Chapter 1: General

Article 1: In order to implement the principle of “safety first, prevention first”, thoroughly eliminate the phenomenon of “violating the rules, operating illegally, and violating labor discipline” and ensuring the realization of the overall safety production target for the current year.

Article 2: Main objectives of safe production

1. No major or major accidents occur;

2. There is no accident in which the agricultural and electrical workers are seriously injured;

3. There is no accident of electric shock and death in rural areas;

4. Eliminate power transmission and substation accidents;

5. The distribution accidents are not issued by the supermarket bureau;

6. No fire accidents, responsible traffic accidents and boiler pressure explosion accidents;

Article 3: Division of accident responsibility

1. The person responsible for the accident and the responsibility of the leader of the accident unit and the relevant personnel;

2. In the event of a major or major accident, the agricultural and electric power workers shall be responsible for the accidents of serious injuries and the accidents of electric shock and casualties in rural areas, and shall be held accountable for the party, government, and industry leaders and the safety production committee;

3, sending, substation and 10kv line accidents caused by equipment, biotechnology chief, special responsibility, in charge of the director has a certain responsibility;

4. In the event of an accident in the low-voltage power grid, the squad leader, the director of the power supply, and the director in charge of the responsibilities have certain responsibilities;

5. Due to poor management, it will cause accidents to the employees of industrial enterprises, investigate the director of the power supply department, the responsibility of the chief of the marketing department and the relevant personnel, and the responsible director has certain responsibilities;

6. The accident of the unit safety officer is not in place, and the responsibility of the safety officer is investigated;

7. Man-made accidents caused by illegal operations:

1) Failure to strictly carry out training and assessment according to regulations, and investigate the responsibility of the competent director and relevant departments;

2) Without safety and technical pre-job training, the personnel will be assigned to the agricultural power production position or exchange jobs, who will be responsible for who will be responsible;

3) The electrician working on the equipment in the system network of the Karamay Banner Agricultural Power Bureau did not participate in the annual “Safety Regulations” assessment of the safety supervision department, and investigated the responsibility of the department head, the safety supervision personnel and the in charge of the department;

8. Units that have fire accidents and theft accidents, and hold the responsibility of security personnel and leaders in charge;

9. Responsible traffic accidents occur, and the drivers, unit heads and supervisors are held accountable;

10. A general assessment accident occurs, and the safety record is terminated. In addition to investigating the relevant responsible persons, the competent department and the responsible director are also held accountable;

Article 4: Division of responsibility for jurisdiction of electrical equipment

1, 66kv transmission line routing Xingda company is responsible;

2. The substation equipment biotechnology department is responsible;

3, 10kv distribution line, 0.4/0.2kv low-voltage line, distribution transformer station, managed by each power supply;

Chapter II: Penalties for violations and violations

Article 5: Division of violations and violations of discipline

1. It is necessary to investigate the responsibility of those who violate the rules and regulations;

2. Investigate the responsibility of the unit according to its severity;

3. The inspection of safety inspectors is not in place, not strict or not, and does not deal with violations of disciplines and disciplines seriously, and investigates the responsibility of safety inspectors;

Article 6: Units that cannot effectively control violations or violations of disciplines, and give the units responsible for demotion

Minute

Article 7: When one of the following violations is committed, the administrative punishment shall be given to those who violate the rules and regulations, and the person in charge of the unit and the relevant personnel shall be given an economic penalty of 300 yuan, and the annual safety award of the unit shall be deducted.

1. Violation of the rules;

2, with the ground wire closed;

3, with load pull knife brake;

4, the wrong pull switch;

5, mistaken into the charging interval;

6, charged ground wire;

7, mistakenly boarded live equipment;

8. Stop and send electricity when the time is up;

9. Misdirected or misdirected orders;

10. Work on electrical equipment and lines does not perform work permit procedures;

11. Power outages, multiple lines on one line and live lines nearby. The line names and pole numbers of all the operating points have not been carefully checked beforehand. The competent person in charge is not arranged, and the safety measures are not complete.

Article 8: When one of the following habitual violations occurs, the violation of the rules and the relevant personnel 200/times of the yuan economic punishment

1. Hearing the power failure of the superior line or the system power failure, do not apply for the work ticket, and see the sewing pin to work without authorization;

2. Use a steel tape measure and a metal ruler to measure or align the charged equipment;

3. The staff should remove the grounding wire in advance without leaving the work site.

4. The power-off operation of pulling the branch switch does not use the work ticket;

5. If the work ticket is not approved, the staff member will enter the construction site to go to the pole or do other preparatory work;

6. If you do not check the line name and the pole number before boarding, you will blindly board the pole;

7. The person in charge of the work has completed the finalization of the work, but the members of the work class have not completely withdrawn from the work site or are still working;

