Tiancheng County People's Government

Report on the work of key tasks from January to May

County People's Congress Standing Committee:

The year 2005 is the last year of implementing the 10th Five-Year Plan, and it is also the key to consolidating and maintaining the good momentum of rapid economic and social development in our county. In order to conscientiously implement the spirit of the Third Plenary Session of the Tenth Committee of the County Committee and implement the tasks of the Third Session of the 12th National People's Congress, we will truly implement the “Five Major Strategies” and “Three Processes” of our county, and will now focus on the county government from January to May this year. The work report is as follows:

1. The agricultural and rural economy develops steadily, and the adjustment of agricultural industrial structure is further optimized.

Baicun Demonstration Project

The construction of “100 Village Demonstration Project” in our county, combined with the poverty alleviation direction of the whole village promoted by the province and the state, each village group arranged about 150,000 yuan for the construction of facilities such as leeches, biogas, roads and villagers' activity rooms. This year, townships and towns reported 197 villager groups that need to implement the “100 Village Demonstration Project”. The whole village promoted poverty alleviation projects. 10 villager groups were arranged in the province, and 9 villager groups were arranged in the state. A total of 19 villager groups in our county were arranged. In the next step, the situation reported by each township will be identified by village, and will be finalized before and after the province and the state approve the whole village to promote the planning and then implement the “100 Village Demonstration Project”.

Scale cattle raising

As of May 19, there were 58 cattle farmers in the county, and 8454 cattle stocks, including 35 households with 50 to 100 heads, 14 households with 101 to 200 heads, and 4 households with 201 to 300 heads; 5 households with 301 to 700 heads. The small-scale cattle farmers have risen rapidly, and the county has formed a beef cattle industrial zone with large households as the point and small households.

Bamboo industry cultivation

The bamboo pulp and pulp integration project of 308,000 mu of bamboo forest base has been planned to the Shantou block. Bamboo seedlings, fertilizers and labor costs are provided by Tianzhu Company. Farmers plant bamboo shoots according to technical requirements on the planned land, manage bamboo forests, and sell bamboo materials to Tianzhu Company at a price not lower than the protection price. The farmer's sales volume will be paid to the land owner according to the standard of 8 yuan/ton; in addition to the project of planting 80-100,000 mu of the core area of ​​Tianzhu Company, the local radiation-planning planting plan of 30,000 mu has been issued. In towns and villages, the required 1 million bushes of Mazhu seedlings were tendered and cultivated on January 31, 2005. A total of 5.306 million yuan of bamboo seedlings were required.

flax

In 2005, the county planted 33,540 mu of flax, of which 31,213 mu was received, with an estimated total output of 10.619 million kg. As of May 17, the newly built flax factory purchased 8.3 million kilograms of flax, paid 8.549 million yuan, and the average price was 1.03 yuan/kg. Runfeng Flax Factory purchased 480,000 kilograms of linen, payable 470,400 yuan, and paid 428,400 yuan. The price is 0.98 yuan / kg.

vegetables

In 2005, the county planted 51,410 acres of winter and early vegetables. At present, it has received 37,700 mu; the cultivation of the mid-shed facilities has completed 1,000 mu, and the varieties are pepper, tomato, cucumber, zucchini, etc., all of which are now on the market. Wholesale price: pepper 0.7 yuan / kg, cucumber 0.6 yuan / kg, tomatoes 0.8 yuan / kg, zucchini 0.5 yuan / kg.

Second, continue to promote the process of industrialization, and strive to create a platform for county economic development

Progress in the integration of bamboo pulp and paper

The “Pre-review Report on Project Construction Land”, which was reviewed and approved by the State and County Land and Resources Department, has been reported to the Provincial Department of Land and Resources and is currently under review; the “Environmental Impact Assessment Report for Construction Projects” commissioned by the Chinese Academy of Environmental Sciences was commissioned. The draft for comments has been sent to Tianzhu Company for final review, proofreading and revision, and strives to be approved in mid-May; the construction of raw material forest base for bamboo pulp production has been formally approved by the Provincial Forestry Department; the project construction commissioned by Kunming Nonferrous Metals Design Institute was commissioned. The Soil and Water Conservation Plan passed the review on April 22; the Project Water Resources Argument Program prepared by the Technical Consultation Center of Yunnan Hydrology and Water Resources Bureau was delivered in mid-May, and the Pearl River Water Resources Commission or the Provincial Water Resources Department can be invited to organize experts. Review and approval; At present, we have begun to select and identify senior management personnel and technicians in the construction and management of bamboo pulp mills nationwide, and started the first round of technical exchanges with the technical experts of foreign equipment manufacturers to be introduced.

