Water destruction project implementation plan
Part 1: Implementation plan for water destruction project
Two heavy rains on June 27 and July 13 caused serious damage to the town. In order to ensure the normal production and living order of the people, the flood disaster recovery and reconstruction work was initiated in the town. In order to effectively carry out the implementation of various tasks, combined with the actual situation of our town, this plan was specially formulated.
First, the overall idea
Guided by the scientific concept of development, we adhere to the people-oriented principle, give priority to safeguarding people's livelihood, make proper arrangements for the affected people and resume reconstruction work as the top priority of the current work, effectively organize the people, widely mobilize the people, rely on the people, and fully integrate Various resources, mobilize positive factors in all aspects, and quickly carry out disaster relief and self-rescue and post-disaster recovery and reconstruction work.
Second, the basic principles
Adhere to the principle of small disasters relying on ourselves, disasters relying on collectives, and catastrophic government assistance, adhere to the principles of government guidance, hierarchical responsibility, social mutual assistance, and self-rescue, adhere to the principles of scientific reconstruction, planning first, based on the current and long-term perspective, and insist on co-ordination. The principle of balancing, highlighting key points, rushing and slowing down, and overall advancement.
Third, the target task
Renovate the house.
According to the county civil affairs department, up to now, the whole town has been involved in 7 villages and 11 households with 18 households, including 6 households with 6 households and 2 households with 2 households. The whole resettlement will be implemented by the main leaders and departments of the town. The other households will be covered by the village. The damaged households will be repaired by the households themselves to ensure that the reconstruction tasks will be completed before the winter. All affected people have housing and warmth. winter.
Water damage infrastructure restoration work.
1. The water conservancy facilities are restored. In accordance with the principle of “who benefits, who repairs” and “first rush and slow down. Considering the current or the main flood season, it is not appropriate to build water conservancy on a large scale. Small projects are organized and revitalized by the village mobilization people; large projects are formulated by the water conservancy department. After the expiration of the period, the organization will resume the organization; for projects that affect safety and endanger the lives of the people, the town defense plan should formulate plans and pay close attention to risk management; for projects that seriously affect agricultural water use, each village should organize emergency repairs to ensure agricultural production water; safe drinking water The water damage project will report to the county leading group and strive for the organization to resume as soon as possible.
2. The transportation facilities are restored. In accordance with the principle of “grading responsibility”, the pass-through beneficiaries will repair themselves, and the village-level organization will repair the villages. The township will be repaired by the town, ensuring smooth roads and safe travel with the fastest speed and best quality to avoid safety. Accidents reduce more losses.
Agriculture fights against disasters and saves itself.
The agricultural sector should go deep into the production line, organize technical personnel to go deep into the field to propose constructive opinions on remediation and replanting of disaster-prone and unrecognized fields, and mobilize farmers to take time to replant and replant to vigorously develop late-season production, and minimize disaster losses. The agricultural insurance department should promptly verify the disaster situation, make timely claims, and win the trust of the people.
Fourth, funding guarantee
1. The town will allocate emergency funds to the villages: Longjing, Zifu, Taoling, Houshan, Archway and Siqiao each in the disaster-stricken villages, each of which costs 5,000 yuan each.
2. Consolidate project funds such as “one case, one discussion” financial awards.
3. Social donation funds.
4. Actively strive for funds.
The above funds are used for appropriate subsidies for housing reconstruction, infrastructure emergency projects, and fire prevention projects.
V. Job requirements
1. Strengthen organizational leadership. The main responsible persons of each village personally grasped, took the overall responsibility, clarified the tasks, implemented the responsibilities, and made every effort to ensure that the restoration and reconstruction work was completed on schedule;
2. Carefully organize and implement. The technical department should do a good job in design planning and implementation plan. The villages should carefully organize and implement, ensure the progress and quality of the project as required, and ensure the safety during construction.
3. Actively strive for the project. Relevant departments should take overall consideration from the perspective of the whole town, actively report to the post-disaster reconstruction project and major infrastructure construction projects, and comprehensively improve the flood control and disaster prevention capabilities and infrastructure construction standards.
