[Legal Education Network] Our company plans to build a new building interior decoration project, in order to ensure the quality, safety and economic efficiency of the project, in accordance with the principles of openness, fairness and fair competition, according to the "Building Law of the People's Republic of China" and "The Chinese People" The Republic of China Bidding and Tendering Law, the Ministry of Construction of the People's Republic of China Order No. 89, Hunan Province implements the "People's Republic of China Bidding and Tendering Law" and other relevant provisions, and reported to the Municipal Planning Commission for approval, the project is proposed to use the form of open tendering, Choose the preferred construction team. The bidding conditions and bidding requirements of the project are as follows:

First, the project overview:

1. Project Name: ** Building Interior Decoration

2. Construction site: **路1#

3. The investment of the project is 17.0 million yuan. The nature of the investment: the unit is self-raised, and the funds already in place are 17.0 million yuan.

4, functional layout: See the decoration design and construction drawings provided by the owner.

5. The whole building decoration project of the engineering category.

Second, the scope of project bidding:

See the decoration design and construction drawings provided by the owner.

Third, the contracting method:

1. According to the relevant provisions of the "Tendering and Bidding Law", the project shall sign a contract between the construction party and the construction unit according to the winning bid price, the bidding period, the bid quality level and other provisions of the bidding document, and the relevant provisions of the Contract Law. Contracting methods for contract work, materials, contracting period and package quality.

2, the fee standard

2-1. Civil engineering: According to the current quota and its supporting fee collection standards, the material budget price will be executed* (price) [2002] No. 08; the fee collection standard will be implemented by Xiang Jian [1999] price word No. 296; manual adjustment The temporary adjustment coefficient was adjusted according to the text of No. 09 of [Jian Jianding [2001], and included in the pre-tax quotation; the construction site safety, civilized construction and occupational health increase fees were implemented in Jianding [2001] No. 011.

2-2. Installation project: According to the current fixed amount, the material budget price is executed at the current market price.

2-3. Decoration and decoration project: According to the current fixed amount, the material budget price will be implemented in the construction price [2002] No. 08, and the fee collection standard will be implemented in the Hunan Construction [1999] price word No. 296 and related supporting documents. .

1. The quotation of this project does not include the labor insurance pooling fund.

Fourth, the main material supply and quality requirements: the procurement of materials by the owners and Party B after joint inspection, with the consent of the owners and supervisors can be used.

V. Construction period:

The construction period of the project is determined according to the current national construction period quota and combined with the actual situation of the owner. The bidder can determine the bidding period according to his actual situation.

Sixth, project quality:

According to the current national construction acceptance specification and quality standards, the project quality must meet the engineering design and current specifications. When completed, it must be approved by the local quality supervision department and the quality level must meet the excellent standards.

Seven, the contract signing requirements:

1. The winning bidder shall not subcontract the project; if the subcontracting behavior is found, the construction management department shall investigate and deal with it according to the regulations. The construction unit shall submit the approval of the municipal bidding office, and shall have the right to select a top construction unit from the winning bidder. .

2. Sign the construction project construction contract in strict accordance with the relevant provisions of the State and the relevant requirements of the Contract Law.

3. Project settlement: The project will use the winning bid price as the basis for the settlement of the project price; the increase and decrease, as well as the changes in the fee collection standard and material budget price due to the change of national policy during the contract period, should be adjusted.

The settlement of this project is entrusted*****.

4. Disbursement of the project price: After the construction contract is signed, 10 days before the start of construction, 10% of the bid price will be paid in advance for the project preparation; thereafter, it will be paid monthly according to 60% of the Jianan workload actually completed last month.

When the project funds are allocated to 60% of the winning bid price, the disbursement will be stopped; the remaining 40% will be accepted and accepted by the project and meet the contract requirements, and will be paid within two years after the settlement of the project.

5. Liability for breach of contract and reward and punishment methods:

5-1. The project implements high quality and high price. If the project completion and acceptance is assessed as excellent project, it shall be rewarded with 2% of the bid price; if the quality grade fails to meet the bidding commitment, it shall be punished according to 2% of the bid price.

5-2. The project is required to be completed according to the successful bidding period; every time it is delivered or deferred one day in advance, it will be rewarded and punished according to the price of the winning bid.

5-3. If the construction project delays the construction period, the liquidated liquidated damages shall be paid to the construction party on the basis of two ten thousandths of the bid price.

Eight, the bidding instructions:

1. The bidder shall, when obtaining the bid invitation, pay the tender holder a guarantee deposit of 10,000 yuan.

2. After winning the bid and signing the contract, the bidder shall provide the tenderee with a bid performance guarantee contract to ensure that the bidder will sign and complete the bidding project according to the relevant provisions of the bidding documents once the bid is won; The bidder will be deemed to have refused to respond to the bidding conditions, and the bid bond will not be refunded.

2-1. Form of performance guarantee: cash guarantee.

2-2. Guarantee amount: In cash, the performance guarantee amount is 10,000 yuan, and the bid performance bond will be deposited in the bank account designated by the tenderer.

2-3. Validity period of performance guarantee: The validity period of the bid security is the approved construction period of the bidding project.

3. Project site survey and bidding questions:

3-1. The project will hold a bidding meeting at the city trading center at 16:00 on the **, **, and 2002, and organize site surveys.

3-2. The project will be questioned in the bidding at the city trading center at 09:00 on the day of the month of 2002. The bidders shall submit their opinions on the issues that are not clear about the invitation to bid and the construction design, and then the tenderee will reply in writing with the design unit.