8. If the report is not submitted, the equipment that does not meet the requirements of the Regulations or has serious defects shall be put into operation;

9. The electricity inspection is not serious. If there is no electricity or induction electricity, it will be blindly operated without careful analysis;

10. The dispatcher will resume power transmission without the permission of the dispatcher;

11. Unauthorized expansion of the scope of work tickets;

12. After the work ticket is filled in, the work ticket issuer will issue the certificate without detailed review of the work tasks and security measures;

13. The person in charge of work, the guardian of work and the safety inspector acquiesce in the scene or do not stop illegal operations and unsafe acts;

14, unlicensed driving or random car, drunk driving;

Article 9: When one of the following habitual violations is committed, the relevant personnel shall be given a financial penalty of 150 yuan/time.

1. Drinking or drinking after work during work;

2. Seat work does not use seat belts;

3, high-altitude operations do not use the transfer rope, just throw items or tools;

4. The work site does not strictly implement the safety measures listed in the work ticket. For example, the grounding wire should be connected only to the corresponding short circuit, even without the grounding wire and the electroscope;

5, the work has been approved, but the person in charge of the work does not carry a work ticket, indiscriminate command at the scene;

6. The lines erected on the same pole, working in parallel with the electric line, should be set up by special personnel without being set up;

7, high-altitude operations, felling trees should be guarded by special personnel;

8. When the work is resumed every other day, the work will not be checked if the safety measures are in good condition;

9. There is no unified password for large-scale operations such as poles, tight lines, and pay-off lines.

10. After the pole is set up, the pole equipment and the temporary cable are removed and the pole is put into operation without waiting for the backfill to stratify and compact;

11. The person removes the line on the pole by suddenly cutting the wire;

12. Working through the live line and the tight line without taking safety measures;

13. The analog board indication does not match the field operation wiring method;

14. Do not perform the simulation operation carefully before the operation, and do not carefully check the device name and number;

15. The operating personnel handed over to the sloppy, unclear and unclear, and did not arbitrarily adjust the class or class without the consent of the director or the leader;

16. The relay protection automatic device exits without permission;

17. Dispatching and changing the duty of the staff on duty, leaving the post;

18 At the end of all maintenance work, the operating duty personnel shall remove the safety measures and resume the power transmission without checking the acceptance;

19. After all the overhauls have been completed, the tools are left on the equipment.

20, equipment cleaning, switching

Personnel should be guarded during operation and not set up;

21. Conduct electrical maintenance tests under unsupervised conditions;

22, the high-voltage test site does not have a fence, no signboard, no guardianship;

Article 10: When one of the following habitual violations occurs, the party and the relevant personnel shall be given a financial penalty of 100 yuan/time.

1. Do not fill in the work ticket before the operation, and fill in the work ticket after the operation;

2. The person in charge of the work left the site without temporarily appointing competent comrades to undertake or not to notify all members of the work class;

3. The work task cannot be completed according to the plan time of the work ticket, and the person in charge of the work cannot handle the work permit extension permit procedure in time;

4. The person in charge of the work is allowed to participate in the work if the members of the work class temporarily joined in the work have not given the safety precautions and safety measures;

5. The installation of the temporary cable should not be installed during the construction;

6. The grounding wire is not installed in accordance with the requirements of the Regulations;

7. The person in charge of the work does not confess the on-site safety measures to the members of the work class;

8. The equipment inspection is not serious. The important defects are not discovered in time, and are not registered after the discovery. There is no record after eliminating the defects;

9. Use the insulating rod to pull the knife gate or pull the knife gate through the transmission mechanism without wearing insulated gloves;

10. Do not wear insulated gloves when installing or removing the grounding wire;

11, rainy day operation outdoor high-voltage equipment does not wear insulated boots;

12, the installation and removal of the grounding wire does not use insulation rods;

13. High-voltage electroscope does not wear insulated gloves;

14. Non-workers enter the switchyard, high-voltage room, and control room of the substation, and the on-duty personnel do not stop it;

15. The production of electric power and the entry and exit of children in the workplace are unrestricted;

Article 11: When one of the following habitual violations occurs, the party and the relevant personnel shall be given a financial penalty of 50 yuan/time.

