Work report > implementation plan

Land consolidation project implementation plan


Second, the project status

1. Basic information of the project

The project area is located in the northwest of Chongren County and southeast of the Heshang Town Government. It is 8 kilometers away from Chongren County and 5 kilometers away from the Heshang Town Government. It involves Yuanjia Village and Ganfang Village in Heshang Town. The project is east to Chongren-donglai highway, west to Shi Niu Ganfang Village, south to Zuogang water, and north to Jingkeng Village. The latitude and longitude coordinates are east longitude 116°02′03′′-116°05′21′′, north latitude 29° 49'34"-27°52'09". The total area of ​​the project area is 248.96 hectares, including 192.17 hectares in Yuanjia Village and 56.79 hectares in Ganfang Village. The total investment of the project is 3.07 million yuan.

2. Project benefits

2-1 function and economic benefits

The comprehensive area of ​​248.96 hectares of land in the project area can add 29.22 hectares of cultivated land, which is expected to increase the annual output value by 394,500 yuan.

After the original cultivated land has been sorted by land, the grain production cost of the hectares of farmland will be reduced by about 200 yuan, the production and production will be reduced by about 10 songs, and the total cost of grain production per hectare will be reduced by about 500 yuan. The original cultivated land can reduce the production cost by about 93,200. yuan.

After the project area has been landed, the farmland infrastructure conditions of the original cultivated land have been improved very well. One season of rice can be changed into double-season rice, and winter crops can be planted. It is estimated that the original cultivated land can increase the output value per hectare by RMB 0.225 million. The annual output value can be increased by 419,300 yuan.

2-2 Social Benefits

Land use controls can be strengthened to give landowners long-term social benefits.

Through land consolidation, the unused land was fully utilized, and the land utilization rate increased from 91.40% to 96.92%.

The area of ​​cultivated land has been increased from 186.35 hectares to 215.57 hectares, and the newly added arable land area is 29.22 hectares, accounting for 11.37% of the total land area of ​​the project.

Through the arrangement, the water conservancy project network covers 186.35 hectares, which improves the irrigation conditions, improves the quality of cultivated land, and reduces the input of the original cultivated land.

2-3 ecological benefits

Before the consolidation, the scattered and disorderly plots were changed into standardized fields that were integrated into the shape of the plastic, and the level of mechanization and land intensive use was improved.

Establish farmland shelterbelt network, change the status of previous Shaolin or Wuweiwu forest, improve forest coverage, and effectively enhance wind and sand fixation and reduce soil erosion.

The situation of rural roads with unevenness and crooks has been changed, and a road network that facilitates mechanized farming and pedestrian management has been established, which has improved the network level of roads.

3. Source of funds

The total funding of 3.072 million yuan is funded by the state

4. The purpose and significance of the project

4-1 Give full play to the potential of land resources, protect the ecological environment in accordance with the principles of ploughing and ploughing, and make the farmland basically level to the same level, and establish high-standard and high-efficiency farmland.

4-2 Improve agricultural infrastructure conditions, improve roads and ditches systems, and transform fields with different shapes and sizes into standardized fields, which is conducive to land use control, improve mechanized operation level and land intensive scale utilization effect, and realize land. Sustainable use of resources.

4-3 Improve soil water and fertilizer conditions, improve farmland quality, adjust agriculture and crop structure, implement intensive scale management and management, and increase the output rate of cultivated land.

4-4 Through the planting of farmland shelterbelts such as roadsides and ditch edges, the forest coverage rate in the area will be improved, the wind and sand fixation effect will be enhanced, the ecological environment in the area will be improved, soil erosion will be reduced, and the sustainable use of land resources will be realized.

Third, the overall goal of project construction

1. Through the comprehensive consolidation of ditch, field, water, forest and road, the construction of 248.96 hectares of land consolidation will be carried out, so that the fields of different shapes and sizes will become “Tian Chengfang, Xicheng Net, Shuchengxing, and Roads”. Standardized ecological agriculture parks.

2. Improve the road network in the project area and complete the construction tasks of 1950 meters of trunk roads, 5,610 meters of field roads, 2,580 meters of branch roads, 14970 meters of production roads, 12 machine-grown bridges, and 6 artificial bridges. Improve the transportation capacity of agricultural materials and agricultural products, and facilitate the mechanized production of agricultural products;

3. Newly and improve farmland water conservancy facilities, build a total length of 35,760 meters of ditches, 1,070 water culverts, and 1 control gate to ensure the drought and flood protection of farmland;

4. Complete the planting work of 11,750 farmland shelterbelts, planted according to the standard of 3 meters and 1 plant, to achieve the functions of preventing wind and sand, improving ecological environment and reducing soil erosion.

5. Actively do a good job in the adjustment and distribution of land tenure, and achieve the goal of sorting out one piece of use.

Fourth, the project implementation steps, fund allocation, scheduling

1. Implementation steps and schedule of the project

In accordance with the principle of easy and difficult, combined with the local climate and financial situation, we must first invest in projects that are less effective and quicker, and try to avoid the rain commission, make full use of idle periods, and reduce crop damage.

Topographic map of the survey project area: year, month and day - year, month and day;

Prepare project detailed planning and design drawings and plans: year, month, day, year, month and day;

Verify the status of land ownership in the project area and formulate adjustment plans: year, month, day, year, month and day;

Project project bidding: year, month, day, year, month and day;

Completion of the preparatory work for the project: year, month, day, year, month and day;

Construction start-up of the project: year, month, day, year, month and day;

Filling and rebuilding the land and leveling the land: year, month, day, year, month and day; completing the earthwork of the grid and terraced fields, in line with the farming requirements.