4. Strict financial supervision. The departments of finance, auditing, and supervision should strengthen the supervision and management of funds to prevent and eliminate problems such as corruption, seizure, misappropriation and waste, and ensure openness and transparency and financial security.
5. Create a public opinion atmosphere. Make full use of the news media, increase publicity, carry forward the spirit of flood prevention and relief, timely summarize and publicize good experiences and good practices, encourage and encourage the cadres and people at all levels to work together, self-reliance, unity and mutual assistance, and strive for self-improvement to jointly win the overall victory after the disaster.
Part 2: Water Destruction Project Implementation Plan
First, the guiding ideology:
Guided by Deng Xiaoping Theory and the important thinking of the "Three Represents", we adhere to the people-oriented principle and regard the disaster relief work as the top priority of the current situation. We will make arrangements for the production and living of the victims and the repair of water and electricity infrastructure. Focus on mobilizing the people of the region to invigorate the spirit, strengthen confidence, strive to resist disasters, minimize disaster losses, and ensure the completion of the goals and tasks set at the beginning of the year.
Second, work measures and work arrangements
Established the "7.15" and "7.26" Water Destruction Restoration Leading Group
The district government set up a “7·15” and “7·26” flood disaster and water destruction project recovery leading group, which was appointed by the first secretary of the Central Committee and Zhou Yingchun District, and the chief deputy head of Yang Jianhua as the commander, deputy secretary Zhang Dianwen and Cao Xinhua. Deputy District Head, Li Hao Deputy District Head, Chen Luxiang as Deputy Commander, members: Wu Daiyou, Xie Kaifu, Yan Wei, Peng Xiong, Chen Jian, Liu Jianping, under the office, the office director is served by Xie Kaifu, Liu Jianping as the deputy director of the office .
working arrangement
In order to restore water-damage facilities as soon as possible and ensure the use of agricultural production water, according to the principle of “immediately slowing down and ensuring the focus”, the projects that are urgently needed to be repaired are divided into “two large blocks and three large pieces”.
1, two large blocks
1) Channel damage repair in Siqing Reservoir Irrigation District
The deputy secretary of the district party committee, the district head Zhou Yingchun served as the consultant, the deputy secretary of Zhang Dianwen served as the commander, the deputy head of Cao Xinhua as the deputy commander, Liu Jianping as the technical leader, and the technical members: Zhang Guangrong and He Mingming. The Siqing Reservoir Management Office is the responsible department.
2) Restoration of the Lushui River Water Destruction Project:
The secretary of the district party committee was appointed as the consultant, the deputy head of the district, Yang Jianhua, as the commander, the deputy head of the district, Li Hao, Chen Luxiang, and Wu Daiyou as the deputy commander. Liu Jianping is a technically responsible person and a technical member: Yan Pinghui and Mei Jianshe.
The two projects were completed by the end of August.
2, three large films
1) Shigaitang tablets
The township heads of the townships and towns are the administrative responsible persons of the jurisdiction, and Comrade Luo Xiaozhong is the technical leader. The technical members are Zhang Guangrong and He Mingming.
2) Huatang tablets
The township heads of the townships and towns are the administrative responsible persons of the district, and Comrade Zhong Guohua is the technical leader. The technical members are: Cheng Yu, Zhou Shaolin, Li Hongbo, Xu Bo, Huang Jun.
3) Lutang tablets
The township heads of the townships and towns are the administrative responsible persons of the jurisdiction, and Comrade Liu Jianping is the technical person in charge. The technical members are: Ping Pinghui and Mei Jian.
The administrative responsible persons shall make overall arrangements for the water damage restoration project within their respective jurisdictions, further increase investment in water destruction projects, vigorously guide farmers to invest in labor, actively organize labor storms to repair irrigation canals, and ensure the completion of work before the end of August. All technically responsible persons shall provide technical guidance in a timely manner to supervise the progress of the project and ensure the quality of the project.
