Emergency treatment and rescue plan for collapse and collapse accident


Emergency treatment and rescue plan for collapse and collapse accident

project name

the term

Responsible

Editor

Reviewer

Approver

date

First, the purpose

In order to effectively prevent accidents from expanding, reduce the risk of employees' lives, and minimize economic losses, this plan is specially formulated.

Second, the organization and responsibilities

The emergency response headquarters will be set up by the project department to be responsible for command and coordination.

Team leader:

Members: , , , , , ,

The specific division of labor is as follows:

1. Responsible for immediately organizing personnel to rescue the wounded.

2. Responsible for organizing personnel to carry out landslide treatment.

3. Responsible for immediate contact with the hospital, labor and other departments, explain the location of the accident, the accident situation, and send people to the intersection to meet.

4. Responsible for the dispatch of on-site materials and vehicles.

3. Emergency measures for collapse and collapse accidents

5. The emergency rescue command should be reported immediately after the accident.

6. Excavate the buried wounded and get out of the danger zone in time.

7. Remove the wounded mouth, nose mud, clots, vomit, etc., and pull out the comatose's tongue. It is expected to suffocate.

8. Perform simple dressing, hemostasis or simple fracture fixation.

9. Resuscitate the injured person who has stopped breathing or heartbeat.

10. Get in touch with the 120 Emergency Center as soon as possible, explain the location and severity of the accident, and send someone to the intersection to meet.

11. Organize personnel to relieve heavy object pressure as soon as possible, reduce the occurrence of casualty crush syndrome, and transfer it to a safe place.

12. If there is a fracture, it should be sent to the hospital immediately after being easily fixed with a splint.

13. Foundation pit:

1) Strengthen drainage and precipitation measures;

2) Strengthen the support and support the pile plate, etc., and strengthen the weak links of the slope;

3) Rapidly transporting heavy objects such as spoil, spoil, materials, machinery and equipment;

4) Eliminate part of the slope and slow down the slope.

14. In the absence of personal injury, the person in charge of the site shall study the remedy according to the actual situation and organize the restoration of normal construction order under the premise of ensuring the safety of the personnel.

15. The on-site safety officer shall analyze the cause of the collapse of the construction equipment such as the footwork, derrick, tower crane, etc., formulate corresponding corrective measures, carefully fill out the casualty accident report form, accident investigation, etc., and report it to the Group Emergency Rescue Leading Group.

Fourth, emergency supplies

Standing medicines: disinfection supplies, first-aid items and all kinds of commonly used small splints, stretchers, hemostatic bags, oxygen bags.

V. Communication

Hospital Rescue Center: 120 匪 Police: 110 Fire Alarm: 119

Site site duty phone:

The person in charge calls:

Project leader: Mobile:

Security Officer: Mobile:

Technical leader: Mobile:

Six, matters needing attention

1. Construction should be stopped immediately.

2. Pay attention to the buildings or equipment around the foundation pit.

3, artificial chest external heart compression, artificial respiration can not easily give up, must adhere to the end.