Fan Wen Daquan > Contract Model > Contract Model

About the subcontract contract for the construction and installation of the sintering cooling system


Employer: _________

Registered address:_________

Legal representative: _________

Attorney: _________

phone:_________

fax:_________

Postal code: _________

Bank of deposit: _________

account number:_________

Contractor:_________

Registered address:_________

Unit address: _________

Legal representative: _________

Attorney: _________

phone:_________

fax:_________

Postal code: _________

Bank of deposit: _________

account number:_________

Both Party A and Party B agreed on the construction of the sintering and cooling system construction and installation project within the scope of the sintering machine project, and signed this subcontracting contract for mutual compliance.

The first project overview

1.1 Comprehensive situation:

1.1.1 Project Name: Sintering Machine Engineering - Construction and Safety Engineering for Sintering and Cooling Systems.

1.1.2 Project Location: _________

1.1.3 Project Owner: _________

1.1.4 Construction content and scope:

Including sintering cooling chamber, machine head electric dust removal, main exhaust fan room and control room, electrical building, equipment assembly platform, circulating water pump station and pool, mixing and pumping station, mechanical and electrical equipment installation, material procurement, water supply and drainage, ventilation and dust removal, pressure gas And other engineering construction.

Construction of electrical, automated instrumentation, computer and communication engineering throughout the plant.

Construction of outdoor nitrogen, compressed air, steam, outdoor gas, natural gas pipelines, and dust removal pipe networks in the area.

The above-mentioned workshop and the whole plant three electric engineering single-unit test and air-load linkage test, and cooperate with the owner to carry out thermal load linkage test.

1.1.5 The main construction points and scope of the above construction and other Party B are: _________. Other unclear handover points, such as the site pipe network, shall be specified by Party A after the completion of the construction drawing design. The secondary grouting of all the equipment foundations that Party A has separately installed shall be the responsibility of the construction of the civil engineering structure of this subproject. Party A's equipment installation project and Party B's handover point shall be designated by Party A.

1.1.6 The project content of the specific subcontracting shall be determined according to the construction drawings and related instructions provided by Party A.

1.1.7 If Party B's work does not meet the contract requirements, Party A has the right to negotiate a contract with other construction units at any time, and designate the project and content that has not been designated or subcontracted by the contractor. Party B shall not obstruct, harass or dismantle the facilities and equipment belonging to the construction unit.

1.1.8 Party B shall be responsible for the commissioning and cooperation related to Party B during the construction.

1.1.9 There are a number of subcontracting units in this general contracting project. The problems of mutual cooperation and cooperation in the specific construction shall be resolved by Party B and the other party in consultation. If there are still problems, Party A shall jointly solve the problem.

1.2 Project quality and safety:

1.2.1 The materials and components used in the project must meet the current quality inspection standards of the country and the industry. The quality of the construction and installation project must meet the current quality assessment standards of the state and the industry. The environmental protection monitoring indicators should conform to the “Environmental Protection and Facilities Acceptance Monitoring Technology for Construction Projects”. Requirements "38) requirements.

1.2.2 Failure to meet the quality standards of the state and metallurgical industry, Party B shall be responsible for rectification, and the delays and expenses incurred by the project shall be the responsibility of Party B; the quality of the project shall not meet the quality standards of the State and the metallurgical industry, and Party A shall refuse to pay the quality of the Jian'an Project. Margin.

1.2.3 Party B is fully responsible for the safety problems in the construction of the project, and promises that the serious death, major fires and major equipment accidents caused by Party B due to Party B are zero, and the injury rate of 1,000 people is less than 1/1000. If there is a safety accident within the scope of construction of Party B, Party B shall bear all the responsibilities and expenses.

1.3 Project period:

1.3.1 The total construction period of this contract project is ______ days of calendar duration. On the _________ year _________ month _________ day, Party B must start work and complete the empty load linkage test to _________ _________ month _________ day and pass the test. The total duration of this contract includes the necessary time to meet the normal engineering requirements of other aspects.

1.3.2 The main construction period must meet the following control points and the duration of some of the contents that need to be completed in advance:

_________ Year _________ Month_________ Complete the basic construction of all sub-projects.

_________ years _________ months _________ completed the construction of the main civil works.

Equipment installation begins on _________ years _________ months _________.

_________ years _________ month _________ completed all construction and installation works, _________ month _________ day began a single machine test.

_________ years _________ month _________ days before the start of the empty load linkage test.

_________ years _________ month _________ days before the start of the heat load linkage test.

1.3.3 The major delays caused by the above-mentioned construction period except Party A's liability can be extended and no longer adjusted due to any factors. If Party A guarantees the total construction period and requires Party B to complete the construction ahead of schedule, Party B shall, according to the requirements of Party A, rush to work, and shall not increase the expenses.

1.3.4 Delay in the completion of key projects of critical lines due to Party B: Compared with the completion time determined by the network plan, the delay compensation for each delay of one week is one thousandth of the price of the delay, during the contract performance period. If the subcontractor takes effective measures to catch up with the delayed construction period, Party A shall reissue the deferred construction period delay compensation to Party B.

1.3.5 Delayed completion and completion time due to Party B: Compared with the completion and completion time of the contract, the delay in the first week after the delay of one week is equivalent to one thousandth of the total contract price. The delay in delay of one week’s loss is one-thousandth of a fifth of the total contract price.