Third, the next step of work
1. Continue to pay close attention to the rain and water conditions. Now our district is still in the main period. It is expected that in August, our district will be affected by 2-3 typhoons, and the possibility of floods still exists. Measures should be taken to minimize the damage to water conservancy facilities.
2. Strengthen leadership and make overall arrangements. The work involved in this repair work plan is mainly the water damage project that is urgently needed to be restored. For water-destruction projects that are not included in this restoration plan, all localities should combine water conservancy and winter repairs, make overall arrangements, and make early planning, early deployment, early implementation, and concentrate manpower, material resources, and financial resources to do a good job of water damage recovery.
3. For the "two large blocks and three major films" included in the restoration work plan, all relevant personnel and units must implement measures and increase efforts to ensure that the project is completed on time. The district committee and the district government will conduct spot checks to inform the slow-moving projects.
Part 3: Water Destruction Project Implementation Plan
Affected by this year's "5.22" and "6.18" Meilong heavy rainstorms, the storms and floods caused 19 towns and villages in our city to suffer different degrees of loss. Among them, towns and towns such as Baoxi, Lanju, Jinxi, Chengbei and Yanqi were seriously affected. The affected population was 159,000. People, direct economic losses of 437 million yuan.
Disasters such as house collapse, landslides, road collapse, and damage to water conservancy facilities have occurred in various parts of the city, especially the damage to water infrastructure. According to statistics, two heavy rains caused a direct economic loss of 70.53 million yuan in the city's water conservancy facilities, including 92.1 km of 1253 at the dike damage, 603 damage to irrigation facilities, and 7 hydropower stations. After the water disaster occurred, in order to ensure the early restoration of the water damage and water conservancy project, the water conservancy system fully launched the emergency response plan, and quickly set up six disaster prevention and relief leading groups to conduct a detailed registration of the city's water conservancy and water destruction projects, to beware of, dams, channels, The damage of drinking water forms graphic materials, which are registered and summarized into a book, laying the foundation for scientific and orderly restoration and reconstruction.
In order to ensure the rapid and rapid advancement of post-disaster recovery and reconstruction, and minimize the damage caused by disasters, Longquan has taken the following measures to restore the reconstruction of the city's water conservancy infrastructure:
The first is to further clarify the basic principles. In accordance with the principle of "guarantee the people's livelihood, preserve the whole, protect the production", "first focus, then general, first emergency, then improve". In the first time, we will concentrate on restoring the interruption of domestic water as soon as possible, and ensure that people's domestic water and farmland irrigation water return to normal.
The second is to further clarify the subject of responsibility. In accordance with the principle of “priority, improvement and improvement”, for the restoration of water conservancy projects of more than 80,000 yuan, or the permanent repair and reconstruction projects with technical difficulties, the water conservancy department shall be responsible for the implementation; for the repair funds of less than 80,000 yuan The emergency repair project shall be jointly implemented by the township and the village, and the water conservancy department shall be responsible for technical guidance.
The third is to raise funds through multiple channels. On the one hand, we will do our utmost to strive for the support of the Provincial Water Resources Department; on the other hand, we will integrate various project funds to ensure multi-channel investment; on the other hand, we will launch water-damage township people to work and rebuild.
The fourth is to further clarify the repair time. Strive to basically complete the repair and reconstruction of the main water-damaged water conservancy facilities in the city within 2 years; the water conservancy department will measure, design, price, and tender the water-damaged water conservancy projects in two batches from July 7 to August 31. jobs. The construction of some water-damaged water conservancy projects will be started before July 31, ensuring that the scheduled projects will be completed by the end of next year. Before December 31, the water-damaged water conservancy project repaired and rebuilt by the township will be led by the water conservancy department for inspection and acceptance, and will be subsidized according to a certain proportion.