Dairy Development and Dairy Processing Construction Project

At present, the multi-drinking milk company is carrying out the preliminary construction of the production site of the production base in Huludao, the village of Kuailu, Xinqiu Town; the water and electricity of the processing base are carried out in the village of Xujiazhai, the village committee of Miyang Town. The construction of roads, field houses and other projects is expected to achieve a one-stop operation of “production, addition and sales” during the year.

Foot drop marsh coal mine construction

As of April 26, the cumulative footage of Mitsui was 177 meters for the main shaft, 193 meters for the auxiliary shaft and 142 meters for the wind shaft. The accumulated investment was 9.5 million yuan. At present, through multi-party coordination, land acquisition, road repair and compensation for the original two illegal shafts in the mining area, the company has fulfilled the compensation according to the relevant national policies, but some local villagers still have no way to create trouble, which affects the whole to some extent. The progress of the project.

Shanxin Village Coal Mine Resources Integration Project

At present, various preliminary calculations and assessments have been completed. The state government agreed that Yunnan Petrochemical Corporation will build a Sanxincun coal mine and its corresponding transportation company in Tiancheng County based on the resources of Shanxin Village, and organize the implementation of the construction of the Shanxincun coal mine. The project started this year and the first phase of construction is 500,000 tons / year.

Planning approval and construction of industrial parks

First, during the "two sessions", the county government invited experts to conduct in-depth investigation and research on the construction of Tiancheng Industrial Park, and combined with the actual situation of Tiancheng industry, proposed the overall concept of Tiancheng Industrial Park. The second is to contact with the design and qualification units inside and outside the province, contact and compile the “Planning and Design of Tiancheng Industrial Park” and the “Feasibility Study Report”, and finally determine the cooperation with Kunming University of Science and Technology with Grade A design qualification. The planning and design of Tiancheng Industrial Park and the Feasibility Study Report cost 800,000 yuan. On May 13th, a cooperation agreement was signed with Kunming University of Science and Technology, which is expected to be completed by September 30th. The third is fund guarantee. In order to implement this work, the county people's government allocated a special fund of 500,000 yuan as the preliminary work fund to ensure the smooth progress of this work. From May 12th to 14th, 11 special professors from the Polytechnic University went to our county to conduct on-the-spot investigation and collection of information on the planning and feasibility report of the industrial park. The whole work is progressing smoothly. The planning and design and feasibility study report will be completed in early September, and it is expected to pass the provincial assessment and acceptance in October.

3. New progress has been made in infrastructure construction and the development environment has been further improved.

Municipal construction

1. Key planning

The recent construction planning and professional planning of the Western District: the planning of the Provincial Construction Department to Tiancheng for pre-planning research, as the Western District's recent construction planning, transportation system planning, water supply and drainage planning and other professional planning should be compiled under the guidance of the overall planning, so that According to the opinions of the Planning Department of the Provincial Construction Department and the planning experts, the three professional plans, such as the “Recent Construction Plan for the Western District of the County, the Water Supply and Drainage Planning of the County, and the Planning of the County Road Transportation System”, which were originally scheduled to be prepared at the beginning of the year, have not yet been carried out.

Planning of the administrative center and the hall: The administrative center is planned and designed by Yunnan Tianyi Design Company. The planned land is 280 mu. The original planning layout includes municipal buildings, halls, museums, trade unions, kindergartens and other buildings. The municipal building covers an area of ​​50 mu. The building is a five-storey, 22-meter-high curved modern building, including 59 departments of the county party committee, the people's congress, the government, the CPPCC, and various bureaus, with 1,030 people. The outdoor area includes evacuation plaza, parking lot, green water body, etc. The total construction area is 16680m2; the design of the hall is a two-storey 15-meter high modern building covering an area of ​​15 acres, including the conference center building, evacuation plaza and parking lot. The function of the conference center is: one large conference hall for 802 people; one conference room for 120 people; one for small and medium-sized conference rooms for 30-70 people; two for VIP lounges; two for reception rooms. The ground floor area is 4956.9m2 and the total construction area is 7673.9m2.

