Work report > implementation plan

On-site implementation plan for the development of green fish culture community


[According to] the fourth aquatic product work conference in the city---"The whole city's aquatic product processing and aquatic product development site meeting" will be held at the Hyatt International Hotel in Shashi from November 16th to 17th. The theme of the conference was to solve the processing bottleneck that plagued the sustainable development of the city's aquatic industry, and to speed up the development of the city's aquatic product processing industry. The meeting also focused on the deployment of aquatic products development this winter. As the organizer of the aquatic product development site, our district will set up the aquatic product development site in the 5000-mu green fish breeding community in Leihu Village, Jinan Town. In the past few days, under the direct leadership of the District Fisheries Work Leading Group, the main leaders of the Bureau of Jinan Town and Leihu Village have conducted a thorough and detailed investigation on the specific matters of the on-site meeting, and initially formulated the implementation plan.

First, the city's aquatic products will be arranged directly

The city's aquatic product processing and aquatic product development site meeting was initially scheduled to be held on November 17. The location is at the Hyatt Hotel, and about 140 people are responsible for the main responsible persons in each county and city. Seven buses are visited, and the duration is one day. In the morning, I saw 6 scenes involving Jingzhou Development Zone, Shashi District and Jingzhou District, including 5 aquatic product processing sites and 1 autumn and winter aquatic product development site. Afternoon meeting, four units typical speech, namely Honghu Deyan Company, Development Zone Daming Company, Jianli County Party Committee Government, and Jinan Town Committee Town Government.

On-site requirements for Jinan aquatic product development: excavation and intensive fish pond reconstruction and upgrading, the requirements of the scene should be large, that is, to carry out more than 500 acres of contiguous excavation and more than 1000 acres of contiguous dredging transformation, on-site construction machinery 15-20 sets It is connected with the development scene of winter and spring, forming a large excavation and transformation momentum; the standard is high, that is, the fish ponds, ditches, fish sheds, roads and trees along the site should be neat, tidy and completely new. The site visit time is 20-30 minutes.

Second, Leihu Community Development Plan

The total area of ​​development is 5,000 mu, of which 1000 mus of two intensive fish ponds are rebuilt and expanded, and 1,000 mu of slabs are rebuilt, and 3,000 mu of ponds are reconstructed. 4 hardening production roads total 10,000 meters, dredging gullies 10,000 meters, planting trees 10,000 meters, and implementing the "1115" herring main breeding mode to achieve an annual output of 5,000 tons of adult fish, an output value of more than 50 million yuan, and a net income of XX million yuan. the above.

Third, on-site construction engineering

It is planned to excavate 500 mu of contiguous pieces, and two new digging fish ponds will be connected before the scene meeting, and three fish ponds will be expanded to form a 200-mu excavation site.

It plans to dredge 1000 mu and reshape 3,000 mu. The site will be excavated next to the site to carry out four slabs of dredging to form a 200-mu dredging site.

It is planned to dig a trench of 10,000 meters. Before the on-site meeting, a total of 4,000 meters of dredging was completed for three ditches.

Completed the erection and refurbishment of the newly built 4000m cement production road.

Along the site visit line, about 1,500 meters long and 500 acres of fish ponds, all the plastics see new.

Fourth, the site layout

400 mu of contiguous excavation and dredging are carried out simultaneously, and more than 15 machines are operated at the same time;

On-site tree 10 event exhibition signs and 2 large fixed signs;

On the scene of the circle XX acres outside the insertion of 200 bunt flags;

Put 6-8 balloon slogans on the spot;

More than 10 crossing banners are hanged along the Jingzhou District;

There are no debris along the line, neat and tidy, and the related objects can be white and white.

V. On-site construction requirements

The dredging of three 4,000-meter ditches requires that the water in the ditch be full of weeds, that the ditch slopes should be new and smooth, and that the ditch should be straight and free of debris. It is required to complete 60% before November 10.

The excavation and reconstruction of the five fish ponds was fully started, requiring the new digging pond to be completed 50 cm deep and completed by November 10. On the day of the site meeting, there was no water in the pond for excavation and renovation. The site of the modified fish pond was gradually formed.

The dredging site requires that all four fish ponds be constructed without water, and the dredging rate will reach 20% or more. It will be completed before November 10, and at least four dredging machines will work on the spot.

The repair work of the shoulders is required to be completed by November 10th. The shoulder width is required to be 0.5 meters. There will be no debris on the roadside.

Along the 1,500-meter road along the route, 500 acres of fish ponds and pools are all plastic.

Leihu Community and the environment along the line. It is required to whiten the fishing shed and the wall of the house along the line. The front and back of the house are clean and free of debris, and the trees are neatly brushed white, which will be completed before November 10.