1.4 Project price:

1.4.1 A comprehensive description of the list of project pricing items;

1.4.2 Civil engineering project pricing method, comprehensive unit price description and comprehensive unit price pricing list;

1.4.3 Installation engineering pricing method, comprehensive unit price description and comprehensive unit price pricing list;

1.4.4 Comprehensive coefficient valuation basis and comprehensive coefficient.

Article 2 Contract File and Order of Interpretation

2.1 The files that constitute this contract may be considered to be interpretable and explained, and the composition and interpretation of the priorities are as follows:

2.1.1 this contract;

2.1.2 Changes and agreements and agreements agreed upon by both parties;

2.1.3 Bidding files;

2.1.4 drawings;

2.1.5 Engineering specifications;

2.1.6 bidding files;

2.1.7 Other relevant files.

2.2 Party B shall keep a complete set of contract files, construction files, drawings, notices of change, other documents submitted or issued, and engineering specifications files on site. Party A has the right to use the above files at all appropriate times.

2.3 In any case, when the parties submit or issue a notice, order, consent order, approval, certificate or award in accordance with the provisions, the above-mentioned documents shall be in writing and shall not be detained or delayed without cause. All certificates, notices or written instructions issued by Party A to Party B, as well as all notices sent by Party B to Party A, shall be sent to the person for receipt and receipt of the written receipt.

Article 3 Engineering Specifications and Drawings

3.1 Engineering Specifications:

3.1.1 During the implementation of this project, the project owner and Party A will supervise and accept the contractor according to the current national construction and acceptance specifications. The requirements of this project meet the design and acceptance criteria.

3.1.2 The engineering content that must be carried out for the construction according to the current construction and acceptance specifications of the country has been considered in the contract price of the comprehensive unit price and comprehensive coefficient calculated by the engineering entity. In the implementation of the project, the contractor shall not increase the cost according to the acceptance specification.

3.1.3 The contractual requirements, design, project owner and Party A's actual situation of the instructions issued by Party B are inconsistent with the acceptance specifications, and are implemented according to the actual situation, and the project investment is not adjusted.

3.1.4 The division of the equipment and construction safety engineering of this project is based on the metallurgical industry regulations, namely, the stipulations of the Metallurgical Construction Engineering Equipment Technology and Materials Division No. 241, which is based on Party A’s construction drawing design. quasi.

3.2 Drawings:

3.2.1 This project is designed by Party A. After the project owner has approved the drawings, materials and alterations designed and provided by Party A, 4 of Party B shall be submitted as the basis for construction, and Party B shall strictly follow the construction. If there are more than 4 copies of the above files, Party B shall make copies at their own expense.

3.2.2 The standard drawings and standard designs promulgated by the countries and regions indicated in the design shall be provided by Party B.

3.2.3 The design drawings of this project shall be distributed by Party A in time according to the designation of each subcontracted project.

3.2.4 The preliminary design master plan, building list and process building system general plan section of the project are only used as reference materials for Party B's bidding, and there is no impact on the contract price due to differences between the project and the construction drawings. .

3.2.5 For any work within the scope of this contract, Party B shall not refuse construction for any reason or refuse to construct to request adjustment of the comprehensive unit price and comprehensive coefficient.

3.3 Design changes:

3.3.1 Design change: Refers to the design change that occurred with respect to the construction drawing of this contract.

3.3.2 Right to change: During the term of this contract, Party A may propose changes by directly issuing instructions or requesting Party B to submit proposals. Party B shall not make any changes or changes to this project without Party A's instructions or Party B's proposals without Party A's approval.

3.3.3 Party A's design changes shall be implemented immediately by Party B. The change in engineering quantity caused by the design change is calculated according to the provisions of this contract, but the comprehensive coefficient and the comprehensive unit price and construction period are not changed due to design changes.

Article 4 Party A’s Responsibility

4.1 Establish an engineering organization and entrust the representative of Party A to perform the duties stipulated in this contract.

4.2 Responsible for overall project management and organization and coordination, responsible for organizing project opening unions and engineering meetings.

4.3 Balance the funds, review the progress report of the project according to the time specified in the contract, and allocate the project payment.

4.4 The production equipment to be installed in the whole factory shall be provided by Party A. Party A is responsible for the quality of the equipment.

4.5 Provide 4 construction files such as construction drawings and design changes, 3 completed drawings, and corresponding design and construction services.

4.6 Provide Party B's right to enter and use the site. However, such access and use rights are not exclusive to Party B.

4.7 Responsible for handling Party B's business tax and additional withholding and payment.

4.8 Responsible for organizing the acceptance and delivery of Party B's projects.

Article 5 Party B’s Responsibility

5.1 The work completed by Party B shall be in full accordance with this contract and shall conform to the engineering design intent specified in this contract. This project shall include any works necessary to meet Party A's requirements or implied by this contract and arising from Party B's obligations. It shall also include this contract, although not stated, but may infer the stability, integrity or All the engineering necessary for safe, reliable and efficient operation. All workers, engineering equipment, materials, temporary works and other materials required for the construction, completion and repair of defects in this project, whether temporary or permanent, shall be provided by Party B at the expense of the responsible party. Party B shall clearly understand Party A's requirements before starting construction. Party B shall notify Party A of the incomplete or other defects in the found construction drawing requirements. After receiving this notice, Party A shall decide whether to correct it and send a corresponding notice to Party B. Regardless of whether Party A has approved or agreed, Party B shall bear construction responsibility for the completeness, stability and safety of all operations, all construction methods and all projects on site.