Part 4: Water Destruction Project Implementation Plan
Due to continuous heavy rainfall in our town in June this year, the Tongcun Highway in the town was seriously damaged by water, especially from the South Bank to the Shiligang Highway, which caused serious damage, resulting in inconvenience to the production and life of more than 27,000 people in the town. . In order to completely eliminate the hidden dangers of road traffic safety and ensure the convenience of people's production and life, this plan is specially formulated:
I. Construction goals and tasks
According to the construction project of the city project, the construction started from July to September 20XX, and completed the repair of the water-destroyed road with the road from the South Bank to the Shiligang Highway of more than 1,000 meters.
Second, construction content and standards
From the South Bank to the Shiligang Highway, three road subgrades such as highway culverts were completed, and the total project price was 96,037.28 yuan.
Third, repair budget and fundraising
Repair budget: See attached file.
Funds Raising: The entire water-damaged road rehabilitation project is planned to have an investment of 96,037.28 yuan. You are requested to seek compensation from the central government for 60,000 yuan and the village level to raise 360,37.28 yuan.
Fourth, organization management
1. Organization. Under the guidance of the town government, Shangnanan Village is responsible for the specific implementation under the supervision of the people.
2. Strengthen supervision. Strictly follow the relevant national regulations for construction, strengthen financial management, and ensure the smooth implementation of the project in accordance with technical specifications.
3. Security management. Develop safety precautions to ensure completeness, responsible for implementing safety work, and regularly check the safety production of the project construction to ensure that the project does not cause safety accidents.
Two heavy rains on June 27 and July 13 caused serious damage to the town. In order to ensure the normal production and living order of the people, the flood disaster recovery and reconstruction work was initiated in the town. In order to effectively carry out the implementation of various tasks, combined with the actual situation of our town, this plan was specially formulated.
First, the overall idea
Guided by the scientific concept of development, we adhere to the people-oriented principle, give priority to safeguarding people's livelihood, make proper arrangements for the affected people and resume reconstruction work as the top priority of the current work, effectively organize the people, widely mobilize the people, rely on the people, and fully integrate Various resources, mobilize positive factors in all aspects, and quickly carry out disaster relief and self-rescue and post-disaster recovery and reconstruction work.
Second, the basic principles
Adhere to the principle of small disasters relying on ourselves, disasters relying on collectives, and catastrophic government assistance, adhere to the principles of government guidance, hierarchical responsibility, social mutual assistance, and self-rescue, adhere to the principles of scientific reconstruction, planning first, based on the current and long-term perspective, and insist on co-ordination. The principle of balancing, highlighting key points, rushing and slowing down, and overall advancement.
Third, the target task
Renovate the house.
According to the county civil affairs department, up to now, the whole town has been involved in 7 villages and 11 households with 18 households, including 6 households with 6 households and 2 households with 2 households. The whole resettlement will be implemented by the main leaders and departments of the town. The other households will be covered by the village. The damaged households will be repaired by the households themselves to ensure that the reconstruction tasks will be completed before the winter. All affected people have housing and warmth. winter.
Water damage infrastructure restoration work.
1. The water conservancy facilities are restored. In accordance with the principle of “who benefits, who repairs” and “first rush and slow down. Considering the current or the main flood season, it is not appropriate to build water conservancy on a large scale. Small projects are organized and revitalized by the village mobilization people; large projects are formulated by the water conservancy department. After the expiration of the period, the organization will resume the organization; for projects that affect safety and endanger the lives of the people, the town defense plan should formulate plans and pay close attention to risk management; for projects that seriously affect agricultural water use, each village should organize emergency repairs to ensure agricultural production water; safe drinking water The water damage project will report to the county leading group and strive for the organization to resume as soon as possible.
2. The transportation facilities are restored. In accordance with the principle of “grading responsibility”, the pass-through beneficiaries will repair themselves, and the village-level organization will repair the villages. The township will be repaired by the town, ensuring smooth roads and safe travel with the fastest speed and best quality to avoid safety. Accidents reduce more losses.
Agriculture fights against disasters and saves itself.
