Street City Construction Section 2019 Work Summary and 2019 Work Plan


In 2019, under the strong and correct leadership of the Party Working Committee and Office of the Street, Yucheng Street City Construction Section, under the care and guidance of the county construction committee, planning bureau, transportation bureau, municipal bureau and other related business departments, combined with the tenth of Daishan County. The spirit of the fifth session of the Second Committee, insisting on the scientific development concept as a guide, comprehensively implement xx's overall deployment of "314" for Chongqing's development and the spirit of the three committees of the third session of the municipal party committee, emancipate the mind, and create work with open thinking. Strengthen the study of political theory and successfully complete the tasks of the year. The work for the whole year of 2019 is summarized as follows:

I. Basic situation of urban construction work

Work division and cooperation, strengthen measures to ensure the normal development of urban construction work.

1. Formulated various systems of the Urban Construction Section, including the learning system, the attendance system, the clean and hygienic system, the supervision system, the commitment service system, and the work discipline. The attendance and attendance registration system was strictly enforced at work. Strengthen the theoretical study of employees and business knowledge learning 1-2 times a month. The establishment of the National General Language and Literature Work Leading Group to strengthen the promotion of Mandarin and the implementation of standardized Chinese characters ensured the normal development of the national language and writing work. Seriously carry out the "liberation of ideas, expand openness" discussion activities, organize employees to seriously find problems, and implement rectification measures, fully mobilize the enthusiasm, initiative and creativity of the work of the central staff, improve work efficiency, and complete all work The mission provides a good institutional guarantee.

2. Formulate assessments, clarify responsibilities, implement hierarchical management of departmental work, clear division of labor, implement at all levels, and responsibilities are in place. Each staff member implements a fragmentation responsibility system. According to the responsibilities of the department, the internal affairs group, the rural housing group, the urban construction group, the urban management group and the transportation group were established respectively. The office staff is required to perform their duties with due diligence, clear division of labor, strengthen the unity of office personnel, and ensure that all work can be completed on time and in good quality.

Do a good job in all aspects of urban construction.

1. Land acquisition, house demolition and resettlement work

Haihong Apparel Project: The land acquisition area of ​​the project is 23.664 mu, and the compensation for land acquisition and resettlement is fully completed.

Lion Flour Mill Project: The project held a hearing and compensation and mobilization meeting at the end of last year. This year, the compensation for land acquisition and resettlement of the project has been fully completed, and 8 people have been transferred from agriculture to non-agriculture.

Yuda Road Project: The reconstruction and expansion project of Yuda Road requires a total of 56.692 mu of land in Tianchi and Yuquan Village along the way. In the absence of land acquisition approval, in order to ensure the progress of the project, the urban construction department's innovative working methods completed the compensation and resettlement work in accordance with the compensation standard for land acquisition. Through a lot of patient and meticulous work, no one has petitioned and blocked the project. Smooth construction.

Guilin Dafa Project: The demarcation work has been completed.

Chaonan River Project: In order to meet the needs of the project, the Weinan River project needs to rent 15 mu of collective land in the four communities of Guanyin Village, Yucheng Street. In order to meet the needs of the project construction, the Urban Construction Section completed the land lease work within one week, which ensured the smooth construction of the project construction.

Yinquan Project: The land acquisition area of ​​the project is 15 mu. The compensation and resettlement work for demolition has been completed last year. Now, 16 people have gone through the procedures for agricultural transfer to non-agriculture, and the follow-up work for the relocation of households to coordinate the construction of land has been carried out.

Lingyun Rubber and Plastics Project: The land acquisition area of ​​the project is 23 mu. The compensation and resettlement work for demolition has been completed last year. This year, 53 people have gone through the procedures for non-agricultural transfer.

Chuanjiang Metal Fittings Factory Project: The land acquisition area of ​​the project is 31 mu. The compensation and resettlement work for demolition has been completed last year. This year, 30 people have gone through the procedures for non-agricultural transfer and completed the follow-up work of demolition and resettlement.

Domestic garbage dump project: Since the project is to build a sewage pipeline of about 3.5 kilometers long through Hufeng Village and Hualong Village, the Urban Construction Section has carried out land reclamation and grassland compensation for the day and night. The long-term meeting and the house-to-house measurement work have been successfully implemented.