5.2 Party B promises:

5.2.1 The project is a key construction management project of _________, a company-level project management department is established and a deputy-level leader is appointed as the commander, responsible for project preparation and overall management.

5.2.2 Appoint an excellent project manager _________ as the project manager of the sintering project department.

5.2.3 The project manager has the right and authority to ensure the supply of materials and equipment, and the workers have normal income. Do not use funds to do other projects.

5.2.4 During the construction process, there will be no problems due to any problems, and the work will be stopped without the consent of Party A.

5.2.5 All the projects undertaken will be self-organized and not subcontracted.

5.2.6 If the time and quality of the contractual commitment are not met due to Party B's reasons, it is willing to accept the penalties specified in the contract and assume the relevant economic responsibilities of the owner to Party A.

5.2.7 Party B is willing to set up a large-scale concrete mixing station and meet the needs of the brother construction unit under the premise of self-operating. If the brother construction unit needs Party B to provide the price, the price is basically the same as that of the Handan Steel area. You can refer to the internal settlement method of _________ construction. The tax and the fee are coordinated by the general contractor.

5.2.8 Party B will maintain the authority of Party A and the owner, obey the command, listen to the audience, and work together with other participating contractors to take care of the overall situation. Proactively doing our own work will ensure the smooth, orderly and coordinated development of the entire project under the leadership of Party A.

5.2.9 During the construction process, _________ will frequently go to the construction site to actively seek the opinions of Party A and the owners, and supervise and honor the commitments of Party A and the owners.

5.2.10 Party B will set up a special account on the spot to make special funds, allowing Party A to inquire at any time. If it is used for other purposes, Party B will accept Party A's double fine for the amount of misappropriation funds.

5.3 Party B shall be responsible for coordination and proper construction with other aspects within the scope of the project, especially the _________ project. Party B shall, according to the requirements of Party A, provide construction site and water, electricity and gas for the work of other contractors involved in the project. Party B must obey Party A's overall coordination and management of all aspects of the project and actively cooperate with other aspects of the project.

5.4 Party B shall release, locate and measure according to the origin, baseline and benchmark elevation given by Party A. Party B shall correct the errors in the location, elevation, size or positioning of the project caused by Party B.

5.5 Party B shall be responsible for the interpretation of the basic data such as on-site hydrology and underground conditions obtained by itself.

5.6 Party B shall be responsible for solving the production and living facilities required for construction. Party B shall be deemed to have confirmed that the access road he has chosen is suitable and available for use. Party B shall be responsible for the maintenance of the access road and shall provide the road signs or direction signs that he considers necessary to guide his staff, workers and other contractors into the premises. Party B shall obtain the permission of the relevant authorities that may be required to use the above-mentioned approach roads, road signs and direction signs. Party A does not guarantee whether the above-mentioned approach road is suitable or not.

5.7 Party B has submitted the construction organization design and project progress plan in the bidding file according to the requirements of Chapter 2 of the bidding file, and clarified the bidding file. Within 10 days after the start of construction, Party B shall formally submit 5 copies of the construction organization design and project progress plan according to Party A's approval opinions and construction drawings of the above files. The preparation of the project's progress plan should use sorting network technology, marking the date of the earliest start, the latest start, the earliest end, and the latest end. Each time Party A requests, Party B shall provide in writing a general description of the work arrangements and methods to be adopted for the implementation of the project for inspection. Without notice to Party A, Party B shall not make major changes to the construction organization design, the project schedule or the above work arrangements and methods. If the actual progress of the project does not match the progress plan, Party A may instruct Party B to modify the progress plan and explain the contents of the modifications required to complete the work within the specified time limit.

5.8 Party B shall provide the relevant Party B equipment required to complete the project. All Party B equipment, once delivered to the site, should be considered as dedicated to this project.

5.9 Party B shall comply with the current national safety regulations and the safety rules and regulations of the owners during its on-site arrangement and on-site operation, and shall start the work from the site to Party A to receive the project. Party B shall provide:

5.9.1 Lighting, security and guarding of the project;

5.9.2 Temporary roads, sidewalks, guards that may be required for the convenience and security of the owner and occupier, the public or other personnel of the adjacent lot.

5.10 Party B shall take various appropriate measures to protect the environment inside and outside the site and limit damage or nuisance caused to people or property caused by pollution and other consequences caused by its construction operations. Party B shall ensure that the exhaust gas, surface drainage and sewage discharged from the site within the validity period of this contract shall not exceed the emission standards stipulated by the project owner and the emission standards stipulated by law.

5.11 Due to engineering needs, Party B has the right to use the electricity, water, gas and other public facilities available on site. Party B shall pay the project owner at the price specified by the project owner. The construction water and electricity consumption shall be calculated according to the price confirmed by the project owner, of which the construction water is _________ yuan/ton, and the construction electricity is calculated according to _________ yuan/kwh. Party B shall provide the instruments required to use the above-mentioned public facilities and measure the consumption, and bear the corresponding risks and expenses.