The agricultural sector should go deep into the production line, organize technical personnel to go deep into the field to propose constructive opinions on remediation and replanting of disaster-prone and unrecognized fields, and mobilize farmers to take time to replant and replant to vigorously develop late-season production, and minimize disaster losses. The agricultural insurance department should promptly verify the disaster situation, make timely claims, and win the trust of the people.
Fourth, funding guarantee
1. The town will allocate emergency funds to the villages: Longjing, Zifu, Taoling, Houshan, Archway and Siqiao each in the disaster-stricken villages, each of which costs 5,000 yuan each.
2. Consolidate project funds such as “one case, one discussion” financial awards.
3. Social donation funds.
4. Actively strive for funds.
The above funds are used for appropriate subsidies for housing reconstruction, infrastructure emergency projects, and fire prevention projects.
V. Job requirements
1. Strengthen organizational leadership. The main responsible persons of each village personally grasped, took the overall responsibility, clarified the tasks, implemented the responsibilities, and made every effort to ensure that the restoration and reconstruction work was completed on schedule;
2. Carefully organize and implement. The technical department should do a good job in design planning and implementation plan. The villages should carefully organize and implement, ensure the progress and quality of the project as required, and ensure the safety during construction.
3. Actively strive for the project. Relevant departments should take overall consideration from the perspective of the whole town, actively report to the post-disaster reconstruction project and major infrastructure construction projects, and comprehensively improve the flood control and disaster prevention capabilities and infrastructure construction standards.
4. Strict financial supervision. The departments of finance, auditing, and supervision should strengthen the supervision and management of funds to prevent and eliminate problems such as corruption, seizure, misappropriation and waste, and ensure openness and transparency and financial security.
5. Create a public opinion atmosphere. Make full use of the news media, increase publicity, carry forward the spirit of flood prevention and relief, timely summarize and publicize good experiences and good practices, encourage and encourage the cadres and people at all levels to work together, self-reliance, unity and mutual assistance, and strive for self-improvement to jointly win the overall victory after the disaster.
Part 2: Water Destruction Project Implementation Plan
First, the guiding ideology:
Guided by Deng Xiaoping Theory and the important thinking of the "Three Represents", we adhere to the people-oriented principle and regard the disaster relief work as the top priority of the current situation. We will make arrangements for the production and living of the victims and the repair of water and electricity infrastructure. Focus on mobilizing the people of the region to invigorate the spirit, strengthen confidence, strive to resist disasters, minimize disaster losses, and ensure the completion of the goals and tasks set at the beginning of the year.
Second, work measures and work arrangements
Established the "7.15" and "7.26" Water Destruction Restoration Leading Group
The district government set up a “7·15” and “7·26” flood disaster and water destruction project recovery leading group, which was appointed by the first secretary of the Central Committee and Zhou Yingchun District, and the chief deputy head of Yang Jianhua as the commander, deputy secretary Zhang Dianwen and Cao Xinhua. Deputy District Head, Li Hao Deputy District Head, Chen Luxiang as Deputy Commander, members: Wu Daiyou, Xie Kaifu, Yan Wei, Peng Xiong, Chen Jian, Liu Jianping, under the office, the office director is served by Xie Kaifu, Liu Jianping as the deputy director of the office .
working arrangement
In order to restore water-damage facilities as soon as possible and ensure the use of agricultural production water, according to the principle of “immediately slowing down and ensuring the focus”, the projects that are urgently needed to be repaired are divided into “two large blocks and three large pieces”.
1, two large blocks
1) Channel damage repair in Siqing Reservoir Irrigation District
The deputy secretary of the district party committee, the district head Zhou Yingchun served as the consultant, the deputy secretary of Zhang Dianwen served as the commander, the deputy head of Cao Xinhua as the deputy commander, Liu Jianping as the technical leader, and the technical members: Zhang Guangrong and He Mingming. The Siqing Reservoir Management Office is the responsible department.
