction committee at all levels or the competent department of the higher authorities at both levels for mediation; if it cannot be resolved, it may The people's court sued.
Article 8 Supplementary Provisions
1. In the budget review procedure, the construction unit shall submit the construction and installation project contract to the municipal construction project contract budget review office for review. If it is required for attestation, it may go to the district or county administration for industry and commerce at the location where the building is located for verification.
2. Prior to the signing of this contract, the construction preparation contract signed by both parties may be used as an auxiliary file of this contract. Letters, faxes, e-mails, etc. confirmed by both parties will be part of this contract and have the effect of a contract.
3. For the bidding project, the contract shall be signed in accordance with the "T______ City Construction Project Tendering and Tendering Temporary Measures".
4. Other matters agreed by both parties.
_______
_______
_______
_______
person A person B:___
Project leader: ______ Project leader: _____
Unit address: _________ Unit address: _________
Bank of deposit: _________ Bank of deposit: _________
Account number: ___________ Account number: ___________
Phone: ___________ Phone: ___________
Date of signing this contract: ____ years __ month __ day
Article 9 Contract Attachment File
1. Project list
2. All construction drawings.
3. Construction drawing budget.
4. A list of materials and equipment that Party A is responsible for.
5. Related agreements:
_______
_______
_______
_______
6. About the supplementary contract:
_______
_______
Article 10 The number of shares and the period of validity.
This contract is a ____ copy. Both Party A and Party B shall each submit one copy and submit a copy to the competent department of the two parties; the remaining copies shall be filed by Party A and the district and county administration for industry and commerce.
This contract is effective as of the date of signing by both parties. It expires after all projects have been completed and accepted and settled.
person A person B:________
Agent: ____ Agent: _______
____ years __month __ days ____ years __ months __ days
Employer: _____
Contractor:_____
In accordance with the "Contract Law of the People's Republic of China", this contract was signed by both parties and was strictly implemented.
First project
1. project name:_____
2. construction place:_____
3. Project Number:_____
4. Project scope and content: All construction area _____ square meters.
5. Project cost: The total construction cost of the construction project is RMB ___ yuan, of which: labor cost ___ yuan ____
Second project deadline
1. Date of commencement of construction: According to the quota of the period of time promulgated by the state, the contract completion date is as follows:
All works started on _______ day, and completed on ________.
2. The preparatory work before the construction shall be completed by the two parties in accordance with the provisions of Article 3 of the Engineering Agreement.
3. During the construction process, the construction period can be extended in the following cases. The extension of the time limit shall be negotiated by both parties in a timely manner, and the agreement shall be signed and reported to the relevant department for the record.
Forced to stop working due to irresistible human resources;
If Party A changes the plan or changes the construction drawing, it cannot continue the construction;
Because Party A cannot supply drawings, supplies, equipment or materials and equipment as required, and is forced to stop working, it cannot be smoothly constructed.
Article 3 Material supply
1. The materials required for all projects are handled in the following manner.
Special materials, integration, departmental materials, and mechanical and electrical products of the department and department are all purchased by Party A and supplied to the designated place of Party B. Other materials are purchased and supplied by Party B.
For the matching and departmental materials, Party B shall be responsible for handling the application, ordering, transfer and use, special materials and integrated mechanical and electrical products. Party A shall be responsible for the procurement and supply to the designated place of Party B. All other materials shall be purchased and supplied by Party B.
The contractor does not include the project, and all materials and equipment are purchased and supplied by Party A to the site or designated processing location.
other methods:________
2. The type, specification, quantity and entry period of materials and equipment supplied by Party A.
3. For complete sets of equipment and non-standard equipment, Party A shall be responsible for handling the application, ordering and processing, and the introduction of the established equipment shall be inspected by Party A before delivery to Party B. Party A entrusts Party B to undertake equipment ordering and non-standard equipment processing, and an agreement shall be signed.
4. If the materials required for the project cannot meet the engineering requirements due to the specifications, varieties or materials of the supply department, and must be replaced or processed by other specifications and varieties, the original design unit and Party A shall obtain the prior consent and be signed by the three parties. . The amount difference, price difference and processing fee incurred due to substitution or processing shall be settled according to the current regulations.
5. Any material that should be accompanied by a certificate of conformity must be verified by the supplier when entering the site; if there is no certificate of conformity, it must be used after the supplier has passed the test, and the test cost shall be borne by the supplier. As the construction unit or design unit requires retesting the materials with the factory certificate of conformity, the test cost shall be borne by Party A.
6. If the materials and equipment provided by Party A are not supplied on time, or the specifications and quality do not meet the requirements, they will not be resolved by the efforts of both parties, thus causing Party B’s losses, which shall be borne by Party A.