5.12 During the construction period of the project, Party B shall maintain that there are no unnecessary obstacles on the site, and Party B equipment or excess materials shall be properly stored and disposed of. Party B shall promptly remove and remove all residues, garbage and temporary works that are no longer needed from the site. Otherwise, Party A shall have the right to dispose of it without the consent of Party B. Once the receiving certificate is issued, Party B shall immediately remove and remove all Party B equipment, surplus materials, residues, garbage and temporary works from the part of the site and project involved in the receiving certificate. Party B shall keep the site and the project clean and safe, and Party A shall be satisfied. If Party B fails to transport all remaining Party B equipment, surplus materials, residues, garbage and temporary works in accordance with the above requirements, Party A may sell or otherwise dispose of the above materials, and Party B shall bear the expenses.

5.13 Party B shall abide by the state's laws on labor protection and shall not affect the progress and quality of the project due to these reasons.

5.14 Party B shall limit its operations to the work area where the site agrees to be the scope of its operations. Party B shall take all necessary precautions to ensure that its personnel and equipment are within the scope of the above-mentioned operation area, and to prevent and prohibit its personnel and equipment from encroaching on its neighbors.

5.15 Party B shall consult with Party A in advance when withdrawing the appointment of Party B representatives and key management personnel on site.

5.16 In principle, Party B is not allowed to replace the project manager by itself. If it is necessary to replace it in special circumstances, it should be entrusted to the same qualified person to replace it. It can be replaced only after being approved by Party A, and the replacement project manager's personnel fee is _________ million.

5.17 Party B shall use personnel who are skilled and qualified to have skilled skills and experience in their respective industries or occupations. Party A may request Party B to remove the personnel who work in the project and Party A believes that one of the following acts, including Party B's representative:

5.17.1 There are often errors in the work;

5.17.2 Incapable of performing their duties or neglecting their duties;

5.17.3 Failure to comply with the provisions of this contract;

5.17.4 Adhere to acts that are harmful to safety, health or environmental protection.

5.18 Party B shall take all reasonable precautions at any time to prevent illegal acts or social harassment within its employees or employees, and to maintain law and order, prevent such acts and personnel and property in the vicinity of the project.

5.19 Party B must organize the construction of the project by the first-level project department. Except for some civil works services that can be outsourced after Party A's permission, the project may not be subcontracted or subcontracted to other parties. Once Party A confirms that Party B has unauthorised subcontracting or subcontracting, it can correct it by means of correction within a time limit and fine. If Party B cannot make timely rectification according to Party A's requirements, Party A will have the right to terminate the contract. The resulting loss of construction period and expenses shall be borne by Party B.

5.20 At the project site, excavation of fossils, valuable cultural relics, etc., Party B shall immediately take appropriate precautionary measures to protect and notify Party A and the project owner.

5.21 Party B shall be responsible for handling all the formalities, such as leaving the factory for construction permit, safety, fire prevention, security, temporary residence, family planning, blasting, etc., and shall bear the expenses. For engineering spoils, follow _________.

5.22 Party B shall be responsible for handling the various types of water, electricity, steam, roads, etc. during the construction and carrying out the water and electricity at the construction site, and shall be responsible for the effluent at the designated location of Party A and bear the expenses.

5.23 Party B shall be responsible for the protection of underground pipelines at the construction site, and shall not jeopardize the adjacent buildings or structures, and the costs shall be agreed upon separately.

5.24 After the production equipment provided by Party A is delivered to the site, Party B is responsible for unloading, transshipment, cleaning, storage, etc. The cost is included in the installation unit price. Party B shall jointly count with Party A and then hand it over to Party B for management.

5.25 Party B shall be responsible for the delivery of the project and provide complete sets of completion data and 3 sets of as-built drawings. The completion of the completion of the transfer of materials shall be completed within the time required by Party A of the project owner. For each one month postponed, the construction cost shall be deducted _________ million.

5.26 The payment for the project is not handled in accordance with the contract, and Party B has the right to lodge a notice.

5.27 It is indeed a staff member of Party A who uses improper means to deliberately harass Party B's matters. Party B has the right to propose to replace Party A's staff.

5.28 Party B shall sign the Safety Management Agreement with the owner in accordance with the provisions of the owner and pay the safety performance bond to the owner in accordance with the agreement.

5.29 Party B shall arrange for the employment of all staff and laborers from the local or other places and shall be responsible for their remuneration, housing, meals and transportation. The wage standards paid and the labor conditions to be complied with shall not be lower than the current standards and conditions for similar businesses in the workplace. If no existing standards or conditions are applicable, the wages paid and the labor conditions to be complied with shall not be lower than the general wage standards paid by the business owners engaged in similar work and the labor conditions to be observed. Party B shall comply with the relevant labor laws applicable to its employees, and shall pay them reasonablely and protect them from all the rights stipulated by law. All employees are required to comply with all applicable laws and regulations relating to safe work.

Article 6 Supervision and inspection of project quality

6.1 The owner of the project entrusts the supervision company to be responsible for quality inspection of the construction. Party B shall accept the quality supervision and inspection of the project owner, supervision company and Party A.