4. The value of the bid price:

The upper limit of the bid price is ****.00 million yuan;

The lower limit of the bid price is ****.00 million yuan.

5. Preparation, sealing and delivery of tenders

5-1. Bids include business bids and technical bids.

5-2. The contents of the commercial tender include:

5-2-1, business standard A: the degree of resounding of the bidding file; the degree of competence and credibility; comprehensive explanation; the signature of the bidder and the legal representative; the list of the members of the project manager; and other files and certificates that need to be explained material.

5-2-2, business standard B: bid quotation, commitment form.

Bind the above information into a book, in one copy. Bidders and legal representatives in the bid quotation and commitment form must sign.

5-3. The technical tender is mainly the construction organization design; the project requires the bidder to provide the construction organization design in one copy; the requirements are as follows:

5-3-1. The chapter layout in the technical tender is produced in the following order and requirements:

First, the construction plan

Second, the construction schedule and guarantee measures

Third, quality assurance measures

Fourth, to ensure safety measures

V. Civilized construction site measures

Sixth, rationalization advice

5-3-2, cover: Receive a uniform cover style at **** Tendering Agency Co., Ltd.;

5-3-3, catalogue and title: the font is unified into the third imitation Song font;

Headline level one, two, three...

5-3-4, subtitle and text type are unified into the fourth imitation Song font; the subtitle and body content arrangement level is:

The second level 1, 2, 3, ...;

The third level 1-1, 2-2, 3-3...;

5-3-5, the table and the schematic diagram are the No. 4 imitation Song font, and the content font is unified to the No. 5 imitation Song font;

5-3-6, all fonts are standard fonts, no bold or inclined processing; CAD drawing according to drawing specifications;

5-3-7, technical tenders may not be arranged page numbers, no blank inserts may be left before and after;

5-3-8, the following technical indicators may not appear to help the review experts to see or appreciate the contents of the tender preparer: the name of the unit, the name of the person, the location of the unit, the telephone number and special marks.

5-3-9, typesetting requirements:

5-3-9-1, the line spacing is 1.5 times the line spacing;

5-3-9-2, no blank lines between chapters, no left and right indentation;

5-3-9-3, decorative content such as headers and shading is not allowed.

5-4. Business bids and technical bids are uniformly printed on A4 paper, black and white, and color pages are not allowed; forms and schematics are useful for A3 paper to be folded into A4 size binding, and there is no need to flip and reverse. Technical tenders must be printed on the computer and must not be written.

5-5. Sealing of business bids: The business standard A and the business standard B are respectively packed in the specified information bag and sealed with transparent glue. The cover of the data bag must not show any mark.

5-6. Sealing of technical tenders: The above-mentioned sealed commercial tenders, even the same type of technical tenders, are neatly folded, and then sealed with a prescribed wrapping paper and transparent glue into a large package, and the cover must not show any marks.

5-7. The bidder shall deliver the above-mentioned sealed bid to the construction project trading center of the city of ** before 09:00 on the date of the **.

Nine, bid opening, bid evaluation, calibration

1. The project is scheduled to open at 09:00 on the day of the month of 2002, at the construction project trading center of the city.

2. The bidder must attend the meeting: the legal representative or the legal representative shall entrust the agent to bid for the project manager of the project. The total number of each bidder shall not exceed 5;

3. All participants must attend the meeting on time and abide by the rules and disciplines of the bid opening site.

4. The following information must be submitted at the opening of the bid:

4-1. Original copy of enterprise qualification certificate and business license;

4-2, the legal person's certificate and the corresponding original ID card;

4-3. Project manager certificate, project technical person in charge certificate and corresponding original ID card;

4-4. Valid certificates and files of the administrative department of construction.

5. The evaluation method for this project is based on the comprehensive evaluation method in the No. 6 text of Jian Jian Zhao Zi [2002]. The scores and weights are shown in Schedule 1, Schedule 2, Schedule 3, Schedule 4, and Schedule 5.

6. The winning bidder of this project is determined as the method of winning the highest score according to the bid evaluation result.

X. In any of the following circumstances, the bid or bid qualification is invalid:

1. The tender is not sealed as required, and the official seal of the commercial tender is not stamped with the official seal of the unit;

2. If the technical tender is not printed as required, the technical tender is invalid;

3. The tender is not delivered to the city trading center as specified;

4. Two quotations appear in one bid book;

5. The bidder is late after the bid opening;

6. The legal representative of the bidder or its entrusted agent did not participate in the bid opening meeting;

7. The entrusted agent does not authorize the power of attorney to participate in the bid opening meeting;

XI. Other matters

1. After the bidder wins the bid, the bidding agency will receive the bidding notice issued by the bid inviting party and the municipal bidding office within 10 days; if the unsuccessful bidder requests reconsideration for the bid evaluation and the calibration result, Within 10 working days, a written request shall be submitted to the tenderee and the municipal bidding office, and will not be accepted after the deadline.

2. The winning bidder will sign the construction bid with the constructor within seven days and obtain the construction permit before entering the construction.

3. Matters not covered in this tender, in accordance with the "Building Law of the People's Republic of China", "Tendering and Bidding Law of the People's Republic of China", Order No. 89 of the Ministry of Construction of the People's Republic of China, and the implementation of the "Tendering and Bidding Law of the People's Republic of China" The construction of No. 394 file of Xiangjian Construction and the relevant provisions of the municipal government and the municipal construction department shall be implemented.

legal representative

Tenderer

The date of the year 2000

** City Construction Project Tendering and Bidding Management Office

The date of the year 2000