2) Restoration of the Lushui River Water Destruction Project:
The secretary of the district party committee was appointed as the consultant, the deputy head of the district, Yang Jianhua, as the commander, the deputy head of the district, Li Hao, Chen Luxiang, and Wu Daiyou as the deputy commander. Liu Jianping is a technically responsible person and a technical member: Yan Pinghui and Mei Jianshe.
The two projects were completed by the end of August.
2, three large films
1) Shigaitang tablets
The township heads of the townships and towns are the administrative responsible persons of the jurisdiction, and Comrade Luo Xiaozhong is the technical leader. The technical members are Zhang Guangrong and He Mingming.
2) Huatang tablets
The township heads of the townships and towns are the administrative responsible persons of the district, and Comrade Zhong Guohua is the technical leader. The technical members are: Cheng Yu, Zhou Shaolin, Li Hongbo, Xu Bo, Huang Jun.
3) Lutang tablets
The township heads of the townships and towns are the administrative responsible persons of the jurisdiction, and Comrade Liu Jianping is the technical person in charge. The technical members are: Ping Pinghui and Mei Jian.
The administrative responsible persons shall make overall arrangements for the water damage restoration project within their respective jurisdictions, further increase investment in water destruction projects, vigorously guide farmers to invest in labor, actively organize labor storms to repair irrigation canals, and ensure the completion of work before the end of August. All technically responsible persons shall provide technical guidance in a timely manner to supervise the progress of the project and ensure the quality of the project.
Third, the next step of work
1. Continue to pay close attention to the rain and water conditions. Now our district is still in the main period. It is expected that in August, our district will be affected by 2-3 typhoons, and the possibility of floods still exists. Measures should be taken to minimize the damage to water conservancy facilities.
2. Strengthen leadership and make overall arrangements. The work involved in this repair work plan is mainly the water damage project that is urgently needed to be restored. For water-destruction projects that are not included in this restoration plan, all localities should combine water conservancy and winter repairs, make overall arrangements, and make early planning, early deployment, early implementation, and concentrate manpower, material resources, and financial resources to do a good job of water damage recovery.
3. For the "two large blocks and three major films" included in the restoration work plan, all relevant personnel and units must implement measures and increase efforts to ensure that the project is completed on time. The district committee and the district government will conduct spot checks to inform the slow-moving projects.
Part 3: Water Destruction Project Implementation Plan
Affected by this year's "5.22" and "6.18" Meilong heavy rainstorms, the storms and floods caused 19 towns and villages in our city to suffer different degrees of loss. Among them, towns and towns such as Baoxi, Lanju, Jinxi, Chengbei and Yanqi were seriously affected. The affected population was 159,000. People, direct economic losses of 437 million yuan.
Disasters such as house collapse, landslides, road collapse, and damage to water conservancy facilities have occurred in various parts of the city, especially the damage to water infrastructure. According to statistics, two heavy rains caused a direct economic loss of 70.53 million yuan in the city's water conservancy facilities, including 92.1 km of 1253 at the dike damage, 603 damage to irrigation facilities, and 7 hydropower stations. After the water disaster occurred, in order to ensure the early restoration of the water damage and water conservancy project, the water conservancy system fully launched the emergency response plan, and quickly set up six disaster prevention and relief leading groups to conduct a detailed registration of the city's water conservancy and water destruction projects, to beware of, dams, channels, The damage of drinking water forms graphic materials, which are registered and summarized into a book, laying the foundation for scientific and orderly restoration and reconstruction.
In order to ensure the rapid and rapid advancement of post-disaster recovery and reconstruction, and minimize the damage caused by disasters, Longquan has taken the following measures to restore the reconstruction of the city's water conservancy infrastructure:
The first is to further clarify the basic principles. In accordance with the principle of "guarantee the people's livelihood, preserve the whole, protect the production", "first focus, then general, first emergency, then improve". In the first time, we will concentrate on restoring the interruption of domestic water as soon as possible, and ensure that people's domestic water and farmland irrigation water return to normal.