6.2 During the construction of the project, the project owner and Party A shall have the right to supervise and inspect the progress, quality and other aspects of the project. Party A may issue relevant design changes and instructions according to the actual conditions of the project, or make a decision to stop work, rectify and terminate the contract according to the construction conditions of Party B, unless it can not be implemented according to the natural law, Party B shall strictly enforce it.

6.3 Party B shall establish a quality assurance system to demonstrate that it can comply with the requirements of this contract. Compliance with this quality assurance system does not relieve Party B of its duties, obligations and responsibilities. The subcontractor shall submit to the Employer 10 days before the commencement of construction of any unit project the construction organization design material certificate, the experimental report, the special type of work permit concrete, the mortar matching and other notices, and fill out the inspection form, and issue the package. Party newspaper supervisor and owner. Before the start of each construction phase, Party B shall submit the details of all programs and execution files to Party A for inspection. When submitting any of the above files to Party A, a signed quality statement of the file should be attached. Party A has the right to review any aspect of the quality assurance system and has the right to request corrective action.

6.4 The engineering materials required for the construction of the cost project shall be purchased by Party B in addition to the request of Party A for further entrustment. Party A has the right to notify Party B to stop using the raw materials, semi-finished products and equipment that do not have a certificate of conformity.

6.5 The subcontractor shall purchase the main construction and installation materials and shall be certified by the general contractor for the qualification of its suppliers.

6.6 The project owner proposes that the 砼 mixing and conveying must be set on the site to set up a large 砼 mixing station or use commodity 砼, and pump it to the pouring point, Party B should follow the implementation, and the difference that may occur relative to the on-site mixing 砼It is included in the comprehensive unit price and comprehensive coefficient, and is not adjusted.

6.7 Party A has the right to participate in the inspection, inspection or testing of the quality of the works and materials in accordance with the regulations. Party B shall provide conditions to Party A to inspect, inspect, measure or test the works and materials on site or at other work sites. The expenses shall be borne by Party B.

6.8 Party B shall promptly notify Party A before the construction project is ready to be covered or masked. Party A shall conduct inspection, inspection, measurement or test in time with the main representative, without undue delay; or notify Party B that it is not necessary to carry out the above work. If Party B fails to issue a notice in accordance with the above requirements, Party B shall, when requested by Party A, remove the cover on the above project and then restore it to its original condition at the expense of Party B.

6.9 If Party A requires other tests in addition to the construction specifications, Party B shall be responsible for providing all the files and other materials necessary for the above tests, and shall also provide the workers and materials required for the effective implementation of the above tests. , electricity, fuel, test supplies, test equipment and instruments, meters, etc. If the test is qualified, the expenses shall be borne by Party A; otherwise, Party B shall bear the responsibility.

6.10 If Party A determines according to the results of inspection, inspection or test that the quality of a project or material is unqualified, Party A may reject the above-mentioned project or materials, and shall immediately notify Party B and explain the reasons for the rejection. Party B shall immediately repair the defects and ensure that the rejected items are in compliance with this contract. If Party A requests to re-test the quality of the above-mentioned projects or materials, then these tests shall be carried out according to the original test conditions. If the test is re-qualified, the costs shall be borne by Party A; otherwise, Party B shall bear the costs.

6.11 When all projects and materials are delivered to the site and payment has been made equal to the price of the relevant works and materials, the property rights shall be owned by Party A.

6.12 After completion of the project, Party A shall cooperate with the owner, supervisor and Party B to conduct the acceptance assessment of the project quality. Party B shall send the results and relevant completion data to Party A for review and submission to the owner for archival purposes.

6.13 The test report of the construction raw materials and semi-finished products shall be provided by a qualified quality inspection center or supervision station.

6.14 In the event of a major quality accident, Party B shall notify Party A in writing within 24 hours, and timely organize a quality accident investigation and analysis, and submit a handling opinion and report it to the relevant department for the record.

Article 7 Project Acceptance and Warranty

7.1 Completion acceptance is based on construction drawings, specifications, design changes, construction acceptance specifications and quality standards issued by the state and the metallurgical industry.

7.2 Completion acceptance:

7.2.1 After the completion of all or part of the construction of Party B, it is responsible for organizing the single-machine test and the no-load linkage test. After the test drive is qualified, the three parties signed the "No-load Linkage Test Certificate".

7.2.2 The project owner is responsible for organizing the load linkage test, and Party A and Party B participate together. Party B is responsible for providing driving operation services. During the test run, if there is a problem such as construction that belongs to Party B, Party B shall handle and bear the expenses. After the load linkage test is qualified, the project owner, Party A and Party B jointly signed the “Load Link Test Certificate”.

7.2.3 All or part of the project has the conditions for completion acceptance. Party B will provide the project owner with three sets of complete completion data and completion acceptance report in accordance with the relevant provisions of the national project completion, and in three months. Three sets of as-built drawings are provided. After receiving the completion acceptance report, the project owner shall promptly organize the relevant departments to accept the inspection, and give approval or propose amendments after acceptance, and Party B shall make modifications as required. After the modification is passed, Party A will accept the inspection. After the acceptance, the performance certificate will be signed, and the completion acceptance report will be approved. The project has passed the acceptance test.

7.3 The project warranty period shall be implemented in accordance with the provisions of Article 40 of the State Council Order No. 279 from the completion of the completion acceptance.