Article 4 Settlement of construction funds
1. The settlement method of all construction costs shall be handled in accordance with the following provisions.
Settled by reviewing the construction plan budget plus the increase or decrease of the change budget.
According to the construction drawing budget plus the dry coefficient, the package cost is settled, the expenses outside the scope of the package are covered, and the payment is made according to the relevant regulations.
According to the standard construction drawing, the unilateral cost will be settled, and the expenses outside the scope of the contract will be paid according to the relevant regulations.
The contractor does not include the project, and the labor fee is set according to the budget quota.
The bidding project shall be settled according to the bid price.
2. The payment and settlement methods for project funds shall be handled in accordance with the current regulations.
Article 5 Construction and Design Changes
1. Party B shall organize the construction according to the construction acceptance specifications and quality inspection standards and equipment requirements issued by the State, and all shall be qualified.
2. It is necessary to adhere to the construction according to the drawings, and no party may change the design at will. In case of the following circumstances, the work of the other party, such as work, rework, backlog of materials and components, construction strength and institutional transfer, shall be borne by the responsible party.
If any design is found to be wrong or seriously unreasonable during construction, Party B shall notify Party A in writing, and Party A shall agree with the original design unit within seven days to propose to amend or change the design file, after the agreement is signed between Party A and Party B. Quasi-construction.
During construction, if the design change exceeds the original design standard or scale, it should be re-approved according to the approval procedure before construction. After reviewing the project budget by the review office, the bank will review the investment and the agreement will be signed by both parties. construction. Otherwise, no one may force the construction.
During the construction, if the construction is suspended or slowed down in the middle of the construction, both parties shall make a custom-made project to the safety site.
During the construction, if Party A is found to be under-invested, the project progress payment cannot be paid on time, and the construction will be suspended or slowed down in the middle, and the losses caused to Party B shall be borne by Party A.
3. Party B shall strictly implement the concealed project acceptance system. After the concealed project is completed, it must be recorded and accepted before proceeding to the next process. Before the concealed project is concealed, Party B shall notify Party A to inspect. If Party A fails to check in time, Party B may check it by itself, fill in the hidden project inspection record, and send the record to Party A. After Party A checks the concealed project and meets the quality standards, the inspection fee shall be borne by Party A; if it does not meet the quality standards, the inspection fee shall be borne by Party B. Party B did not notify Party A to inspect and conceal the project by itself. The inspection fee shall be borne by Party B.
4. Both Party A and Party B shall encounter construction projects in the course of construction and shall report for approval according to the quota management method. The change budget attached to the change of the engineering agreement shall be sent to the bank in time for construction as the basis for settlement of the project.
Article 6 Completion Acceptance, Settlement and Warranty
1. Party B shall notify Party A of the acceptance date in writing on the date of completion of the individual project five days before the completion of the individual project. If Party A fails to participate in the acceptance on time, Party B shall notify Party B in advance to obtain the consent of Party B and set the acceptance date, but Party A shall acknowledge the date of completion. If you fail to participate in the acceptance on time, the management fees and losses incurred by the company shall be borne by Party A. And pay the overdue liquidated damages of Party B to one-tenth of the daily cost of the budget.
2. The completion of the completion of the project acceptance, within three days from the date of acceptance, Party B is handed over to Party A. If Party A cannot take over as scheduled, the loss of the project after acceptance shall be borne by Party A.
3. If the unit project in a project needs to be handed over to Party A separately, at the time of handover, both parties shall go through the intermediate acceptance procedures as the basis for the acceptance of the completion project of the unit.
4. In the completion of the completion of the project, if the quality of the project is found to be inconsistent with the regulations, Party B shall be responsible for the repair or rework without compensation, and shall be completed within the agreed measures and deadlines. After the experience is accepted, the transfer will be made. If the project is overdue, Party B shall reimburse Party A for overdue liquidated damages of one-tenth of a million per day of the budget.
5. The project has been basically completed. If a certain material or equipment cannot be resolved, the project cannot be completed on schedule. With the consent of both parties, the project can be completed and reduced, and the completion and acceptance of the completed project will be completed.
6. The acceptance of the completion project is based on the construction acceptance specifications, quality inspection standards and construction drawings issued by the state. In the case of completion acceptance, Party B shall provide Party A with the following files 10 days before the acceptance:
Increase or decrease the change file and other negotiation records;
Concealed project acceptance record and intermediate delivery acceptance record;
After the completion of the project, the as-built drawings shall be drawn. The construction unit shall make a description of the construction change on the original construction drawing and submit it to the construction unit for filing. If the project changes greatly, the construction unit may draw or commission the design unit or the construction unit to draw the as-built drawings.
