Secretarial knowledge > Emergency plan

Flood control and emergency prevention and rescue plan


Flood control and emergency prevention and rescue plan

project name

the term

Responsible

Editor

Reviewer

Approver

date

First, the purpose

During the encounter with the sorghum period, strong typhoon and heavy rain "three brothers", the construction site will be able to resist the anti-riot and anti-riot storms, minimize economic losses and ensure personal safety. Actively do a good job in the early implementation of flood prevention and prevention work, actively prepare for disaster relief materials, ensure the safety of the construction site, and specially formulate emergency treatment and rescue plans for flood control and prevention.

Second, the organization

The project department set up an emergency rescue command team for flood control and prevention, responsible for command and coordination.

Team leader:

Members: , , , , , ,

1. Rescue team and material list

Repair team

Repair detachment

2. Rescue sacks only

3. Mud pump platform

4. Lead wire kg

5. Control box only

6. Wood cube

7.

8. Car

Third, the responsibility

1. Responsible for the preparation, management and distribution of anti-hazard materials and equipment on site.

2. Responsible for collecting information and notices of typhoon warnings during the flood season, arranging on-duty personnel, organizing and convening rescue teams.

3. Responsible for organizing safety inspection and prevention work before flood season, typhoon and heavy rain.

The first group: total responsibility, high-rise tower cranes, scaffolding, material hoists, construction lifts on the construction site;

Specifically responsible for the high-rise tower cranes;

Responsible for the construction of the lift;

Responsible for the material hoist;

Responsible for scaffolding works;

Responsible for the cantilever steel platform;

Responsible for the entrance of the hole, the protection of the edge, and the pile of the high-rise side;

Responsible for all kinds of safety passages and anti-fall sheds;

Responsible for cement warehouse

The second group: is responsible for the waterproof drainage of the civil air defense basement and the sewerage of the site;

The third group: is responsible for temporary power consumption, distribution boxes for various parts, and on-site support for rescue materials;

The fourth group: Responsible for the office area, living quarters, and logistics life support.

4. Hazard rescue procedures caused by flood season, typhoon and heavy rain, implemented according to other duties

1. In the event of an electric shock, perform an emergency response and rescue plan for electric shock accidents.

2. In the event of a collapse or collapse accident, the emergency treatment and rescue plan for the collapse and collapse accident shall be implemented.

3. If there is a fall from a height, perform an emergency treatment and rescue plan for a high fall accident.

V. Relevant communication addresses

1. Telephone management department:

2. Engineering Management Department Tel:

3. Project Manager: Mobile or Phone

Project Deputy Manager:

Project Engineer:

Security officer:

Construction Worker:

Material Equipment Officer:

Supervision Department Management Department Tel:

Local Safety Production Supervision Bureau Tel:

Local safety supervision station phone:

Local flood prevention and prevention department telephone:

Attached to the nearby hospital address:

Industrial accidents refer to the catalogue of featured hospitals