Work Summary > Unit Work Summary

Summary of Urban Forest Engineering Work of the Bureau of Landscape Architecture


Summary of the situation of real city forest projects This year, the bureau implemented the urban forest project in the spring of this year according to the “Annual Implementation Plan for District Forest Projects”. The relevant situation is summarized below.
I. Urban Forest Project Construction This year, there are 6 urban forest projects under the responsibility of the bureau, with a total area of ​​151.4 mu, which is currently being implemented.
The first is the greening project of Bayue Avenue. The green area is about 85.5 mu, and the greening plan has been fixed. The main tree species are Tianzhugui and Chongyangmu. The tendering phase is being prepared and the project is scheduled to be completed in the second half of the year.
The second is the greening project of Jiujian Road. The green area is about 15 mu. The current greening plan has been finalized. At present, the comprehensive pipe network pre-buried land plan is being improved, and the greening project plan is completed in the second half of the year.
The third is the youth road greening project, the green area is 6 mu, and the main tree species are Tianzhugui and Huanggeshu. 80% of the workload has been completed and the project is completed by the end of the year.
The fourth is the greening project of the North Ring Road. The green area is 15 mu. The main tree species are Tianzhugui and Huanggeshu, which have been basically completed.
The fifth is the greening supporting project of section b of Xihu Avenue. The green area is 7.5 mu. The main tree species are eucalyptus, camphor, and Tiangui Gui, which have been completed.
Sixth, Shuangnan Road into the city entrance landscape green area reconstruction area of ​​10.4 acres, the main tree species are Guangyulan, crystal rose apple, purple magnolia, Ziwei and so on. 50% of the workload has now been completed.
II. Investment Overview The total investment for the six projects is RMB 19,048,700. Among them, Ba Yue Avenue is 12.375 million yuan, Jiujian Road is 2.5 million yuan, Youth Road is 600,000 yuan, Beihuan Road is 1.5 million yuan, and Shuangnan Road is a green land renovation of 6.25 million yuan.
III. Work Suggestions There are many urban forest projects and heavy tasks. In order to ensure the smooth implementation of various construction projects, first, the construction funds need strong support from the higher authorities. Second, in the development of specific work, it is necessary to strengthen the relevant departments. Mutual cooperation.

recommended article