Yashi Project: In order to stabilize the ideological sentiments of 13 dangerous households and prevent the contradictions from being handed over to higher authorities and leaders, the Urban Construction Section has held several coordination meetings for people to solve problems this year, and issued transitional fees for the moving out personnel on schedule. A request for the project solution for the county government was prepared.

Chengding Toll Station Project: Through the review of relevant road administration files, the problem of land construction that cannot be solved by Chengding Toll Station for many years has been solved. The toll station has been successfully relocated.

Hann Sunshine: Responsible for the emergency rescue work of the farmers in the Dawang community “Han En Sunshine. North City Mong Kok”.

Compensation and resettlement work for demolition of Wenfeng area: completed the investigation of the bottom.

Compensation and resettlement for demolition of Dawang Community Winery: completed the preparatory work and assisted the county demolition office to successfully solve the remaining problems of illegal demolition of four houses including Chen Suzhen.

The land acquisition compensation and resettlement work for the second phase of low-rent housing and the follow-up land lease for the first phase will be fully completed by the end of December.

2. Land requisition report work

This year, our department took over the land acquisition work of two projects, namely Zhengda Nonferrous Metals Parts Co., Ltd. and Puyuan Substation, and is now reporting various procedures.

Zhengfa Nonferrous Metals Factory Project: The procedures for land acquisition and approval have been completed. The compensation and resettlement for land acquisition and house demolition of the project will be started soon.

Puyuan Substation Project: Currently, the land acquisition and approval procedures for the project are being processed.

3. Residential construction work

Completed the construction of the ancillary facilities of the Xinsheng Village Lions Gate Residency, the Hufeng Village Taiping Bridge Residents, the Tianchi Village Reconstruction Residents, and the Datang Village Reconstruction Residents.

4. Construction of small towns

The area of ​​newly built, renovated and expanded houses in the town was 582,865 m2.

The completed urban housing area was 379,035 m2, and the built-up area was 1.5 km2.

The newly built town has a road area of ​​1900 m2.

The length of the drainage pipe in Jiancheng Town is 800m.

5. Construction and management of rural houses

This year, our department approved a total of 258 new, renovated and expanded farmhouses, occupying 7021 m2 of cultivated land, 6406.9 m2 of non-cultivated land, 8907.3 m2 of original homestead, and a construction area of ​​4,2048.5 m2.

Some houses that were restored and rebuilt in the “7.17” floods in the XX year of the year were inspected and accepted, and the housing approval procedures and confirmation rights were actively carried out for the victims.

Investigation and punishment of illegal construction: From September 19th to October 20th, the Urban Construction Section will take the lead and combine the four departments of the Territory Land, Agricultural Office, Economic Development Bureau and County Land and Planning to violate the law in the whole street planning area. Comprehensive clean-up of land use and illegal construction, involving 16 villages in the whole street. The objects of clean-up are mainly illegal land and illegal buildings such as enterprises, aquaculture, farmhouses, etc., totaling 719 households, including 455 households, 233 enterprises, and other land occupations. 31 households, covering an area of ​​5,937 mu, with a construction area of ​​590,000 square meters, the 719 households that have been cleared up are currently being published in the villages.

6, urban management work

Environmental sanitation management: Continue to implement a cleaning, second cleaning, three flushing, and four supervision systems for the town. And the reward and punishment system has been increased, that is, the monthly salary of the cleaners is temporarily deducted as 50 yuan for rewards and punishments, and every time a cleaning is found, the cleaning is not clean and 50 yuan. Since the implementation of the system, the cleanliness of the town has been significantly improved.

Municipal supervision and administrative law enforcement: All urban management personnel participated in the administrative law enforcement training organized by the Chongqing Municipal Committee, standardized and corrected more than 500 violations, and 6 administrative administrative procedures, a fine of 200 yuan, and adhered to the improvement of the Municipal Supervision Record and organized learning. The new "Chongqing City Appearance and Environmental Sanitation Management Regulations" was 6 times. The staff members have basically mastered the urban management regulations and uniformed for work.

Management of farmer's market: continue to implement one hour ahead of schedule, insist on people-oriented, civilized law enforcement, maintain the town and market order, standardize business behavior, explain and regulate the people who sell local products, and have not conducted an administrative punishment. .