Farmland water conservancy, field roads, other projects: year, month, day, year, month and day; construction of various types of roads and bridges and culverts, irrigation channels and drainage ditch, construction of ecological protection forests, supporting power projects, water storage and irrigation stations.

Completion acceptance: April 2019

2. Fund allocation

The total investment of the project country is 10,000 yuan, of which:

Construction cost: 10,000 yuan as a percentage of total investment

Equipment purchase fee: 10,000 yuan as a percentage of total investment

Pre-work expenses: 10,000 yuan as a percentage of total investment

Owner management fee: 10,000 yuan as a percentage of total investment

Unforeseen expenses: 10,000 yuan as a percentage of total investment

3. Measures taken by the project construction

3-1. Management system implementation measures

3-1-1. Implementation measures of the announcement system

The basic situation of the project is announced. 14 to 28 days before the implementation of the project, the name, total scale and scope of the project, new cultivated land area, construction period, land ownership, project undertaker, project construction unit, project supervision unit, project design unit, etc. The content is announced to the public.

Project bidding announcement. In order to improve the transparency of the project bidding work and ensure the quality and progress of the project, the county land development and consolidation center will decompose the project content one by one, make a tender announcement on the news media, and then open bidding to the public according to the bidding section of the Tendering and Bidding Law. Open, fair, fair and fair use of construction enterprises with qualifications of three or more levels within the province for bidding. In accordance with the quality of the project and the construction requirements, the bidding party shall formulate plans for the construction period, quotation and quality standards. Finally, the leading group of the county land development and consolidation project will select the winning bidding unit according to the following formula: Announcement-Registration-Preliminary Qualification Examination-Worksheet Answer--Construction Unit Bidding - public bidding - bidding review - determine the winning bidding construction unit.

The contents of the project bidding announcement mainly include the name and address of the bidder, the nature of the bidding project, the location and time of the quantity implementation, the method of obtaining the bidding file, the bidding method, and the bidding result.

Title management announcement. Before the implementation, the basic situation of land ownership in the project area and the land ownership adjustment plan shall be announced for 15 days in the township and village of the project area.

3-1-2. Implementation Measures for Project Legal Person Responsibility System

As a legal entity, the County Land Development and Consolidation Center implements full management and overall responsibility for each process of the project cycle.

Implementation preparation stage: Responsible for organizing project construction, bidding, selecting the construction unit and supervision unit, signing the contract, preparing the implementation plan and project progress plan, and formulating the project quality standards and related systems.

Project construction stage: Announce the announcement to accept the supervision of the local people, fulfill the obligations of legal persons, supervise and inspect the project construction unit and supervision unit to perform the contract, coordinate other issues, and do a good job in organization, information, statistics, and file management.

After the completion of the project construction task, the project project acceptance.

3-1-3. Implementation of contract management measures

In accordance with the relevant provisions of the "Contract Law" and other relevant organizations, the county land development and consolidation center, as the project implementation unit, signed the construction and project supervision contract with the construction unit and the supervision unit to clarify the rights and responsibilities of the three parties. The contract management is handled by a special person, and a special chapter for project contract management is set up. Other bidding contracts and equipment purchase contracts must be issued by the legal person. The settlement of contract disputes is handled in accordance with the procedures of the Contract Law.

3-1-4, implementation plan of bidding system

Organization and implementation of bidding: The county land development and consolidation center will work with the county construction project recruitment and investment center to propose a specific bidding plan, and the county land development and consolidation project leading group will be implemented after examination and approval. The County Commission for Discipline Inspection, supervision, auditing, and finance departments shall participate in the whole process of supervision of bidding, construction, and acceptance from beginning to end.

Bidding method: Open bidding, the bidding unit will issue bidding announcements through electronic curtain wall, TV station, newspapers and other propaganda media, and openly invite qualified construction enterprises to participate in bidding competition. Any construction enterprise that meets the specified conditions can voluntarily participate in the bidding.

The basic procedure for bidding for land consolidation project construction is: the tendering agency prepares the bidding archives or the pre-qualification files, issues the tender notice, issues the bidding archives, and then bids, opens the bids, evaluates the bids to determine the winning bidder, and signs the contract. No unit or individual may illegally interfere with the project construction bidding activities in any way.

Relevant content and specific requirements: The bidder must be qualified as an independent legal entity and a construction enterprise with a water conservancy level of three or above. For the project manager, the project manager above the second level, more than three years of construction experience and similar construction performance in the past three years. The bid opening process shall be recorded on the case, and the person in charge shall be clearly responsible. When the bid opening file is inspected according to the regulations, the public will be opened and read out. The bid evaluation shall be undertaken by the bid evaluation committee established by the bid inviting party according to law. The members of the bid evaluation committee shall be composed of the experts selected by the bid inviting party and the experts of the bid evaluation experts. The total number is singular for more than five persons, and the number of experts shall not be less than three thirds. two. The project adopts a fixed quotation, and the bidder sets the maximum price a of each bid. The quotation greater than or equal to the maximum price is an invalid quotation, and the quotation less than the maximum price is a valid quotation. Remove the highest value from all valid bid quotations and remove the minimum value of the arithmetic mean b. The bid evaluation base price c = ÷ 2 × k. If the bidder's quotation is the closest to the c value, the bidder is the winning bidder. If the bidder's quotation is close to the same degree, the bidder who is less than the c value is the winning bidder. When two or more bidders are listed in the same winning bidder, the winning bidder is determined on the spot. In order to ensure the progress and quality of the project, and pass the completion acceptance. The construction enterprise shall submit a 15% performance bond to the county land development and consolidation center according to the regulations, and the performance bond shall be passed through the entire project until the completion of the project warranty. The winning bidder may not subcontract by itself, and subcontracting is strictly prohibited, otherwise it is considered a breach of contract. The tenderee and the winning bidder sign the contract according to law.

3-1-5, work