Reconstruction plan of the old city: The architectural style of the old city is mainly based on the imitation of Ming and Qing Dynasties. In the transformation, it adheres to the planning guiding ideology of “respecting history, taking care of reality and facing the future” and the idea of ​​restricting sporadic reconstruction and promoting contiguous development. The construction details of the Weng Road are determined to determine the current situation of the Weng Road route. The 26-meter overall expansion to the south is completed into a 53-meter county-level east-west main axis landscape avenue. In accordance with the principles of these two plans, the county government has strictly controlled the sporadic construction and reconstruction of the old city in the past two years.

Planning of the newly built Tiancheng Middle School: The Tiancheng Middle School Planning and Construction Leading Group passed the on-site reconnaissance site selection. The newly built Tiancheng Middle School site was fixed at the Xiaoshishe of the West District Renting House, with a planned land area of ​​300 mu. Please ask the Planning Department of the Provincial Construction Department to visit the site and consider it feasible. The Yunnan Provincial Surveying and Mapping Engineering Institute has been commissioned to test the topographic map of 1:500. It can be produced in mid-May. At present, various preparatory work is being prepared for the planning.

Fire Planning: At the end of 2004, Yunnan Huijing Planning and Design Company was entrusted to prepare the county town fire protection plan. The preliminary results have been completed and have not yet been reviewed.

2. Key project construction

Cultural and sports center project: As of the end of April, the main frame of A and B sections, brickwork, interior wall plastering, ground backfill, hydropower, etc. have been completed; door and window installation, indoor and outdoor decoration have not yet started; C section is completed. After some foundations, the work was stopped in October 2004 until now; the main frame of the D section, the concrete floor of the basketball court floor has been completed, the brickwork is finished 90%, the interior wall plastering is 85%, and the ground floor backfill is completed 95. %, the installation of water and electricity parts and pre-embedded pipe fittings is basically completed, and the installation of the platform plastering, floor and door and window, and indoor and outdoor decoration have not yet started. The steel frame part of the grid has been completed, the installation is completed 30%, the scaffolding has been completed, and the steel color plate has been shipped to the construction site warehouse. The exterior decoration entered the bidding program. The original plan was opened at the beginning of April, and was temporarily suspended due to the complicated situation; the E section completed the design drawings of the outdoor sports field and the grandstand. The AB section has paid 2.4 million yuan, the payment ratio is 65.38%; the section C has not paid the construction cost; the section D civil construction has paid 5 million yuan, the payment ratio is 62.3%; the steel structure is not paid.

Expansion project of the second water plant: The expansion scale of the second water plant was designed according to 30,000 tons/day and was constructed in phases. The recent project is implemented on a scale of 15,000 tons/day. The preliminary design estimate is 21.164 million yuan, including civil engineering, equipment procurement and installation engineering and water supply pipe network expansion. At present, the construction of civil engineering, equipment procurement and installation projects started. The bid price for civil construction construction was 5,211.8 thousand yuan, and the contract price for equipment procurement and installation project was 6,654,400 yuan, totaling 11.868 million yuan. The entire project won a total of 8 million yuan of national debt funds. . From the start of construction on June 6, 2004 to April 30, 2005, 95% of the total amount of civil works has been completed, and all equipment purchased by the water purification plant has been put into operation. The installation and commissioning of the equipment has been completed by about 60%. It was installed at the end of May and was completed and accepted at the end of June.

Construction of Qinglai Road: Qinglai Road was originally planned to be two roadways, a pedestrian street and four rows of commercial houses, totaling 113 meters wide, and planned to be a Ming-style style building. After the development and construction of the red tobacco enterprise, construction began in 2004, the roadbed has been completed, and road construction is underway.