7.4 If the accident occurs due to the construction quality during the warranty period, Party B shall be responsible for repairing and bearing the expenses.

Article 8 Project Cost Payment

8.1 Within 30 days after the contract is signed, Party B's personnel and machinery will be stationed at the construction site and officially started. Party A shall pay Party B an advance payment of _________ million yuan. From the month when Party A pays Party B all the money reaches a certain amount, Party A shall deduct the project advance payment from Party B's progress payment in three months according to the average amount.

8.2 From the commencement of the project, Party B shall submit the project budget book in accordance with the list of contracted project pricing items to Party A for review. Party B shall actively cooperate with Party A's audit work, and the approved project budget shall be deemed as project payment and project settlement. The basics. Party B shall prepare a monthly progress report in accordance with the approved project budget, in three copies, and submit it to Party A before the 25th of each month. Each progress report should include:

8.2.1 The signing of the construction quality and progress of Party A's construction management personnel;

8.2.2 Report on the progress of the image of the construction;

8.2.3 The investment income meter of this paragraph calculated according to the construction drawing and the contract price calculation method;

8.2.4 Payment application form.

8.3 Party A shall verify Party B's statement by the 15th of the next month, issue a project payment certificate and pay. Party B shall actively cooperate with Party A's review work.

8.4 15% of the monthly project investment approved by Party A is the reserved warranty, which is deducted from the payment certificate for each project. Before the project is completed and accepted, Party A will pay 85% of the total settlement price. After the completion and acceptance of the project is completed and the heat load test is completed, it will be paid for 10% within one week. After the expiration of the warranty period, the balance of the settlement part of the premium will be paid within 5% within one week.

8.5 Within 3 months after the project is completed and accepted, the two parties shall complete the completion settlement.

8.6 During the warranty period, due to quality problems caused by Party B's quality, Party B shall provide free warranty.

8.7 If Party B fails to meet the construction plan, quality requirements or does not follow the instructions of Party A, Party A has the right to unilaterally adjust the above payment plan.

8.8 Party B's business tax and surcharge shall be withheld and paid by Party A in each payment, and Party A shall provide Party B with a tax payment certificate.

8.9 Awards and penalties:

8.9.1 Reward: According to the completion of Party B's construction, Party A may give certain rewards to the content of the project that is satisfactory.

8.9.2 Penalties: If Party B does not perform the contract or does not complete the subcontracted project for various reasons, Party A may impose a double fine according to the scope and content of its actual impact on the project.

8.9.3 Fees for awards and penalties are paid for in the engineering payment for the next month's project.

Article 9 Force Majeure

9.1 Determination of force majeure: according to the relevant regulations of the state or provincial competent department.

9.2 If force majeure occurs, Party B shall promptly take measures to minimize the loss and notify Party A of the damage within 24 hours.

Article 10 Performance Guarantee

10.1 Party B shall provide Party A with a performance guarantee letter issued by its bank within 6 days after the signing of the contract.

Article 11 Disputes

11.1 The dispute shall be settled by negotiation between the two parties.

11.2 In the event of litigation, it shall be accepted by the people's court where the project is located.

Article 12: Entry into force and termination of the contract

12.1 This contract shall become effective after it has been signed and sealed by both parties.

12.2 If the project owner and Party A confirm that Party B is unable to complete the project in accordance with the contract period and quality requirements, the project owner and Party A have the right to terminate this contract, and the losses caused by Party B shall be borne by Party B.

12.3 This contract shall terminate from the date of full completion of the work, except that 8.4 is valid.

12.4 After Party A pays the full amount of the project, the relevant warranty terms are terminated by themselves.

12.5 Matters not covered in this contract shall be settled through negotiation between the two parties.

12.6 The original of this contract is two copies, which are separately kept by Party A and Party B; 12 copies are made, and 6 copies are for each of Party A and Party B.

person A person B:_________

Party A's representative: _________ Party B's representative: ______

_________Year ____________________________________________

Place of signing: _________ Signing location: _________

Subsidiary file

A comprehensive description of the list of project-related projects

1. The list of project pricing items should be used in conjunction with the contract conditions and format.

2. This comprehensive description is used together with the list of engineering valuations, which are mutually explained and together constitute the project price calculation file for this contract.

3. The settlement and payment to Party B shall be based on the amount of work actually completed according to the construction drawing, and the actual project investment will be obtained by multiplying the actual project quantity by the contract price.

4. The list of project pricing items is a fixed price, which is not adjusted due to changes in the actual conditions of the project.

5. Party B confirmed that the site situation has been fully understood and grasped, and various problems and measures that may occur during the construction have been fully predicted, and these factors have been taken into account in the bid price.

6. Party B confirmed that the site conditions, the project content and the layout of the general plan, the situation, characteristics, difficulty level, and construction period requirements of the large-scale sintering project have been fully understood and grasped, and the comprehensive engineering content of the comprehensive unit price and comprehensive coefficient has been A full estimate has been made and these factors have been taken into account in the bid price.

7. In the implementation of the project, each project is set at a certain contract price, and similar projects are applied at similar contract prices. The contract price is deemed to contain the cost risk that may be caused by the difference between similar projects.