7. After the completion and acceptance of the individual project, Party B shall belong to the industrial construction project within 15 days after the completion of the acceptance of the civil construction project. The completion settlement shall be sent to Party A for review within 30 days after the completion of the acceptance. Party A shall, after receiving the completion settlement, within 15 days of civil construction, the industrial construction shall be reviewed within 20 days. If no objection is filed at the expiration date, the appropriation bank shall approve the appropriation.
8. After the project is completed and accepted, Party B shall be responsible for the quality of the civil works for construction for one year. During the warranty period, Party B shall be responsible for the repair of quality accidents such as roof leakage, pipeline leakage, air leakage and blockage caused by the responsibility of the construction unit.
9. If the project is not experienced, Party A shall use it in advance or use it automatically, and Party A shall be responsible for the quality or other problems arising therefrom.
Article 7 Liability for breach of contract and arbitration
1. Since Party B’s liability is not completed according to the date stipulated in this contract, every one day overdue shall be repaid to Party A for overdue liquidated damages of one ten-thousandth of the budget. If it is not covered by the contractor, it shall be repaid to Party A for each day. Overdue liquidated damages of ___ of the budget labor cost of 10,000.
2. Party A and Party B shall not owe all kinds of payables for any reason, such as delaying payment, and paying the default payment of overdue payment according to the bank's short-term loan interest rate.
3. In the implementation of the rationalization proposal award and the advance completion award, both parties shall make an agreement in accordance with the relevant policies.
4. When a contractual dispute arises in the contracting of a construction and installation project, both parties shall consult in time. If the negotiation fails, either party may apply to the urban and rural construction committee at all levels or the competent department of the higher authorities at both levels for mediation; if it cannot be resolved, it may The people's court sued.
Article 8 Supplementary Provisions
1. In the budget review procedure, the construction unit shall submit the construction and installation project contract to the municipal construction project contract budget review office for review. If it is required for attestation, it may go to the district or county administration for industry and commerce at the location where the building is located for verification.
2. Prior to the signing of this contract, the construction preparation contract signed by both parties may be used as an auxiliary file of this contract. Letters, faxes, e-mails, etc. confirmed by both parties will be part of this contract and have the effect of a contract.
3. For the bidding project, the contract shall be signed in accordance with the "T______ City Construction Project Tendering and Tendering Temporary Measures".
4. Other matters agreed by both parties.
_______
_______
_______
_______
person A person B:___
Project leader: ______ Project leader: _____
Unit address: _________ Unit address: _________
Bank of deposit: _________ Bank of deposit: _________
Account number: ___________ Account number: ___________
Phone: ___________ Phone: ___________
Date of signing this contract: ____ years __ month __ day
Article 9 Contract Attachment File
1. Project list
2. All construction drawings.
3. Construction drawing budget.
4. A list of materials and equipment that Party A is responsible for.
5. Related agreements:
_______
_______
_______
_______
6. About the supplementary contract:
_______
_______
Article 10 The number of shares and the period of validity.
This contract is a ____ copy. Both Party A and Party B shall each submit one copy and submit a copy to the competent department of the two parties; the remaining copies shall be filed by Party A and the district and county administration for industry and commerce.
This contract is effective as of the date of signing by both parties. It expires after all projects have been completed and accepted and settled.
person A person B:________
Agent: ____ Agent: _______
____ years __month __ days ____ years __ months __ days
recommended article
- Demonstration text of commercial housing contract
- Construction project demolition house contract
- Demonstration text of construction project contract (2)
- Engineering construction supervision commission
- Qingdao Construction Project Construction Contract
- Room decoration commission
- Urban residential area owner management committee charter
- Shanghai Participatory Housing Agreement
- Shanghai Housing Sublease Contract Sample
- Shanghai housing rental (commercial housing pre-leasing)
- Construction Engineering Design Contract (3)
- Construction engineering technical consulting contract
popular articles
- Construction engineering survey contract
- Construction project demolition house contract (official model
- Construction project construction contract (general)
- Boasting words 2019
- MacArthur's famous sayings
- Funny quotes
- Lincoln's famous sayings
- Trusted quotes
- Missing childhood sentences
- Save your boyfriend's words
- Ministry of Construction, State Administration for Industry and Commerce
- a famous saying that overcomes setbacks
- Common English sentences
- Blessing Dad’s words
- Real estate mortgage loan contract
- Contract conditions for construction of water conservancy and hydropower civil engineering
- 2014 encourages the words of a lost person
- a good sentence for the motherland
- Construction project entrusted supervision contract (Chinese and English)
- The latest topic of chatting with girls
- Qingdao Construction Project Construction Contract
- Dedicated good words
- Putin's famous sayings
- Mandela’s famous words
- Philosophical words 2019
- Sad sentence
- English inspirational maxim
- Team construction contract (construction team)
- Say goodbye
- Temporary wall construction agreement