Construction of the garbage treatment plant: The new site is selected from the loess slope 7 km away from the northeastern suburb of the county town. The scale is 220 tons per day, the storage capacity is 1.9 million tons, the service life is 20 years, and the estimated investment is 35 million yuan. At present, the environmental protection evaluation information has been sent to the provincial Environmental Protection Bureau, and the feasibility study has been sent to the Provincial Planning Commission. After the approval of the Provincial Environmental Protection Bureau, the Provincial Planning Commission will organize the feasibility study review and demonstration.

Construction of key towns: Zhuyuan Town Sanna Line renovation project total length of 750m2, total investment of 1.7 million yuan, asphalt pavement, started construction on October 16, 2004, completed on January 30 this year, has been put into use The construction plan of the town of Pengpu is doing preparatory work; the Xingfa Village of Xinshao Town has completed the revision of the plan.

Road traffic construction

1. West Third to the inspection and construction department of the township road construction

As of May 10, a total of 700,000 cubic meters / 109 kilometers of roadbed earth and stone, 1053 cubic meters / 133 culverts, 7384 cubic meters / 54 walls, 115 kilometers of roadbed completion, 70,000 square meters / 20 kilometers of concrete pavement, completed 2200 investment Ten thousand yuan, the capital in place was 15.1 million yuan. The construction of each tender is underway and is expected to be completed and open to traffic at the end of December 2005.

2. Construction of the third-grade highway from the inspection department to Xiaolongtan

Inspection Department - Kaiyuan Xiaolongtan Highway, with a total length of 38 kilometers, is designed as a three-level mountainous and heavy hill road, with a roadbed width of 8.5 meters and a road width of 7.7 meters. The design information has been reported to the State Transportation Bureau for review. The project is being surveyed and set up by the Provincial Highway Planning and Design Institute, with a total investment of 120 million yuan. The project is expected to start construction in September 2005.

3. Rural road construction

As of May 10, the county has started construction of 72 rural roads, 124.104 kilometers, of which 50 have been completed, 83.99661 kilometers. The county has 3,0365.4 tons of cement. In 2005, the government executive council decided that the county should arrange construction tasks of 60 kilometers of bullet stone road, 60 kilometers of gravel road and 20 kilometers of cement road. The specific subsidy standard is 200-300 tons of cement per kilometer of cement road, and every kilometer of bullet road The subsidy fund is 30,000 yuan, and the subsidy fund per kilometer of gravel road is 10,000 yuan, and the remaining insufficient funds are raised by the relevant towns and villages.

Water conservancy facility construction

1. Construction of “five small” water conservancy projects

As of May 12, the county has built 1,517 “five small” water conservancy projects, including 11 dam ponds and 1,506 pools, which solved the problem of drinking water for 16,167 people and 3215 large livestock. On April 13, 2005, the thirty-eighth executive meeting of the county government decided that the county government should concentrate on subsidizing the construction of small households in the townships and towns of the mountainous towns and villages from 2005. At present, the special poverty-stricken households without family waters are subsidized by the county. A family of leeches, the subsidy standard is 1,000 yuan / month. The poverty-stricken households in the mountainous areas of the towns and villages in the dam area shall be subsidized by 500 yuan per household of the county finance. If the subsidy is to be increased, the township shall solve the problem by itself. The original subsidy standard of 500 yuan/person has not been implemented since 2005.

2. Construction of key projects under construction

Hongxi Drainage Tunnel Project: The total length of the tunnel is 4084.21m, and the estimated total investment is 26,847,900 yuan. The project started construction on December 26, 2003. By the end of April 2005, the tunnel footage was 2344.87m, and the total length of the tunnel was 64.37%. The accumulated investment was 11.319 million yuan, the capital in place was 8.03 million yuan, and the gap was 18.81 million yuan. From January to April, the tunnel footage was 585m, and the investment was 1.78 million yuan, and the funds in place were 2.23 million yuan.