1. Enter the building and do not wear a helmet at the high-altitude operation site;

2. Work on the tower, hang the helmet on the tower or use it as a kit;

3. The door to the high pressure room is not blocked;

4, patrol the power distribution device, the high pressure room does not close the door;

5. The patrol equipment and lines are not carried out according to the specified time;

6. After the operation of the split circuit breaker, the actual position of the split action is not checked at the site;

7. The hanging position of the signboard does not conform to the actual situation on site;

8. The line branch switch is powered off, and the signboard of “The line is working, prohibiting the closing” is not suspended after the switch is opened;

9. The contents and signature of the work ticket are unclear;

10. There are unqualified work tickets and operation tickets;

11. Agricultural power production and management personnel have no special operation certificates, and do not take the initiative to participate, and participate in electrical work;

12. The unlicensed electrician operates in the system power grid;

13. Use copper wire, aluminum wire and other metal wire instead of fuse;

14. The lighting line is not inspected after inspection, and the fire line and the neutral line are incorrectly connected;

15. Electrical equipment that should be protected and grounded is not reliably grounded;

Chapter III: Penalties for accidents

Article 12: Accidents of major and major accidents, and serious accidents of agricultural and electrical workers

1. The administrative person responsible for the accident shall be dismissed from the administrative position of the public office, and the leader of the accident-generating unit shall be given administrative sanctions for dismissal, and at the same time, the above-mentioned personnel and relevant personnel shall be given financial penalties of 500-1000 yuan each;

2. Give administrative responsibility for the demotion of the responsible person of the responsible management department, and give the responsible person and relevant personnel 200 yuan in economic punishment;

3. The punishment of the bureau-level leader shall be reported to the higher authorities in charge;

Article 13: Accidents causing electric shock and casualties in rural areas

Causing a liability accident, causing the bureau to suffer direct economic losses of more than 10,000 yuan;

The person responsible for the accident shall be dismissed from the retained period, and only the basic salary shall be paid during the period of retention, and 5% of the economic loss shall be punishable;

Giving the person in charge of the accident unit the administrative disposition of the dismissal of the position;

The person in charge of the responsible management department and the relevant personnel shall be fined 200 yuan;

The main leaders of the party, government, and industry, and the director in charge of the bureau, were fined 100 yuan;

Article 14: Other assessment accidents, fire accidents and responsible traffic accidents, boiler accidents, deductions for accidents are 500 yuan, and the person in charge of the deduction is 200 yuan. The management of the competent department is not in place, and the responsible person and relevant personnel are given 100. Yuan fine, giving the in charge of the director a fine of 100 yuan

Chapter IV: Assessment Requirements for Safety Production Work

Article 15: Safety production work is assessed once every six months

Article 16: When one of the following circumstances is found during the assessment, the security bonus of 20% of the unit in charge shall be deducted

1. The safety production files and notifications of the superiors were not implemented and no records were made;

2. The safety work tasks arranged by the superior are not completed;

3. Spring and autumn inspections and 100-day safety activities have not been planned, arranged, summarized, and evaluated.

Defects are not handled in time;

4. Classes and groups fail to carry out weekly safety activities as required;

5, did not carry out examination and explanation, technical questions and answers, anti-accident exercises, etc. according to the regulations, superior inspection

Not qualified

6. The monthly safety meeting, quarterly safety analysis, semi-annual and annual safety work summary did not work;

7. Should participate in the safety and technical training organized by the bureau. Some people are absent from the exam.

Passed personnel;

8. It is necessary to report the safety work text materials and various reports that have not been reported in time;

Chapter IV: Penalties for safety inspectors failing to meet their standards in place

Article 17: After receiving a large-scale construction notice, the safety inspector cannot track the on-site inspection, and the fine is 50 yuan.

Article 18: The safety supervision personnel must conduct regular inspections of the "two votes" as required, and fail to check the safety supervision personnel for 20 yuan according to the regulations.

Chapter 5: Awards

Article 19: All units do not have an assessment accident throughout the year, and statistical accidents are controlled within the indicators issued by superiors. When there is no violation of regulations, all units at the bureau level issue safety bonuses.

Article 20: Give rewards of 200-500 yuan to those who are able to avoid extraordinary or major accidents in time.

Article 21: For large single project projects exceeding 100,000 yuan, no violations or accidents have occurred, and 1% of the safety bonuses are awarded to the relevant personnel in the project.

Article 22: No safety award in any of the following circumstances

1. Units and personnel who have been punished by accidents during the year;

2. Units with more than two habitual violations during the year;

3. Persons who violate the relevant provisions of these Regulations;

Article 23: When a habitual violation occurs within one year, the penalty for the person in charge of the unit is 30%, and the safety bonus for the violation of the rules is 50%.

Chapter VII: Supplementary Provisions

Article 24: The rewards and penalties of these Measures are simultaneously carried out with the assessment of the security risk mortgage, and the rewards and punishments are repeated.

Article 25: Safety management of fire prevention, traffic, and boilers shall be formulated by the office, and shall be responsible for implementation, inspection, assessment, and assessment of the situation.

Article 26: These Measures shall apply to the Agricultural Power Bureau. If there is any conflict with the provisions of the higher level, the above provisions shall prevail.

Article 27: The assessment of these Measures shall be undertaken by the Bureau of Safety Production and the Safety Supervision Section, and shall be interpreted by the Bureau of Safety Production of the Bureau of Administration.