8. The list of project pricing projects is divided into two major parts: civil engineering and installation engineering. Civil engineering and installation engineering are divided into three types: fixed fixed unit price, combined coefficient according to quota, and actual cost plus adjustment fee and tax. The preferred usage relationship between the three pricing methods is:

8.1 Pricing by fixed comprehensive unit price: The items included in the comprehensive unit price item are applied according to the same.

8.2 Calculating the comprehensive coefficient according to the quota: For the items not included in the comprehensive unit price project, the civil works and decoration works shall be applied according to _________, and then calculated by means of comprehensive coefficient. When applying the above quotas, only the quota direct fee portion is calculated. The "management fee" portion of the _________ provincial construction, decoration, and installation quota shall be included in the quotation of the comprehensive coefficient, and shall not be calculated.

8.3 In the implementation of the project, if the above two methods are not applicable, the civil works and installation works shall be calculated according to the following principles: the manual, material and mechanical work required for the actual construction of the project confirmed by Party A. The actual cost of the project is calculated by the consumption and the corresponding price, and then the engineering investment is determined by the method of calculating the fee and the normal tax according to the provisions of _________. The labor unit price and material price are based on the current market price of construction, installation and municipal engineering materials issued by the _________ city construction project cost management station. The price of the mechanical station is executed at the price of _________, and the insufficient part is consulted by Party A. The price is determined.

9. The engineering investments calculated according to the above three pricing methods have included:

9.1 All fixed direct costs, other direct fees, on-site management fees, temporary facilities fees, enterprise management fees, financial expenses, environmental protection measures, safe and civilized construction measures, night construction fees, secondary handling fees, concrete and Reinforced concrete slabs and brackets, scaffolding, completed engineering and equipment protection fees, construction drainage and precipitation fees, engineering insurance warranty fees, rushing measures, budgetary levies, labor insurance, construction waste, freight, profits, all fees, Various local taxes and fees, detailed design fees for steel structures, construction fees, fixed management fees, and taxes calculated according to regulations.

9.2 The market price of labor, materials and machinery classes may change during the whole process of project construction.

9.3 Equipment or the main material purchased by Party A shall be unloaded, transferred, and discharged from the site, unpacked, inspected, cleaned, and stored until transported to the construction site.

9.4 Changes in various unforeseen factors such as changes in engineering geological conditions and changes in external conditions.

9.5 Except for the tenth in this article. In addition to the provisions of the paragraph, the use of large machinery in the construction of the entrance and exit fees, installation fees and the use of the desk fee; due to poor space, obstacles, trenches, pits, etc. caused by the increase in equipment, materials, equipment, etc. Handling, assembly and disassembly work; slag, sand, stone, roadbed, etc. laid for transportation equipment and equipment; fixed bolt frame required for foundation construction; pumping of cast-in-place concrete; and other necessary construction measures. Except as otherwise agreed by the parties in the contract price, no construction measures are charged.

9.6 The content of price difference, labor, materials and machinery consumption may change due to different engineering.

9.7 Due to the owner's suggestion, the mixing and conveying of the crucible must be set on the site with a large concrete mixing station or the use of commodity crucibles, and pumped to the pouring point, the difference that may occur relative to the on-site mixing crucible.

9.8 Possible policy adjustments and special local charges.

9.9 All risks and responsibilities in terms of construction period, owner's special requirements, design, safety and losses caused by various reasons.

9.10 The vertical transportation fee is included in the corresponding comprehensive unit price and is not separately calculated.

9.11 Contents to be included in other terms of this tender file.

10. Additional construction costs that are allowed to be calculated in civil works and installations include:

10.1 The difference between the construction hoisting machinery of more than 30 tons approved by Party A and the construction hoisting machinery in the original contract unit price according to the reasonable construction organization design;

10.2 According to the reasonable construction organization design, the tower cranes approved by Party A shall enter and exit the entrance fee, installation fee and basic fixed fee.

In addition, other construction measures are included in the quotation of the comprehensive unit price and the comprehensive coefficient, and are not calculated.

11. The actual price of the use of special materials shall be determined by Party A in the course of project implementation.

12. When calculating the engineering investment, if there is a material price difference, the price difference will only be calculated as normal tax, and no other expenses will be calculated.

13. If there is any doubt about the contract price in actual use, Party A's explanation shall prevail.

14. The items included in the comprehensive unit price project do not represent the contents of construction or construction of Party B, and are constructed according to the construction drawings and related instructions provided by Party A. When Party A entrusts part of the construction and safety work such as the installation of certain buildings and equipment within the scope of the contract to other units designated by Party A for construction, the comprehensive unit price in this contract shall not be adjusted, and no construction coordination fee and comprehensive management fee shall be paid.

15. If Party B fails to perform the contract or fails to complete the subcontracted project for various reasons, Party A may impose a double fine according to the scope and content of its actual impact on the project.

16. Party B shall purchase the main civil engineering and installation materials and shall obtain the certification of Party A's qualifications for its suppliers. The owner of the project supplies part of the steel at a fixed price, and the price is based on the attached file VII. Party B shall submit the procurement plan to Party 15 on the 15th in advance. After Party A's approval, Party B shall purchase the goods at the owner's office according to the progress. Party A shall charge 5% of the purchase management fee for each purchase price. The purchase price and procurement management expenses are deducted from the payment of the project payment according to the progress of the project payment. In the project settlement, the purchase price of this part of the material will be offset.