The project of the Dahebian branch canal in Miyang Irrigation District: the total length is 9.369km, and the estimated investment is 18.36 million yuan. The project started construction on May 28, 2004. By the end of April 2005, the investment was 11.81 million yuan, the funds were 4.37 million yuan, and the shortfall fund was 1390.07. Ten thousand yuan. From January to April, the investment of 3,325,900 yuan was completed, and the funds in place were 2.38 million yuan. It is expected to be completed in July.

Channel anti-seepage project in the lower section of Zhupengba Donggou: The lower section of Zhupengba Donggou is 18.05km long, with an estimated investment of 13.2096 million yuan. It will be completed by the end of January this year, and the tailing project will be carried out from February to March. The completion data is being prepared. carry out. The project has a capital of 3.835 million yuan and a gap of 937.46 million yuan.

Xiaobai Temple Shagou Flood Control Project: The total length is 1,560m. Construction started on November 5th, 2004. It was completed on January 25th this year and completed on April 26th. The final investment was 1,128,200 yuan, the capital in place was 200,000 yuan, and the gap was 928,200 yuan.

3. Construction of the reservoir reinforcement project

Baiyun Reservoir Reinforcement Project: The Preliminary Design Report has been approved by the State Water Resources Bureau with a total investment of 25.08 million yuan. Source of funds: 70% of the central subsidies, 30% of the state and county support, and the matching ratio of the state and the county is 4:6. The county government is required to raise 4,541,400 yuan and start construction within this year. In mid-April, the county government promised to the state people's government that the county-level matching funds for the Baiyun Reservoir reinforcement project will be fully and in place on time.

Reinforcement and Reinforcement Project of Fenhe Reservoir and Renting Reservoir: The Preliminary Design Report of the Reinforcement Project of Fenhe Reservoir has passed the expert review on August 14, 2004. The estimated total investment is 11.5072 million yuan, which will be approved. The feasibility study report of the “Safety Appraisal of the Renting Reservoir Dam” has completed the feasibility study report, with an investment estimate of 46.723 million yuan. It is currently reported to the Ministry of Water Resources for project approval and is expected to be implemented during the 11th Five-Year Plan period.

4. Construction of grape water saving irrigation efficiency demonstration project

The project uses drip irrigation to design an irrigation area of ​​755 mu. The Provincial Water Resources Department approved an investment of 2.86 million yuan. Among them: the central subsidy of 1 million yuan, the provincial supporting 500,000 yuan, the state supporting 300,000 yuan, the company promised to raise funds of 500,000 yuan. The preliminary work of the project is ready.

Fourth, around the "big investment, big development" strategy, investment promotion work has achieved results

Actively mobilize and organize enterprises to participate in the “2005 Yunnan High-quality Ecological Agricultural Products Promotion Exhibition” and “Yunnan-Guangdong Key Project Promotion Conference”. On March 30th, the organization of the Star Repair Shop and the Zhuyuan Lotus Farmers Market participated in the “Yunnan-Guangdong Key Project Promotion Conference” held in Kunming, laying the foundation for the next step of attracting investment and seeking partners in Guangdong; April 1 From the 3rd to the 3rd, “2005 Yunnan High-quality Ecological Agricultural Products Promotion Exhibition” was held in Shanghai Exhibition Center, and two enterprises including Yunnan Red Wine Factory and Tiancheng County Agricultural Machinery Promotion Center were organized. At the meeting, the products were sold out by Shanghai consumers due to their good quality. Currently, he is actively preparing to participate in the work of the Kunming Fair. The main exhibiting products are Yunnan Red Series and Sugar Series.

On the basis of the original preparation of 26 investment projects, 17 investment projects were reorganized. Use state government organizations to study in Ningbo, Taizhou and Jinhua City, Zhejiang Province to study and attract advanced opportunities for investment promotion. When contacting foreign businessmen and receiving visits, interviewers and other foreign exchanges, we will actively cooperate with enterprises to find bridges, find funds and partners for enterprises, and introduce foreign businessmen to start businesses in our county.

Seriously do a good job in tracking and statistical reporting of project implementation. Timely and accurate grasp of the implementation of investment promotion projects in our county, understand the operation status of the project, production value, profit, taxation, carefully track, keep abreast of the latest developments.

