Summary of annual work of the Ministry of Electrical and Mechanical Services


Under the correct leadership of the company, 12 projects of Lushan Lake were carried out in an orderly manner. The following work summary was made in this year's design and electromechanical installation.
I. Project overview and XX design completion workload:
1. Overview of the project this year:
Projects being started: 1, 5#, 6#, 2, shopping center, 3, Lushan Lake Hotel site, 4, cable into the ground.
Projects under construction: 1, Wuhuwan residential, 2, theme shopping area, 3, clubhouse, 4, Tuanshan Road, 5, Huanhu Road, 6, Jiefang Road.
The project being swept out: Carina Plaza.
2. Design and construction design of this year:
Remarks: The construction area under construction is 325496.18m2; the total length of road construction is 5145.28m; the design area under construction is 1648557.57m2.
Second, this year's Laoshan Lake design management design content:
Under the general planning of Zhang Zong and the general manager of Fan Manager, the main work is as follows:
1. Complete the general planning of the Laoshan Lake and the detailed design management of the 5 and 6# grounds. The report construction is basically passed, and the 6# ground can be used for the next step.
1. Complete the management design management of the Laoshan Lake for the planning bureau construction.
3. The preliminary plan for the completion of the sewage drain pipe of the Laoshan Lake will be used for the general plan control of the future, which will become the main drain pipe of the land.
4. Complete the general design management of a-2# and 8#, and report to the Planning Bureau.
5. Complete the planning and design of the shopping center and its construction drawing plan, expand the initial design management, and complete the construction drawing design after the year.
6. Complete the design modification of the theme shopping area and the change management of the construction drawing.
5. Complete the planning and design of the newly added 5 mu of land and complete the construction drawing design management.
6. Complete the fine decoration design of the clubhouse and modify and manage the construction drawing design.
7. Complete the design management of the west road.
8. Complete the planning and design of the Huanhu Road and basically complete the construction drawing design management.
9. Complete the preliminary plan design management of the ecological park general plan.
10. Complete the 110kv high-voltage line into the ground design management.
11. Complete the design management of the 2# ground power supply line.
Second, the planning and preliminary design work:
1. The relevant units of the management complete the surveying and mapping line. The main contents are as follows: the release line, the fixed test and the control release point of the Huanhu Road; the west side road release line, the control release point, the current earthwork mapping; the Tuanshan Road control release point; the Penghu Bay control release point, Inspection line, outdoor handover earthwork mapping, increase project control and release point; shopping avenue control release point, inspection line; shopping center surveying, drawing, and so on.
2. Manage relevant units to complete geological exploration, such as: preliminary exploration and detailed survey of Huanhu Road, and supplementary survey of t17.
Third, the design site coordination:
1. Command and arrange site site changes, such as: Wuhu Bay Residence, Three Roads, Shopping Avenue, Square Sculpture, etc.
2, organize management to start the technical project of the construction project, such as: central garage, shopping avenue, Tuanshan Road.
3. Review the technical plan of the construction project and its deepening design, such as: deepening of residential windows and doors, residential smart and weak electricity.
4. On-site design and technical guidance, such as: model room and lobby.
Fourth, with the cooperation of various departments:
1. Directly participate in and arrange for personnel to cooperate with the Strategic Development Department for report construction, such as: review of shopping avenues, evaluation of shopping center experts, approval of Wuhuwan fire protection, and planning and construction of 5 mu of land.
2, direct participation and arrange personnel and marketing planning department to cooperate with sales, such as: shopping avenue area mapping, communication of design planning and design requirements, shopping avenue shop floor 21 renovation plan.
3. Cooperate with other departments of the company, such as: cooperating with the human resources department to select and recruit personnel in the engineering department, property housing and supporting facilities, contract related engineering bidding technical questions and so on.
V. Installation of projects under construction:
The on-site installation of Wuhu Bay is mainly based on Huanggong, and it is necessary to check the doubts, difficulties and key points in the installation technology.
1. Formulate, improve, and review equipment bidding technical standards, such as: 2# ground power supply equipment, club air conditioning equipment, swimming pool equipment, etc.
2. Technical review of equipment contracts, such as elevators.
3, on-site technical guidance, such as: Wuhu Bay smart household control box location and its wiring, on-site drainage pipe problems, shopping center construction and hydropower.
Sixth, internal organization management:
1. Formulate a design management system.
2. The training has just joined the work staff.
3. Strengthen team building and carry out collective activities.
The following aspects of XX years are mainly required to be completed:
1. Cooperate with the project to design and cooperate with Wuhuwan residential, shopping avenue, shopping center, three roads, cable into the ground, and the first phase of construction of 6#, on-site installation technical guidance and related work.
2. Complete the planning and design of a-2# and 8# plots and its 8# construction drawing design, ecological park planning and basic construction of the main construction drawings.
3. Improve and implement the design management system, and carry out comprehensive management of the progress, quality and investment of the design.
4. Strengthen the training of the reserve forces of the engineering and technical personnel of the Lushan Lake.
Work and suggestions for adjustments and improvements in the future:
1. After we send out the mail, we will send the postage personal postal postage, take the invoice, and then go to the financial report. With the expansion of the project, there are more correspondences and mails, so that it can not be effectively worked for many times. It is recommended that the mail flow be XX yuan, and the clerk should coordinate the regular account management.
2. In order to further improve the design management and carry out comprehensive management of progress, quality and investment, the current progress is directly managed by us, and the plan review center conducts quality review of the specifications. This year, the control and management of design investment is not enough. With the expansion of the project in the future, it is recommended that we also look for design and consultation institutions for design quality and investment.
3. At present, there is a general contractor for surveying and mapping and exploration and construction units. On the one hand, we have reduced many duplications such as signing contracts and increased the effectiveness of the work. On the other hand, its progress and quality have certain constraints. Suggestions: Another increase in surveying and mapping, exploration and general construction units, thus increasing our initiative. In addition, for the deepening of the design, the construction party can not complete, completed by the design consulting agency.
4. According to the design contact situation of this year, in order to reduce the contact of different projects to the same design institute and the management mode of strong matrix, it is recommended to design and increase personnel, especially the installation technology is comprehensive, and the professional management experience of Party A is more and more important.
5. At present, all aspects of the company's electromechanical installation are lagging behind. It is recommended that: 1 increase the management personnel of Party A with hydropower site management experience; 2 establish an electromechanical equipment installation management system; 3 formulate mechanical and electrical equipment installation equipment material plan and its procurement plan painting.