Year-end summary of the mechanics workshop in 2019


1. Technical transformation completed 108 technical transformation projects throughout the year, with a total output value of 3,351,700 yuan and a project commission of 557,100 yuan, including 7#, 8# blast furnace bag dust removal, ore tank safety and post-reconstruction projects of 20,281,100. Yuan, iron and steel plant new coal injection project 1,745,100 yuan, furnace material plant 200,000 tons / a lime project 3,705,200 yuan, 265 sintering machine electrical installation project 345,000 yuan, second plant second phase project 5,245,700 yuan, sintering plant logistics return The large-scale technical transformation project of the mine project is 2,118,900 yuan, 265 sintering machine head electrostatic dust removal transformation 2.85 million yuan.
2. In the aspect of maintenance, 1432 sets of electrical equipment such as electric motors and electric welding machines of various main factories were repaired throughout the year;
In the whole year, the company completed a large-scale overhaul of the company three times, a total of 24; repair
9 items; 1412 items for daily maintenance of each branch: 628 items for power plant daily repair, 4282 for oxygen plant, 44 for furnace material factory, 210 for quality inspection and supply, and 210 for iron and steel plant The painting was overhauled 8 times and the sinter plant was 4 times.
3. In terms of spare parts and spare parts processing, the company completed 46,622 daily spare parts processing, including 5,759 steelmaking plants, 16,270 h-shaped steel plants, 9,892 iron-making plants, 6,390 sintering plants, and 2,354 rolling mills. , more than 3,600 anchor bolts in the infrastructure, and 6,157 emergency spare parts processing in each main factory;
Repair and process 29,450 rolls of various types of rolling mills, and repair more than 70 steel drums of various tonnages.
4. Finishing and scrap recycling In the period from February to December this year, a total of 10,976 tons of h-beam finishing tasks and 1,050 tons of scrap steel recycling tasks were completed, which ensured the completion of production tasks.