Actively do a good job in land coordination for Kaiyuan Lvbao Biotechnology Consulting Co., Ltd. to negotiate the dioscore deep processing project in Pengpu Town of our county.

V. Increasing capacity for sustainable development

Rural energy construction

In the 38th executive meeting of the county government in 2005, one or two biogas ecological demonstration villages were built in each township. The construction rate of the biogas digesters in the demonstration villages should reach 80% or more. It is agreed to further accelerate the development of rural energy biogas construction work. As of May 13, the county has built 787 biogas digesters, rebuilt 30 households, and built 214 square meters of rural solar water heaters.

Safety production work

First, increase safety production education and training, and strengthen the awareness of safety production at all levels and departments and related enterprises; second, do a good job in basic work and create conditions for the work of safety supervision. The county government signed 50 annual safety production target responsibilities with 50 townships, departments and related enterprises, including 175 full-time safety officers and 1565 part-time safety officers, and signed road safety with drivers of different models. The responsibility book is 11,388; the third is to actively carry out special rectification of safety production work to prevent and reduce the occurrence of safety production accidents; the fourth is to promptly investigate the safety accidents that have occurred and urge the rectification of existing safety hazards. From January to April this year, there were 34 production safety accidents in the county, up 78.95% year-on-year; 28 people died, up 154.55% year-on-year; 32 people were injured, down 22% year-on-year; direct economic losses were 862,648 yuan, up 58.44% year-on-year. .

Labor export

From January to May 2005, after extensive publicity and multi-party mobilization, the county realized 33 export of organizational services. The reasons for the slow progress of labor export work and low performance are as follows: First, there is insufficient understanding of the importance and urgency of labor export work. Second, the propaganda was not in place and the labor export situation was not fully opened. 3. Insufficient contact with labor service units in the field, unable to combine the skills of the labor force of the county and the skill requirements of the employer, and timely and extensively develop a large number of workers who meet the skills needs of the market. Fourth, the tracking service is not in place, and the output personnel have a low employment rate. Fifth, the skill training of export personnel is out of line with the skills requirements of market employment. Sixth, some employers and professional intermediaries have deceived migrant workers from time to time, causing ideological obstacles and psychological burdens for migrant workers and their families.

"Eleventh Five-Year Plan"

The Implementation Opinions on the Preparation of the 11th Five-Year Plan for Tiancheng County has been formulated. The pre-planning research work has been carried out in an all-round way, and major project screening and demonstration work is being carried out. According to the industrial orientation and industrial layout of the province and the industrial structure adjustment of our county, the project reserve is continuously adjusted, enriched and improved. At present, there are more than 80 project reserves. In 2005, 15 key construction projects were reported to the State Planning Commission. 16 work items. More than 50 key construction projects such as bamboo pulp and paper integration, squatting hydropower station, drinking dairy dairy industry development, new whistle bamboo lignite development, and grape beverage development will serve as the basis for the preparation of the 11th Five-Year Plan. At present, we are working hard to carry out the implementation plan and major research of the 11th Five-Year Plan.

6. Coordinated development of all social undertakings

Education career

1. Teacher quality improvement project

On March 10th, the county-level secondary school went to Yunnan Normal University to participate in the talent exchange meeting. The county-level secondary schools have signed recruitment contracts with 50 foreign undergraduate students. From January to March, the county carried out 2,450 teachers' continuing education training. The new curriculum concept trains 70 people, selects 2 teachers to participate in the provincial high school campus network technology training, and conducts an information technology education courseware production training course, and trains 54 teachers.

2. Comprehensive education reform

We will comprehensively promote the reform of the school personnel system with the core of “teacher appointment system and performance distribution system”. The "Teacher Appointment Program" and the "Principal's Public Election Plan" were further revised and improved, and the "Implementation Opinions on Accelerating the Development of High School Education" and "The Moral Education Work Facilities Program" were drafted. At present, the faculty and staff performance distribution system operates smoothly.

Analyze and study the development of education and plan the development of high school education. In accordance with the "Tenth Five-Year Plan for Education in Tiancheng County and the Long-Term Development Plan for 2019", in order to ensure the realization of the goals of the project, the school's opinions and suggestions on the development of high school education are widely heard. On the basis of in-depth research, the “Project on New Tiancheng Middle School” was drafted. At present, the newly built Tiancheng Middle School has entered the preparatory stage.