17. If the equipment provided by Party A has non-technical production defects such as transportation deformation, Party B shall agree to accept the treatment. The processing fee of each equipment shall not exceed _________ yuan, and Party B shall not calculate the processing fee. If the amount exceeds this amount, it shall be calculated according to the consumption of verified labor, materials and machine power, and then the fee and business tax and surcharge shall be calculated.

Attachment file 2 civil engineering construction pricing method and comprehensive unit price description

1. The amount of engineering: based on the construction drawing design, design change and on-site visa, the engineering quantity is calculated according to the engineering quantity calculation rule of the comprehensive unit price of the attached table.

2. Comprehensive unit price pricing method:

2.1 Comprehensive description:

2.1.1 The work content of the comprehensive unit price sub-project of the civil engineering project, including the work content included and not included in the description of each unit price sub-item of the relevant quota of _________ province, that is, including the sub-item meeting the design requirements and related All construction processes.

2.1.2 Unless otherwise stated, the unit price will not be adjusted.

2.2 The list of comprehensive unit price sub-headings of civil works is detailed in Appendix 1.

2.3 Calculation program: civil engineering cost = ∑

3. Comprehensive coefficient valuation method: In the implementation of the project, if it does not apply to the comprehensive unit price, it will be calculated according to the following principles:

3.1 Quantity: Calculated based on construction drawing design, design changes and on-site visa.

3.2 Quota: In principle, the civil engineering project is calculated on the basis of the fixed direct fee of ____________, and the comprehensive coefficient reported in the four attached files is calculated.

3.3 Comprehensive coefficient: Calculated according to the provisions of the attached file IV.

3.4 Calculation program: civil engineering cost = engineering quantity × fixed direct price base price × comprehensive coefficient.

4. Several adjustments to the above two pricing methods:

4.1 In the construction drawing design, the mortar mix ratio and the 砼 strength grade and subproject engineering content are not consistent with the comprehensive unit price. Calculate the difference according to the corresponding mix ratio and strength level in _________, and then calculate the comprehensive coefficient. .

4.2 The material of the steel is poor. The steel material according to the design can be compared with the steel material q235b. The difference is determined by the price difference after the quotation, and then the comprehensive coefficient is calculated.

4.3 The construction drawing design with the unit project as the calculation object can adjust the steel content exceeding ±10% of the content of the expanded comprehensive unit price, and ≤±10% will not be adjusted. The difference can be adjusted to calculate the composite coefficient. If one party to the contract proposes to calculate the amount of steel used in a unit of work, it shall provide a standard calculation of the amount of steel used. The accounting for it is carried out after the completion of other settlements of the unit project. During this period, no adjustments will be made to the payment of the project, and neither party to the contract may affect the smooth progress of the project.

4.4 Where the height of the building is more than 20m, it shall be calculated according to the corresponding sub-item of the super high building increase fee in the comprehensive unit price. However, the detachment of the super-high scaffolding and the vertical transportation machinery are not counted.

5. Valuation method for special circumstances: In the implementation of the project, if the above two methods are not applicable, the following principles are used:

5.1 Quantity of work: The physical consumption of labor, materials and mechanical work required by the construction confirmed by Party A.

5.2 Unit price: labor unit price and material price In principle, according to the current latest construction, installation and municipal engineering materials market information price promulgated by _________ city construction project cost management station, the mechanical desk fee is executed at _________ price, insufficient Partially determined by Party A's inquiry.

5.3 Calculation program: civil engineering cost = ×

Attachment file three installation engineering pricing method and comprehensive unit price description

1. The amount of work is calculated based on the construction drawing design, equipment nameplate, design change and on-site visa. The amount of work is calculated according to the calculation formula of the comprehensive unit price of the attached unit.

2. Comprehensive unit price pricing method:

2.1 Comprehensive instructions

2.1.1 The work content of the comprehensive unit price of the installation project shall be included and not included in the descriptions of the “National Unified Installation Project Budget Quota”, namely: unloading, unloading, and field when the equipment arrives at the site. Internal transfer, unpacking, inspection, cleaning, oiling, storage; qualified installation and commissioning of all equipment and materials, equipment unit test, record and on-site cleaning, and responsible for all construction processes, test records and test of empty load linkage test Cooperate with the load to test the vehicle and repair, match and change the work.

2.1.2 In addition to the above, the work content of this comprehensive unit price includes:

a. Acceptance of equipment foundation, shovel surface, trimming of anchor bolt holes;

b. The protective paint color common topcoat required according to the paint requirements and safety regulations required by the design requirements;

c. Construction fee and necessary measures fee confirmed by the bidder.

2.1.3 Installation includes all the processes and contents related to the sub-item and vertical transportation, horizontal transportation, ultra-high increase fees, high-rise building increase fees, mechanical equipment entry and exit and necessary scaffolding.

2.1.4 Unless otherwise stated, all installations include the main material fee. For the comprehensive unit price of the main material, the main material price must be reported.

2.1.5 Electrical small appliances are suitable for the installation of small safety transformers, instruments, electric flutes, power buttons, limit switches, relays, terminal boards, fuses, knife switches, transfer switches, small transformers, etc.

2.1.6 The measuring unit "table" of the instrumentation equipment is calculated and determined according to the number of one-time instruments of the process inspection point.

recommended article

popular articles