The second is to further clarify the subject of responsibility. In accordance with the principle of “priority, improvement and improvement”, for the restoration of water conservancy projects of more than 80,000 yuan, or the permanent repair and reconstruction projects with technical difficulties, the water conservancy department shall be responsible for the implementation; for the repair funds of less than 80,000 yuan The emergency repair project shall be jointly implemented by the township and the village, and the water conservancy department shall be responsible for technical guidance.
The third is to raise funds through multiple channels. On the one hand, we will do our utmost to strive for the support of the Provincial Water Resources Department; on the other hand, we will integrate various project funds to ensure multi-channel investment; on the other hand, we will launch water-damage township people to work and rebuild.
The fourth is to further clarify the repair time. Strive to basically complete the repair and reconstruction of the main water-damaged water conservancy facilities in the city within 2 years; the water conservancy department will measure, design, price, and tender the water-damaged water conservancy projects in two batches from July 7 to August 31. jobs. The construction of some water-damaged water conservancy projects will be started before July 31, ensuring that the scheduled projects will be completed by the end of next year. Before December 31, the water-damaged water conservancy project repaired and rebuilt by the township will be led by the water conservancy department for inspection and acceptance, and will be subsidized according to a certain proportion.
Part 4: Water Destruction Project Implementation Plan
Due to continuous heavy rainfall in our town in June this year, the Tongcun Highway in the town was seriously damaged by water, especially from the South Bank to the Shiligang Highway, which caused serious damage, resulting in inconvenience to the production and life of more than 27,000 people in the town. . In order to completely eliminate the hidden dangers of road traffic safety and ensure the convenience of people's production and life, this plan is specially formulated:
I. Construction goals and tasks
According to the construction project of the city project, the construction started from July to September 20XX, and completed the repair of the water-destroyed road with the road from the South Bank to the Shiligang Highway of more than 1,000 meters.
Second, construction content and standards
From the South Bank to the Shiligang Highway, three road subgrades such as highway culverts were completed, and the total project price was 96,037.28 yuan.
Third, repair budget and fundraising
Repair budget: See attached file.
Funds Raising: The entire water-damaged road rehabilitation project is planned to have an investment of 96,037.28 yuan. You are requested to seek compensation from the central government for 60,000 yuan and the village level to raise 360,37.28 yuan.
Fourth, organization management
1. Organization. Under the guidance of the town government, Shangnanan Village is responsible for the specific implementation under the supervision of the people.
2. Strengthen supervision. Strictly follow the relevant national regulations for construction, strengthen financial management, and ensure the smooth implementation of the project in accordance with technical specifications.
3. Security management. Develop safety precautions to ensure completeness, responsible for implementing safety work, and regularly check the safety production of the project construction to ensure that the project does not cause safety accidents.
recommended article
- Equipment Management Implementation Plan
- Winter Fire Prevention Program 2019
- Collective wedding planning
- Guoxiaoxin Teacher Training Program
- Celebration program
- Supermarket 5.1 Promotions
- Establish a smoke-free unit implementation plan
- July 1 commendation activity plan
- New Year's event plan for 2019
- 2014 organization life meeting plan
- Company opening ceremony planning plan
- Village-level environmental sanitation improvement plan
popular articles
- Philosophical words 2019
- Hyun dance family impression sentence
- 2019 Christmas Eve event plan
- 2014 motivational phrase
- Grateful mother's words
- Blessing phrase
- Encourage words 2019
- Weibo's famous sayings
- Non-mainstream sentence 2019
- Spring Festival blessing
- Life motto
- Company activity planning
- Parental love
- Relieved words
- July 1st activity plan
- Good sentence excerpt 2019
- Space mood phrase
- In-house training program
- 2019 annual training program
- Respect the teacher's famous words
- Summer camp program for 2019
- 2014 Mall National Day Festival Plan
- Legal maxim
- Not afraid of failure
- Teacher's Day Program for 2019
- Distressed sentence 2019
- What I said to my father 2019
- Motivate employees
- Jiujiu Chongyang Festival Program in 2019
- College student business plan