Constantly adjust the optimal education structure and promote the healthy and coordinated development of various types of education. First, continue to do a good job of adjusting the layout of China's small school points. Up to now, the county has adjusted and retracted 250 small schools in China. 22 village committees have achieved the goal of only one complete national small school and no teaching points. Second, vigorously promote the development of vocational education. The vocational education center is in the process of preparing for the provincial demonstration school. The Weinan Wenwu Vocational School plans to invest 20 million yuan, requisition 80 mu of land, expand the campus and school buildings, and the project is under construction. The third is to stabilize the 146 villages. Cheng Technology School, actively use the rural technology school to improve the scientific and cultural quality of farmers.

3. Reform of dangerous buildings in schools

Since the beginning of this year, the investment in the construction of small school buildings in China has reached 12.23 million yuan, of which, the payment of the arrears of the project was 8,956,900 yuan; the construction in the previous year was 2.474 million yuan; the new construction project was 800,000 yuan. In April, the county's China Small Drainage Program was drafted. The county has arranged a crisis of 5 million yuan. Determining the 13 schools for the project, the hazardous area is 5960m2.

Accelerate tourism development and promote the development of national cultural industry

1. Increase the development of tourism resources. In 2005, the development of ethnic cultural resources in Keji Village of Xisan Town was taken as a key task of tourism development, fully integrated into Axi cultural resources and folk customs, and the production of national folk embroidery and handicrafts was promoted by the development of tourism resources. Development of crop, aquaculture, processing and other industries.

2. Strengthen tourism publicity and development work. From April 26th to May 1st, dispatched personnel to accompany the provincial delegation to Vietnam, Sabah, and Hanoi to participate in tourism promotion conferences. At the promotion meeting, various tourism publicity materials of our county were well received by the majority of travel businesses, and more than 300 travel brochures such as “Tiancheng National Culture”, “Nanfu Fudi Tour Tiancheng”, hotels and scenic spots were distributed.

3. Strive to build the Tiancheng Buddha culture brand. In order to further promote the Buddha culture of our county, from February 14 to 16, 2005, the "Buddha and Yunnan Culture Seminar" was held at Jinding Hotel. Through this activity, the buddha culture of our county was vigorously promoted, so that more people can understand Tiancheng and understand Tiancheng, laying a good foundation for better building the Tiancheng Buddha cultural tourism brand.

4. Do a good job in the pre-work of star rating for hotels and hotels. Strictly in accordance with the relevant standards, the two-star Jinding and Jinxiu hotels were pre-worked for the star-rated review, and the assessment of the provincial star review was conducted.

From January to April 2005, the county received 292 overseas tourists, with 358,300 domestic tourists, an increase of 119% year-on-year; the total tourism revenue was 5,966,600 yuan, a year-on-year increase of 67%, of which: foreign exchange income was 106,000 US dollars.

Deepen the reform of radio and television culture

First, actively do a good job in the ideological work of the staff, so that the workers' minds are not chaotic, the work is not chaotic, and all work is carried out in a stable and orderly manner; the second is to seriously organize the county radio and television bureau, the finance bureau, the land bureau, and the audit bureau to do a good job of clearing production. Nuclear work. At present, the work of clearing and producing nuclear resources has come to an end; the third is that the county radio and television industry reform leading group went to Dali, Lijiang and Chuxiong on April 7-9 to conduct inspections on radio and television business and learn from the experience of reform; fourthly, drafted "Tiancheng County" The Radio and Television Bureau Reform Plan and the "Tiancheng County TV Station Reform Plan" will be implemented after the adoption of the county radio and television industry reform leading group. It is expected that the reform of the broadcasting and television culture will be completed by the end of May.

The director, deputy director, and deputies, the above is the main situation of the county government's key work from January to May. We believe that under the correct leadership of the county party committee, under the supervision of the county people's congress and the joint efforts of the people of the county, the key tasks of the government this year will be smoothly implemented and successfully completed.

thank you all!

Tiancheng County People's Government

May 19, 2005