On the same day, the on-site meeting asked the Leihu Community to insert 200 bunting flags along the road of XX mu, with a spacing of 30-40 meters on each side.

Large horizontal banners and exhibition plates are placed on site.

1. Plate content: 1 Autumn and winter development site of Leihu Qingyu Culture Community in Jingzhou District. The request was placed in place two days before the on-site meeting. 2 Brief introduction to the plan and development of herring culture in Leihu Village, with a specification of 3 m × 6 m. The request is placed in place before November 10.

2. Contents of the exhibition: Introduction of Youxin Qingyu Cooperative, Qingyu District Qingyu Industry Planning, Autumn and Winter Aquatic Development Planning, Leihu Community Introduction and Development Planning, Catfish Development, and Leisure Fisheries. The specification is 0.5 m × 1 m. It is required to be placed in the morning on the spot.

Hang 6 crossing banners. Suspension location: Leihu Village Village Entrance, Leihu Community Turning Point, Newly Repaired Road Intersection, Newly-built Road North-South Direction, Return Turning, and the entrance of the Qingyu Market opposite the village committee. The specification is 0.7 m × 12 m. It is required to be put in place one day before the on-site meeting.

Placed with a promotional slogan balloon: 2 at Leihu Village and 4 at the scene. The promotional banner is vertical and the specification is 0.7m x 12m. It is required to be put in place on the morning of the scene.

200 printed spot guides. The contents include the introduction of Youxin Qingyu Cooperative, the planning of Qingyu industry, the development of autumn and winter aquatic products in the whole district, the introduction and development planning of Leihu Community, the introduction of squid production base, and the introduction of recreational fishery.

There are 4 banners along the road from Beimen Small Turntable to Leihu Village, which are hung in Xiaobeimen Turntable, Jianna Street, Youxin Qingyu Cooperative, and Jiudian Street.

6. Estimation of on-site capital investment

The demolition of the kiln chimney requires a capital of 15,000 yuan;

The compensation for the demolition of 3 houses is 35,000 yuan;

The compensation for land recovery losses is 165,000 yuan;

The new excavation of two fish ponds of 60 mu requires a capital of 126,000 yuan;

The finishing cost of a fish pond that has been dug is 10,000 yuan;

The compensation for dredging of the four fish ponds is 40,000 yuan;

It takes 80,000 yuan to dredge the 4,000-meter ditches;

4000 meters road shoulder soil, finishing funds need 60,000 yuan

The environmental rectification along the Leihu Village requires a capital of 50,000 yuan;

Promotional expenses of 80,000 yuan:

1. Make 10 banners for the crossing of the road banner;

2, red flag 200 face need funds of 0.6 million;

3. Do a large exhibition sign of 10,000 yuan on site;

4. It takes 0.5 million yuan to do the Qinghu culture and development planning card in Leihu Village;

5, to do double-sided cross-road signs need 20,000 yuan;

6, do 10 small exhibition cards 10,000 yuan;

7. Make 100 pieces of publicity materials for 0.3 million yuan;

8. Promotional balloons 6 yuan of 0.3 million yuan.

Other expenses: 20,000 yuan.

It is estimated that about 1 million yuan will be invested. Among them, the new excavation and renovation fund of the fish pond is about 200,000 yuan, which can be raised by the owner. The actual dredging cost is about 200,000 yuan, which is self-raised by the fishermen.

Seven, the problem that needs to be solved

Strengthen organizational leadership. According to the relevant opinions of the city, the on-site meeting requirements are high, time is tight, the workload and difficulty are very large, and it is necessary for the district committee and the district government to attach great importance to the establishment of a strong special class on-site supervision and coordination. The party committee and government of Jinan Town must make a full blow, Zhencun The main person in charge must conduct on-the-spot command and solve problems, and ensure that the quality and construction period will be organized on site.

Clear division of responsibilities. On-site project site and environmental remediation along the way, the party committee and government of Jinan Town are responsible for, and prepare the speech materials for the conference; the site materials, exhibition boards, banners, etc. are responsible for the work of the District Fisheries Bureau, and do a good job of communication, reporting and contact. Please arrange the relevant departments for the explanations along the territory of Jingzhou District.

Do a good job of fund raising. The initial estimated funds for on-site planning are 1 million yuan, including 900,000 yuan for engineering construction and environmental remediation, and about 100,000 yuan for propaganda materials, signs, and exhibits. Apart from the fishermen's self-raised 400,000 yuan, there is still a gap of about 600,000 yuan, and it is necessary to formulate financing channels.