Maintenance of municipal facilities: maintenance of street lamps 20 盏 / time, line 50 meters; dredging of lion and Puyuan sewer pipes; completed greening tree pruning and spraying and pest control work, and invested more than 100,000 yuan for lions, The expansion of the electric meter of the street lamp line in Puyuanchang Town was updated.

In order to welcome the 18th Shoe Fair, the Urban Construction Section took the lead in organizing relevant departments to implement a comprehensive comprehensive rectification of the urban and rural areas of the urban and rural areas, and achieved remarkable results, and was rated as an advanced collective by the organizing committee.

7. Road construction work

In the second year of the year, it was an important year for the Ministry of Communications to “fix the rural roads and serve the new countryside” and accelerate the pace of rural road construction to realize the comprehensive development of the city. After a year of hard work, the traffic construction project has progressed smoothly, the road maintenance has improved significantly, and the boosting effect of transportation on the economy has been further exerted.

Road construction

a. Determine the target of road construction tasks this year. In 2019, a total of 15.25 kilometers were reconstructed from the streets, of which 9 kilometers were continued in XX. In 2019, a new 6.25-kilometer rural road construction will be built, with a total investment of about 4 million yuan. In 2020, the county road project will be built 3.7 kilometers by the county transportation bureau. The implementation of these roads will build a well-off rural area for my street. New traffic has laid a solid foundation.

b. The construction of the Yingying Road and Xinpu Road subgrade will be completed in the first ten days of November; the Xinpu Road pavement project implemented by the County Transportation Bureau will be basically completed, and the concrete cushion of the Yingying Road pavement project will be basically completed. Pavement construction, road construction can be completed before the Spring Festival. Both roads are two lanes with a road width of 7 meters.

c. As of the end of November, the contracting work for the construction project of Longguan Road and Baitong Road will be completed. Longguan Road and Baitong Road were all rebuilt according to the standard of the four-level highway in the mountainous hills, with a total mileage of 4.9 kilometers. Longguan Road is a two-lane road with a road width of 7 meters. It has been discontinued since it was included in the planning area of ​​the New Town of the Western Region, and the settlement of the road has been completed. Baitong Road is a pedal lane with a road width of 4 meters and a total budget of about 700,000 yuan. The Baitong Highway Project is currently building a dam, and the roadbed earthwork project has been completed 70%. It is expected to be fully completed and accepted before the end of the year.

d. Completed the plan formulation, engineering survey and bidding for the construction of the rural main road from the Puyuan to the riverside. The total length of the reconstruction of the road section was 3715 meters. Puhe Road was rebuilt according to the standard of Grade 4 Highway of Mountain Ridge and Heavy Hill. It was converted into a two-lane road with a road width of 7 meters and a converted investment of 2.31 million yuan. Now the road reconstruction work has been put into construction and is currently under construction.

e. Organized and implemented the preliminary exploration and construction drawing design of the rebuilt project of Sunjiaqiao in Xinpu Road across the Nanhe River. Sunjiaqiao spans the Chao Phraya River. The original bridge is a three-span stone arch bridge. The original bridge deck is 4 meters wide. During the “717” flood disaster in XX, some of the side walls of the flood-washing bridge body were outwardly inclined. It is now a dangerous bridge; The bridge was redesigned into a double-span concrete girder bridge with a width of 7 meters. The bridge has been completed and the project budget is being organized by the County Transportation Bureau.

f. Coordinated the implementation of the relocation of power communication facilities for five rural roads including Tuanying Road, Xinpu Road, Yuda Tourism Road, Baitong Road and Longguan Road. The street has conducted on-site inspections with the relevant departments of the county five times, and the county government has coordinated two relocation work coordination meetings, and the relocation work has been effectively promoted.

g: Completion of the design budget and bidding for the pedestrian bridge of the Datang Wangjiayuan Pedestrian Bridge is currently under construction.

8. Highway custody work

In order to effectively promote the construction and management of rural roads, the streets further standardized the road construction and custody work, further improved the work incentive mechanism, and the road traffic work was vigorously promoted.

We have effectively grasped the daily maintenance of rural roads across the street. Villages with rural trunk roads have implemented 1-2 full-time maintenance personnel to implement rural road management and maintenance in their respective jurisdictions, ensuring smooth and smooth weather throughout the year. [nextpage